ReraGenieLog inGet a buyer report

Home / Browse projects / Bengaluru Urban, Karnataka / THE HAVEN

Registration approved Residential/Group Housing project

THE HAVEN

By SRI PARVATA BUILDERS PRIVATE LIMITED

RG-KA-10075 · RERA PRM/KA/RERA/1251/446/PR/210518/004154 · Last updated on RERA Karnataka portal: 24 Apr 2021

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No complaints on record
  • Separate project account declared
Jun 2025Possession promisedmoved 12 months from the original
0Complaints at RERA Karnatakaon this registration
Jump to the 87 documents Report an error

THE HAVEN is a Residential/Group Housing project by SRI PARVATA BUILDERS PRIVATE LIMITED in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/210518/004154 on 18 May 2021. Possession is promised by 30 Jun 2025. The completion date has moved by 12 months from the original filing.

At a glance

Project

  • NameTHE HAVEN
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/446/PR/210518/004154
  • ReraGenie IDRG-KA-10075

Builder

  • NameSRI PARVATA BUILDERS PRIVATE LIMITED
  • Entity typeCompany
  • CINU45206AP2006PTC050191
  • Authorized SignatoryT.SESHAGIRI RAO
  • DirectorC.SRINIVASA REDDY
  • Other registrations1 more →

Key dates

this monthRegisteredMay 2021First promiseJun 2024Revised toJun 2025

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on18 May 2021
  • Promised completion30 Jun 2025
  • Revised completionRevised to 30 Jun 2025 (originally 30 Jun 2024)
  • Buildings1 building record
  • Documents filed87 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
The Haven---87087

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 24 Apr 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)Not applicable
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)-
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

As on 24 Apr 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsYes-
Sewage and Drainage SystemYes-
Parks & Tree plantingYes-
Street LightingYes-
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes-
Solid waste management and disposalYes-
Water conservationNoNot applicable
Energy managementYes-
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesYes-
Electricity supply transformer and substationYes-
Emergency Evacuation servicesYes-
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterNoNot applicable
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseYes-
Community HallYes-
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityYes-
Swimming PoolYes-
GymYes-
ParksYes-
Power BackupYes-
GasNoNot applicable
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesYes-
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceNoNot applicable
Outer WallYes-
Open parking areas and common storage spacesYes-
Provision for lodging of management staff and security staffYes-
Water conservation and renewable energyNoNot applicable

Land and ownership4

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,631 sq m
Named landowners4
LandownerVillageDistrict
H.NAGESH--
LAKSHMAMMA--
B.H.MURTHY--
H.SAMPANGIRAMAIAH--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 18.99 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectFORM N SQUARE ARCHITECTS
EngineerKRSNA ENGINEERS

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EX/PRM/KA/RERA/1251/446/PR/241001/004154Jun 2024 → Jun 2025

Reason as filed by the promoterShortage of Labour

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed87

As listed on the registration, under the names the promoter filed them with; the newest 80 of 87 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/210518/004154 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
BWSSB - NOCFile: BWSSB NOC - Uploaded.pdf24 Apr 2021
Notarized Joint Affidavit cum DeclarationFile: Joint Affidavit Cum Declaration.pdf24 Apr 2021
2019-20 Auditors Report with UDIN NumberFile: AUDITOR REPORT 2019-20.pdf3 Apr 2021
2020-21 Auditors Report with UDIN NumberFile: AUDITOR REPORT 2020-21.pdf3 Apr 2021
2019-20 Profit and Loss with UDIN NumberFile: PROFIT &LOSS 2019-20.pdf3 Apr 2021
2020-21 Profit and Loss with UDIN NumberFile: PROFIT &LOSS 2020-21.pdf3 Apr 2021
RERA Bank AccountFile: RERA Bank Account.pdf3 Apr 2021
BWSSB - NOCFile: BWSSB NOC - Uploaded.pdf3 Apr 2021
CertificateFile: SP INCORPORATION CERTI.pdf-
Modified plan details site plan, floor plans, Plan Licence LetterFile: Modified Building Plan.PDF-
Elevation, Sections, Specifications ( If changes are there )File: Modified Building Plan.PDF-
Modification of Plan DetailsFile: AUDITOR REPORT REPORT 2020-21.pdf-
Modification of Plan DetailsFile: Modified Building Plan.PDF-
Modification of Plan DetailsFile: OLD BUILDING LICENSE.pdf-
Modification of Plan DetailsFile: Modified BBMP LICENSE.pdf-
Modification of Plan DetailsFile: OLD BUILDING LICENSE.pdf-
Modification of Plan DetailsFile: Modified BBMP LICENSE.pdf-
Document 1File: POLLUTION CERTIFICATE THE HAVEN.pdf-
Architect Certificate for Work Completion Schedule till DateFile: EX1 ARCHITECT - status of work.pdf-
Engineer Certificate for Work Completion Schedule till DateFile: Engineer Report for Status of Work.pdf-
CA Certificate for Funds UtilizationFile: CA-FUND-REQUIRED-CERTIFICATE.pdf-
Architect Certificate for Pending Work Completion Schedule.File: EX-2 ARCHITECT Pending Work.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: Engineer Report for Pending Work.pdf-
CA Certificate for Funds required for Project CompletionFile: CA-FUND-REQUIRED-CERTIFICATE.pdf-
AffidavitFile: AFFIDAVIT.pdf-
Latest Encumbrance CertificateFile: EC TILL DATE.pdf-
Document 1File: Bescom NOC.pdf-
Document 2File: COMMENCEMENT CERTIFICATE.pdf-
Building LICENCE 8-4-
Approval-BBMP Plan-
DIRECTORES REPORT 2020-21-
Partition deed 8-4_compressed-
DIRECTORES REPORT 2020-21-
Specifications-
EC 8-4-
AFFIDAVIT-
DIRECTORES REPORT 2018-19-
KATHA 8-4-
JDA_compressed-
Coversion-Order-
CONVERSION COPY-15 GTNTS-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
BWSSB-NOC-
P C B NOC 8-4-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Approval-BBMP Plan-
Approval-BBMP Plan-
AUDITAR REPORT 2019-20-
Balance Sheet 2019 - 2020File: BALANCE SHEET 2020-21.pdf-
Balance Sheet 2018 - 2019File: BALANCE SHEET 2019-20.pdf-
Balance Sheet 2017 - 2018File: BALANCE SHEET 2018-19.pdf-
Audited Profit and Loss Statement 2019 - 2020File: PROFIT &LOSS 2020-21.pdf-
Audited Profit and Loss Statement 2018 - 2019File: PROFIT & LOSS 2019-20.pdf-
Audited Profit and Loss Statement 2017 - 2018File: PROFIT & LOSS 2018-19.pdf-
Cash Flow Statement 2019 - 2020File: CASH FLOW STATEMENT 2020-21.pdf-
Cash Flow Statement 2018 - 2019File: CASH FLOW STATEMENT 2019-20.pdf-
Auditor's Report 2017 - 2018File: AUDIT REPORT 2018-19.pdf-
Income Tax Return Acknowledgement 2019 - 2020File: IT ACT 2020-21.pdf-
Income Tax Return Acknowledgement 2018 - 2019File: IT AXT 2019-20.pdf-
Income Tax Return Acknowledgement 2017 - 2018File: IT ACT 2018-19.pdf-
Form - B-
Tower Excel SheetFile: PRMKARERA1251446PR210518004154.xlsx-
Occupancy CertificateFile: OC uploaded.pdf-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one moved by 12 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep THE HAVEN on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: SRI PARVATA BUILDERS PRIVATE LIMITED

SRI PARVATA BUILDERS PRIVATE LIMITED has 2 registrations on RERA Karnataka, including WINDERMERE and THE HAVEN. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if THE HAVEN is delayed beyond 30 Jun 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of THE HAVEN?

The registered promoter entity is SRI PARVATA BUILDERS PRIVATE LIMITED, a company as per the filing. Its CIN U45206AP2006PTC050191 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in THE HAVEN?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at THE HAVEN?

The professionals named in the filing: Architect: FORM N SQUARE ARCHITECTS; Engineer: KRSNA ENGINEERS. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in THE HAVEN?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About THE HAVEN. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save THE HAVEN to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.