Registration approved No litigation declared Residential/Group Housing project

THE POEM BY SHRIRAM PROPERTIES

By SPL PALMS DEVELOPERS PRIVATE LIMITED

RG-KA-75417 · RERA PRM/KA/RERA/1251/309/PR/210319/004033 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • 8 complaints at RERA Karnataka
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
Mar 2027Possession promisedmoved 12 months from the original
0 of 17Construction stages donefurthest along: Earth work and other leveling..., 90%
0 of 660Units unsoldnot recorded sold or booked
8Complaints at RERA Karnatakaon this registration
Jump to the 119 documents Report an error

THE POEM BY SHRIRAM PROPERTIES is a Residential/Group Housing project by SPL PALMS DEVELOPERS PRIVATE LIMITED in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/309/PR/210319/004033 on 19 Mar 2021. Possession is promised by 31 Mar 2027. The completion date has moved by 12 months from the original filing. 660 of the 660 units on this registration are recorded sold or booked, and 0 of 17 construction stages are filed complete. 8 complaints are on record with the regulator.

At a glance

Project

  • NameTHE POEM BY SHRIRAM PROPERTIES
  • TypeResidential/Group Housing
  • Location
    • Bengaluru North
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/309/PR/210319/004033
  • ReraGenie IDRG-KA-75417

Builder

  • NameSPL PALMS DEVELOPERS PRIVATE LIMITED
  • Entity typeCompany
  • CINU70100KA2013PTC068447
  • Authorized SignatorySUNIL CHOWDARY
  • DirectorSUNIL CHOWDARY

Key dates

this monthRegisteredMar 2021First promiseMar 2026Revised toMar 2027

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on19 Mar 2021
  • Promised completion31 Mar 2027
  • Revised completionRevised to 31 Mar 2027 (originally 31 Mar 2026)
  • Buildings6 building records
  • Documents filed119 files

Current status

100%660 of 660 units booked
0.2%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower-1---1140114
Tower-2---1080108
Tower-3---1080108
Tower-4---1080108
Tower-5---1140114
Tower-6---1080108

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 17 construction stages are filed complete. The stage furthest along is Earth work and other leveling preparation work, at 90%.

Building: 34% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work90%
Foundation footing work80%
Retaining wall (All types)50%
Plinth level Beam90%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)60%
RCC or MS Framed structure60%
Masonry construction: Bricks, Concrete blocks etcNot applicable
Plastering inside , outside & Ceiling40%
Joinery: Doors, Windows, Ventilators etc40%
Basic work of Water supply, Sanitary and Electrification40%
Dadoing, Skirting, Flooring, Tiles work (All types)0%
Railing and Grill fixing0%
Electrification, Water supply and Sanitary Finishing20%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network0%
Weather Proof work(tile,concrete)0%
Painting0%
Elevation work0%
Internal and External work including landscapes as per santioned drawings0%

Progress on shared amenities41

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes0%
Internal Roads & FootpathsYes0%
Sewage and Drainage SystemYes0%
Parks & Tree plantingYes0%
Street LightingYes0%
Provision for community buildings and for treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes0%
Water conservationNoNot applicable
Energy managementYes0%
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesYes0%
Electricity supply transformer and substationYes0%
Emergency Evacuation servicesNoNot applicable
Storm water drainsYes0%
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterYes0%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseYes0%
Community HallYes0%
Outdoor Sports facilityYes0%
Indoor Sports facilityYes0%
Swimming PoolYes0%
GymYes-
ParksYes-
Power BackupYes-
GasNoNot applicable
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes10%
LiftsYes0%
Staircases and Lift lobbies, corridor,lobbies, corridorYes0%
Fire escapesYes0%
Common entrance and exit for the building / common portico/foyer/verandahYes0%
BasementYes0%
TerraceYes0%
Outer WallYes0%
Open parking areas and common storage spacesYes0%
Provision for lodging of management staff and security staffYes0%
Water conservation and renewable energyYes0%

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area25,456 sq m
Named landowners1
LandownerVillageDistrict
SUVILAS REALITIES PRIVATE LIMITED--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 196.88 cr
Cost incurredRs 47.23 lakh
Spent of the estimate0.24%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 105.28 crRs 37.26 lakh
Principal sum and interest payable to financial institutions-Non Banking financial institution (NBFC)Rs 54.91 cr-
On site expenditure - salaries on workers,onsite overhead,cost of services and consultants feesRs 36.69 crRs 9.97 lakh

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDesign Desk
EngineerMANOHAR CONSULTANTS

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EX/PRM/KA/RERA/1251/309/PR/260422/004033Mar 2026 → Mar 2027

Reason as filed by the promoterothers

Complaints filed with RERA Karnataka8

Case no.ComplainantRespondentFiled
CMP/210912/0008322-SUVILAS REALITIES PRIVATE LIMITED12/09/2021
CMP/220531/0009555-SUVILAS REALITIES PRIVATE LIMITED31/05/2022
CMP/220719/0009767-SUVILAS REALITIES PRIVATE LIMITED19/07/2022
00369/2023-SUVILAS REALITIES PRIVATE LIMITED23/03/2023
00531/2023-SUVILAS REALITIES PRIVATE LIMITED21/04/2023
00758/2023-SUVILAS REALITIES PRIVATE LIMITED16/05/2023
00902/2023-SUVILAS REALITIES PRIVATE LIMITED05/06/2023
00949/2023-SUVILAS REALITIES PRIVATE LIMITED21/06/2023

Documents filed119

As listed on the registration, under the names the promoter filed them with; the newest 80 of 119 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/309/PR/210319/004033 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form-4 The Poem Sep'26F.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form-5 Architect (QU) POEM Q1 2026-27-DD.pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form-6 Engineer (QU) POEM Q2 2026-27.pdf15 Oct 2026
Q2 2026-27 Water supply and sewage board15 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Oct 2026
Q2 2026-27 KSPCB- MOEF (Above 50 Acres)15 Oct 2026
Q2 2026-27 KPTCL- BESCOM15 Oct 2026
Q2 2026-27 Fire and Safety15 Oct 2026
Q2 2026-27 Airport Authority of India15 Oct 2026
Q2 2026-27 BSNL/Telecommunication Department15 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form-4 The Poem June'26_Signed 1.pdf15 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form-5 Architect (QU) POEM Q1 2026-27-DD.pdf15 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form-6 Engineer (QU) POEM Q1 2026-27.pdf15 Jul 2026
Q1 2026-27 Water supply and sewage board15 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Jul 2026
Q1 2026-27 KSPCB- MOEF (Above 50 Acres)15 Jul 2026
Q1 2026-27 KPTCL- BESCOM15 Jul 2026
Q1 2026-27 Fire and Safety15 Jul 2026
Q1 2026-27 Airport Authority of India15 Jul 2026
Q1 2026-27 BSNL/Telecommunication Department15 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form-4 The Poem March'26.pdf14 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form-5 Architect (QU) POEM Q4 2025-26-DD.pdf14 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form-6 Engineer (QU) POEM Q4 2025-26.pdf14 Apr 2026
Q4 2025-26 Water supply and sewage board14 Apr 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)14 Apr 2026
Q4 2025-26 KSPCB- MOEF (Above 50 Acres)14 Apr 2026
Q4 2025-26 KPTCL- BESCOM14 Apr 2026
Q4 2025-26 Fire and Safety14 Apr 2026
Q4 2025-26 Airport Authority of India14 Apr 2026
Q4 2025-26 BSNL/Telecommunication Department14 Apr 2026
Engineering LicenseFile: Engineer-4-Self attested copy of Engineer License.pdf11 Mar 2026
Form-5 For work completionFile: Form Ex5-Engg certificate - work Completed- The Poem.pdf11 Mar 2026
Form-6 For work pendingFile: Form Ex6- Engg certificate - work pending- The Poem.pdf11 Mar 2026
Latest ECFile: Poem -ECC-26022026-10794471 upto-26-02-2026.pdf11 Mar 2026
BESCOM NOC AffidavitFile: BESCOM Noc Affidavit.pdf11 Mar 2026
BWSSB Noc AffidavitFile: BWSSB Noc Affidavit.pdf11 Mar 2026
List of sold & unsold unitFile: List of sold & unsold units.pdf11 Mar 2026
Latest Fire NOCFile: Poem - Fire NOC.pdf11 Mar 2026
Latest AAI NOCFile: AAINOC.pdf11 Mar 2026
Latest BSNL NocFile: BSNL Approval.pdf11 Mar 2026
Latest KSBCB NOCFile: KSPCB NOC.pdf11 Mar 2026
BESCOM NOCFile: BESCOM NOC.pdf11 Mar 2026
BWSSB NOCFile: BWSSB NOC Modified.pdf11 Mar 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form-4 The Poem Dec'25.pdf6 Feb 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form-5 Architect (QU) POEM Q3 2025-26-DD.pdf6 Feb 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form-6 Engineer (QU) POEM Q3 2024-25.pdf6 Feb 2026
Q3 2025-26 Water supply and sewage board6 Feb 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)6 Feb 2026
Q3 2025-26 KSPCB- MOEF (Above 50 Acres)6 Feb 2026
Q3 2025-26 KPTCL- BESCOM6 Feb 2026
Q3 2025-26 Fire and Safety6 Feb 2026
Q3 2025-26 Airport Authority of India6 Feb 2026
Q3 2025-26 BSNL/Telecommunication Department6 Feb 2026
Bank StatementFile: Bank Account - PALM RERA Account.pdf5 Mar 2021
CA UDIN number Balancesheet FY 2019 - 2020File: Balancesheet_FY 2019 - 2020_With UDIN.pdf5 Mar 2021
CA UDIN number Profit and Loss Statement FY 2019 - 2020File: Profit and Loss Statement for_FY 2019 - 2020_With UDIN.pdf5 Mar 2021
CA UDIN number Cash Flow Statement FY 2019 - 2020File: Cashflow Statement_FY 2019 - 2020_With UDIN.pdf5 Mar 2021
Civic Amenities Sanctioned PlanFile: Civic Amenities Sanctioned Plan.pdf5 Mar 2021
CertificateFile: Certificate of Incorporation.pdf-
Architect Certificate for Work Completion Schedule till DateFile: Form Ex1-Arc certificate - work completed-The Poem-DD.pdf-
Engineer Certificate for Work Completion Schedule till DateFile: Form Ex5-Engg certificate - work Completed- The Poem.pdf-
CA Certificate for Funds UtilizationFile: Poem Extention- Fund's Utilization.pdf-
Architect Certificate for Pending Work Completion Schedule.File: Fom Ex2- Arc certificate - work pending-The Poem-DD.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: Form Ex6- Engg certificate - work pending- The Poem.pdf-
CA Certificate for Funds required for Project CompletionFile: Poem Extention- Fund's Required.pdf-
AffidavitFile: Form EX-7.pdf-
Latest Encumbrance CertificateFile: New EC FOR POEM.pdf-
Details Of Sold/ Un-sold UnitsFile: Poem- list of sold & unsold units.pdf-
BBMP Approved Building Plan-
Approved Development Plan From BDA-
Proforma For Sale Deed-
Proforma of Agreement for Sale-
Sale Deed SY No 20 21 22 and 29 and SY No 60_3-
Data To Be Received-
Area Development Plan Of Project Area_BDA Work Order Dated 11052020-
Allotment Letter-
Shriram Suvilas Palms_Brochure-
Specifications and Amenties_Shriram Suvilas Palms-
EC From 01042004 To 17022021-
Section 3(1) Notarized Affidavit-

How this compares with Bengaluru Urban

100%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one moved by 12 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep THE POEM BY SHRIRAM PROPERTIES on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: SPL PALMS DEVELOPERS PRIVATE LIMITED

SPL PALMS DEVELOPERS PRIVATE LIMITED has 1 registration on RERA Karnataka, including THE POEM BY SHRIRAM PROPERTIES. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if THE POEM BY SHRIRAM PROPERTIES is delayed beyond 31 Mar 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of THE POEM BY SHRIRAM PROPERTIES?

The registered promoter entity is SPL PALMS DEVELOPERS PRIVATE LIMITED, a company as per the filing. Its CIN U70100KA2013PTC068447 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in THE POEM BY SHRIRAM PROPERTIES?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against THE POEM BY SHRIRAM PROPERTIES?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at THE POEM BY SHRIRAM PROPERTIES?

The professionals named in the filing: Architect: Design Desk; Engineer: MANOHAR CONSULTANTS. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in THE POEM BY SHRIRAM PROPERTIES?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About THE POEM BY SHRIRAM PROPERTIES. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save THE POEM BY SHRIRAM PROPERTIES to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.