Home / Browse projects / Bengaluru Urban, Karnataka / The Magic Faraway Tree Phase 2

Registration approved Litigation declared Mixed Development project

The Magic Faraway Tree Phase 2

By Total Environment Building Systems Pvt Ltd

RG-KA-09841 · RERA PRM/KA/RERA/1251/310/PR/171015/000424 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • Litigation declared, 1 case
  • 3 complaints at RERA Karnataka
  • Completion date moved by 45 months
  • 3 extensions taken

Clear

  • Separate project account declared
Sep 2027Possession promisedmoved 45 months from the original
3 of 17Construction stages donefurthest along: Masonry construction: Bricks, 96%
17 of 240Units unsoldnot recorded sold or booked
3Complaints at RERA Karnatakaon this registration
Jump to the 78 documents Report an error

The Magic Faraway Tree Phase 2 is a Mixed Development project by Total Environment Building Systems Pvt Ltd in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/171015/000424 on 15 Oct 2017. Possession is promised by 30 Sep 2027. The completion date has moved by 45 months from the original filing. 223 of the 240 units on this registration are recorded sold or booked, and 3 of 17 construction stages are filed complete. 3 complaints are on record with the regulator.

At a glance

Project

  • NameThe Magic Faraway Tree Phase 2
  • TypeMixed Development
  • Location
    • Bengaluru South
    • Bengaluru Urban
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/310/PR/171015/000424
  • ReraGenie IDRG-KA-09841

Builder

  • NameTotal Environment Building Systems Pvt Ltd
  • Entity typeCompany
  • CINU45202KA1996PTC020790
  • Authorized SignatoryVishal Sureka
  • Other registrations4 more →
  • Declared earlier projects3 →

Key dates

this monthRegisteredOct 2017First promiseDec 2023Revised toSep 2027

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on15 Oct 2017
  • Promised completion30 Sep 2027
  • Revised completionRevised to 30 Sep 2027 (originally 31 Dec 2023)
  • Buildings2 building records
  • Documents filed78 files

Current status

93%223 of 240 units booked
106.3%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower 03 (B2-as per sanction)-----120
Tower 04 (B3-as per sanction)-----120

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 17 construction stages are filed complete. The stage furthest along is Masonry construction: Bricks, at 96%.

Building: 82% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing workNot applicable
Retaining wall (All types)80%
Plinth level BeamNot applicable
Sub-structure flooring (Parking Floor, more than one floor below general ground level)95%
RCC or MS Framed structure100%
Masonry construction: Bricks, Concrete blocks etc96%
Plastering inside , outside & Ceiling94%
Joinery: Doors, Windows, Ventilators etc78%
Basic work of Water supply, Sanitary and Electrification73%
Dadoing, Skirting, Flooring, Tiles work (All types)83%
Railing and Grill fixing82%
Electrification, Water supply and Sanitary Finishing79%
Wardrobe, Showcase, Kitchen cabinet, Puja work56%
Fire prevention and fire fighting fitting and fixture with network85%
Weather Proof work(tile,concrete)84%
Painting61%
Elevation work100%
Internal and External work including landscapes as per santioned drawings50%

Progress on shared amenities41

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes90%
Internal Roads & FootpathsYes100%
Sewage and Drainage SystemYes90%
Parks & Tree plantingYes50%
Street LightingYes100%
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes100%
Solid waste management and disposalYes20%
Water conservationYes40%
Energy managementYes0%
Fire protection and fire safety requirementsYes96%
Education/Health/Other public amenitiesNoNot applicable
Electricity supply transformer and substationYes40%
Emergency Evacuation servicesYes70%
Storm water drainsYes30%
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterYes60%
ElectricityYes80%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes20%
Club HouseYes75%
Community HallYes75%
Outdoor Sports facilityYes0%
Indoor Sports facilityYes70%
Swimming PoolYes0%
GymYes75%
ParksYes50%
Power BackupYes0%
GasYes80%
Water and SanitationYes60%
Air Conditioning And incerntionNoNot applicable
StaircasesYes100%
LiftsYes91%
Staircases and Lift lobbies, corridor,lobbies, corridorYes88%
Fire escapesYes96%
Common entrance and exit for the building / common portico/foyer/verandahYes80%
BasementYes95%
TerraceYes90%
Outer WallYes30%
Open parking areas and common storage spacesYes75%
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes60%

Land and ownership2

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area8,149 sq m
Named landowners2
LandownerVillageDistrict
Vinod Kumari--
Geetha Pundaleeka--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 433.58 cr
Cost incurredRs 460.72 cr
Spent of the estimate106.26%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 321.85 crRs 274.47 cr
Principal sum and interest payable to financial institutions-Scheduled Banks*Rs 52.08 cr-
On-site expenditure-Salaries of workersRs 45.89 crRs 90.75 cr
On-site expenditure-Consultants FeesRs 13.77 cr-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionDec 2023 → Sep 2024

No reason recorded in the filing

EX/PRM/KA/RERA/1251/310/PR/241128/000424Sep 2024 → Sep 2025

Reason as filed by the promoterForce Majeure

ExtensionSep 2025 → Sep 2027

No reason recorded in the filing

Litigation declared1

CaseCourtStatus
1562/2014/2014III Additional Senior Civil Judge, Bangalore Rural-

Complaints filed with RERA Karnataka3

Case no.ComplainantRespondentFiled
CMP/210423/0007919-Total Environment Building Systems Pvt Ltd23/04/2021
CMP/211111/0008539-Total Environment Building Systems Pvt Ltd11/11/2021
00618/2025-Total Environment Building Systems Pvt Ltd09/04/2025

Documents filed78

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/171015/000424 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: FORM-4 THE MAGIC FARAWAY TREE PHASE 2 Q2 26-27.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: FORM-5 THE MAGIC FARAWAY TREE PHASE 2 Q2 26-27.pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: FORM-6 THE MAGIC FARAWAY TREE PHASE 2 Q2 26-27.pdf15 Oct 2026
Q2 2026-27 Water supply and sewage board15 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Oct 2026
Q2 2026-27 KSPCB- MOEF (Above 50 Acres)15 Oct 2026
Q2 2026-27 KPTCL- BESCOM15 Oct 2026
Q2 2026-27 Fire and Safety15 Oct 2026
Q2 2026-27 Airport Authority of India15 Oct 2026
Q2 2026-27 BSNL/Telecommunication Department15 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form-4 TMFT P2 Q1 26-27.pdf15 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form-5 TMFT P2 Q1 26-27.PDF15 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form-6 TMFT P2 Q1 26-27.pdf15 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form-4 Q4 25-26 TMFT PHASE 2.pdf15 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form-5 Q4 25-26 TMFT PHASE 2.pdf15 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form-6 Q4 25-26 TMFT PHASE 2.pdf15 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form-4 CA certificates Q3-25-26 pdf.pdf27 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form-5 Arch Certificate Q3 2025-26.PDF27 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form-6 Engineering Phase 2 31-12-2025.pdf27 Jan 2026
Annual audit clarificationFile: Annual audit clarification.pdf25 Oct 2024
Bank Account Change ClarificationFile: Bank Account Change Clarification.PDF25 Oct 2024
CertificateFile: CoI-TEBS.PDF-
Project Details-
Architect Certificate for Work Completion Schedule till DateFile: AR certificate work done.PDF-
Engineer Certificate for Work Completion Schedule till DateFile: Engineer Certificate Work as on date.pdf-
CA Certificate for Funds UtilizationFile: Certificate TMFT_P2_FundsUtilized.pdf-
Architect Certificate for Pending Work Completion Schedule.File: AR certificate pending work.PDF-
Engineer Certificate for Pending Work Completion Schedule.File: Engineer Certificate work Pending.pdf-
CA Certificate for Funds required for Project CompletionFile: Certificate TMFT_P2_FundsRequired.pdf-
AffidavitFile: Form Ex7 Affidavit.pdf-
Details Of Sold/ Un-sold UnitsFile: Sold Unsold Details.xlsx-
Document 1File: Authorization letter.pdf-
TMFT_BMICAPA commencement certificate-
Annex 7 dwgs 2-
01 of 27 (Site Plan)-
Sale Deed RERA-
4 AfS TMFT 26Sep17 reduced-min-
TMFT_Area development plan_V3-
17 of 27 (Section AA)-
Title Deed, RTC, Mutation, Conversion-
17of27-Section AA-
TMFT_Area development plan_V3-
TMFT RERA Allotment Letter-
RERA BROCHURE V3-
TMFT Approvals Summary 26Sep17-
Project Specs merged-
32-1, 33-1, 33-2 from 01-04-1995 to 22-08-2017-compressed-
TMFT Common C-29 and 30-
JDA merged-
Title Opinion Merged-
TMFT_Fire NOC-
TMFT_AAI-
TMFT_BESCOM-
TMFT_BWSSB-
TMFT_KSPCB-
TMFT_EC-compressed 03-
TMFT_BSNL-
Balance Sheet 2015 - 2016File: TEBS Balance Sheet 2015-16.pdf-
Balance Sheet 2014 - 2015File: TEBS BS 2014-15 compressed.pdf-
Balance Sheet 2013 - 2014File: TEBS BS 2013-14.pdf-
Audited Profit and Loss Statement 2015 - 2016File: TEBS P&L 2015-16.pdf-
Audited Profit and Loss Statement 2014 - 2015File: TEBS PL 2014-15.pdf-
Audited Profit and Loss Statement 2013 - 2014File: TEBS PL 2013-14.pdf-
Director's Report 2015 - 2016File: TEBS -15-16.pdf-
Director's Report 2014 - 2015File: TEBS - 14-15.pdf-
Director's Report 2013 - 2014File: TEBS -13-14.pdf-
Cash Flow Statement 2015 - 2016File: TEBS Cash Flow Statement 2015-16.pdf-
Cash Flow Statement 2014 - 2015File: TEBS Cash Flow Statement 2014-15.pdf-
Auditor's Report 2015 - 2016File: TEBS Auditors Report 2015-16.pdf-
Auditor's Report 2014 - 2015File: TEBS Audit Report 2014-15.pdf-
Auditor's Report 2013 - 2014File: TEBS Auditors Report 13-14.pdf-
Income Tax Return Acknowledgement 2015 - 2016File: TEBS_IT_2015-16.pdf-
Income Tax Return Acknowledgement 2014 - 2015File: TEBS_IT_2014-15.pdf-
Income Tax Return Acknowledgement 2013 - 2014File: TEBS_IT_2013-14.pdf-
20170730193702310-
Prospectus/BrochureFile: RERA BROCHURE V3_1506436435187.pdf-
Advertisement Copy 1File: TMFT-Phase2 Advertisement.pdf-
Tower Excel SheetFile: PRM_KA_RERA_1251_310_PR_171015_000424.xlsx-

How this compares with Bengaluru Urban

93%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one moved by 45 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep The Magic Faraway Tree Phase 2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmThe Magic Faraway Tree POther 37Dot size: filed unitsN

Filed coordinates, straight-line distance. 37 registered projects within 2 km.

Builder: Total Environment Building Systems Pvt Ltd

TOTAL ENVIRONMENT BUILDING SYSTEMS PVT LTD has 5 registrations on RERA Karnataka, including After The Rain Phase III and After the Rain- Phase 1. Its filings declare 3 earlier projects, none of them declared completed. Litigation is declared on 3 of its registrations. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if The Magic Faraway Tree Phase 2 is delayed beyond 30 Sep 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of The Magic Faraway Tree Phase 2?

The registered promoter entity is Total Environment Building Systems Pvt Ltd, a company as per the filing. Its CIN U45202KA1996PTC020790 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in The Magic Faraway Tree Phase 2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against The Magic Faraway Tree Phase 2?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

What should I check before booking in The Magic Faraway Tree Phase 2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About The Magic Faraway Tree Phase 2. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save The Magic Faraway Tree Phase 2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.