Red flags

  • 1 complaint at RERA Karnataka
  • Completion date moved by 9 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
Mar 2027Possession promisedmoved 9 months from the original
17 of 17Construction stages doneevery applicable stage filed complete
48 of 116Units unsoldnot recorded sold or booked
1Complaints at RERA Karnatakaon this registration
Jump to the 128 documents Report an error

The Edge is a Commercial project by Arvind SmartSpaces Limited in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/309/PR/190823/002822 on 23 Aug 2019. Possession is promised by 30 Mar 2027. The completion date has moved by 9 months from the original filing. 68 of the 116 units on this registration are recorded sold or booked, and 17 of 17 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameThe Edge
  • TypeCommercial
  • Location
    • Bengaluru North
    • Bengaluru Urban
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/309/PR/190823/002822
  • ReraGenie IDRG-KA-13217

Builder

  • NameArvind SmartSpaces Limited
  • Entity typeCompany
  • CINL45201GJ2008PLC055771
  • Authorized SignatorySiddharth Dube
  • OthersSailendra Punukollu
  • Other registrations3 more →
  • Declared earlier projects4 →

Key dates

this monthRegisteredAug 2019First promiseJun 2026Revised toMar 2027

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on23 Aug 2019
  • Promised completion30 Mar 2027
  • Revised completionRevised to 30 Mar 2027 (originally 30 Jun 2026)
  • Buildings1 building record
  • Documents filed128 files

Current status

59%68 of 116 units booked
204.6%Of the estimated cost spent so far

Figures as on 10 Jun 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---0116116

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 10 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

17 of 17 construction stages are filed complete.

Building: 100% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Retaining wall (All types)100%
Plinth level BeamNot applicable
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
RCC or MS Framed structure100%
Masonry construction: Bricks, Concrete blocks etc100%
Plastering inside , outside & Ceiling100%
Joinery: Doors, Windows, Ventilators etc100%
Basic work of Water supply, Sanitary and Electrification100%
Dadoing, Skirting, Flooring, Tiles work (All types)100%
Railing and Grill fixing100%
Electrification, Water supply and Sanitary Finishing100%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network100%
Weather Proof work(tile,concrete)100%
Painting100%
Elevation work100%
Internal and External work including landscapes as per santioned drawings100%

Progress on shared amenities41

As on 10 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes100%
Internal Roads & FootpathsYes100%
Sewage and Drainage SystemYes100%
Parks & Tree plantingNoNot applicable
Street LightingYes100%
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes100%
Solid waste management and disposalNoNot applicable
Water conservationYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes100%
Education/Health/Other public amenitiesNoNot applicable
Electricity supply transformer and substationYes100%
Emergency Evacuation servicesYes100%
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterNoNot applicable
ElectricityYes100%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes100%
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupYes100%
GasNoNot applicable
Water and SanitationYes100%
Air Conditioning And incerntionNoNot applicable
StaircasesYes100%
LiftsYes100%
Staircases and Lift lobbies, corridor,lobbies, corridorYes100%
Fire escapesYes100%
Common entrance and exit for the building / common portico/foyer/verandahYes100%
BasementYes100%
TerraceYes100%
Outer WallYes100%
Open parking areas and common storage spacesYes100%
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,140 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 42.14 cr
Cost incurredRs 86.21 cr
Spent of the estimate204.56%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 34.50 crRs 67.75 cr
Principal sum and interest payable to financial institutions-Scheduled BanksRs 3.50 crRs 4.04 cr
Payment of taxesRs 2.43 crRs 2.59 cr
On-site expenditure-Salaries of workersRs 1.71 crRs 11.83 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectApurva Amin Architects
EngineerALFA Consultancy services

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionJun 2026 → Mar 2027

No reason recorded in the filing

Complaints filed with RERA Karnataka1

Case no.ComplainantRespondentFiled
00097/2023-Arvind SmartSpaces Limited19/01/2023

Documents filed128

As listed on the registration, under the names the promoter filed them with; the newest 80 of 128 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/309/PR/190823/002822 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: The Edge Form -Q4, CA.pdf10 Jun 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: The Edge Form -5Architects Q4.pdf10 Jun 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: The Edge Form - 6 Engineer Q4.pdf10 Jun 2026
Q4 2025-26 Water supply and sewage board10 Jun 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)10 Jun 2026
Q4 2025-26 KPTCL- BESCOM10 Jun 2026
Q4 2025-26 Fire and Safety10 Jun 2026
Q4 2025-26 Airport Authority of India10 Jun 2026
Q4 2025-26 BSNL/Telecommunication Department10 Jun 2026
Q4 2025-26 Registration documentFile: Association of Persons - AOP Deed-compressed.pdf10 Jun 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: CA Certificate Edge_120126.pdf15 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: The Edge Form -5Architects Q3.pdf15 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: The Edge Form - 6 Engineer (Q3).pdf15 Jan 2026
Q3 2025-26 Water supply and sewage board15 Jan 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)15 Jan 2026
Q3 2025-26 KSPCB- MOEF (Above 50 Acres)15 Jan 2026
Q3 2025-26 KPTCL- BESCOM15 Jan 2026
Q3 2025-26 Fire and Safety15 Jan 2026
Q3 2025-26 Airport Authority of India15 Jan 2026
Q3 2025-26 BSNL/Telecommunication Department15 Jan 2026
EDGE BANK ACCOUNT STATEMENTFile: 1 Edge Bank Account statement.pdf23 Dec 2021
THE EDGE CONSENT LETTER 1-25File: 2 The EDGE Consent Letter-1-25.pdf23 Dec 2021
THE EDGE CONSENT LETTER 26-50File: 3 The EDGE Consent Letter-26-50.pdf23 Dec 2021
THE EDGE CONSENT LETTER 51-75File: 4 The EDGE Consent Letter-51-75.pdf23 Dec 2021
THE EDGE CONSENT LETTER 76-100File: 5 The EDGE Consent Letter-76-100.pdf23 Dec 2021
CA CERTIFICATEFile: 6 CA certificate- 1-10-2021.pdf23 Dec 2021
ENGINEER CERTIFICATEFile: 7 Engineer certificate- 1-10-2021.pdf23 Dec 2021
ARCHITECT CERTIFICATEFile: 8 Architects certificate- 1-10-2021.pdf23 Dec 2021
Bank Account Statement of State of karnataka( YELAHANKA NEW TOWN, BANGALORE)File: Edge Bank Account statement.pdf9 Sep 2021
Fire Force NOCFile: 29FIRE NOC.pdf9 Sep 2021
KSPCB NOCFile: 33KSPCB NOC.pdf9 Sep 2021
Airport Authority NOCFile: 30AAI NOC.pdf9 Sep 2021
BWSSB NOCFile: 32BWSSB NOC.pdf9 Sep 2021
BESCOM NOCFile: 31BESCOM NOC.pdf9 Sep 2021
SEIAA NOCFile: 34SEIAA.pdf9 Sep 2021
Designated Bank Account statement attached herewithFile: Bank statement Edge - Branch change.pdf1 May 2021
Old Inventory details are attached herewithFile: Old Tumkur Commercial Carpet Area Sheet_2019.08.28_As Per 1st BBMP Sanction.xlsx1 May 2021
New Inventory details are attached herewithFile: The Edge_RERA Carpet Areas_28.01.21_For Mail RERA_As Per 2nd BBMP Approval.xls1 May 2021
CA certificate attached herewith for sold and unsold inventoryFile: The Edge CA Certificate for RERA Alteration.pdf1 May 2021
Consent letter along with list of allottee are attached herewithFile: Edge consent letters with list of allottees.pdf1 May 2021
CertificateFile: 1ASL Certificate of Incorporation.pdf-
Already registered project ongoing detailsFile: The edge Engineer Certifiacte.pdf-
Modified plan details site plan, floor plans, Plan Licence LetterFile: Modified Building Licence The Edge.pdf-
Elevation, Sections, Specifications ( If changes are there )File: Modified Sanction Drawings The Edge 1.pdf-
List Of AllotteesFile: List of the Allottee of the Project The Edge.pdf-
List Of ComplaintsFile: No Complaint filed against Project The Edge.pdf-
Consent LetterFile: Consent Letter.pdf-
List Of Pending LitigationsFile: No Litigation is on the project Land.pdf-
Chartered Accountant CertificateFile: The Edge CA Certificate for RERA Alteration.pdf-
Notarized AffidavitFile: Rera Affidavit.pdf-
Engineer CertificateFile: The edge Engineer Certifiacte.pdf-
Architect CertificateFile: Form-5 Architect Certificate The Edge.pdf-
Structural Engineer Certificate for stability of structureFile: The edge stability Certificate.pdf-
Modification of Plan DetailsFile: 11Approved Building Plan.pdf-
Modification of Plan DetailsFile: Modified Sanction Drawings The Edge.PDF-
Modification of Plan DetailsFile: 10 BBMP License The Edge Registered.pdf-
Modification of Plan DetailsFile: Modified Building Licence The Edge.pdf-
Modification of Plan DetailsFile: The Edge Sold Unsold inventory details registered_compressed.pdf-
Modification of Plan DetailsFile: The Edge Sold and Unsold inventory Alteration_compressed (1).pdf-
Document 1File: 10 BBMP License The Edge.pdf-
10 BBMP License The Edge-
12Approved Layout Plan-
19Sale Deed-
13Agreement for Sale-
14 Sale deed and RTC-
15Approved Section Of Building-
16Area Development Plan Of Project Area-
17Allotment Letter-
The Edge Broucher-
20Specifications-
Encumbrance Certificate 2004-2019-
23Affidavit-
24AD JD AFFIDAVIT CUM DECLARATION-
24Khatha-
21Collaboration Agreement-
25 Any other document-
27Conversion-
28Approval-NOC KTCP Act-
51Utilisation certificate-
52Transfer of development rights certificate-

How this compares with Bengaluru Urban

59%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one moved by 9 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep The Edge on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmThe EdgeOther 13Dot size: filed unitsN

Filed coordinates, straight-line distance. 13 registered projects within 2 km.

Builder: Arvind SmartSpaces Limited

Arvind SmartSpaces Limited has 4 registrations on RERA Karnataka, including Arvind Forest Trails and Arvind Sporcia. Its filings declare 4 earlier projects, 4 of them declared completed. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if The Edge is delayed beyond 30 Mar 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of The Edge?

The registered promoter entity is Arvind SmartSpaces Limited, a company as per the filing. Its CIN L45201GJ2008PLC055771 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in The Edge?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against The Edge?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at The Edge?

The professionals named in the filing: Architect: Apurva Amin Architects; Engineer: ALFA Consultancy services. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in The Edge?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About The Edge. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save The Edge to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.