Home / Browse projects / Thane, Maharashtra / THANSIT CENTRAL DAFFODIL SECTOR C
THANSIT CENTRAL DAFFODIL SECTOR C
By MITTAL PAINTERIOR REALTY LLP
RG-MH-15757 · RERA P51700023256 · Last updated on MahaRERA portal: 3 Mar 2025
Source: official MahaRERA filing
Red flags
- De-registered
- Possession 22 months past the filed date
- Litigation declared, 1 case
Clear
- No complaints on record
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
THANSIT CENTRAL DAFFODIL SECTOR C is a Others project by MITTAL PAINTERIOR REALTY LLP in Thane, Maharashtra, registered with MahaRERA as P51700023256 on 9 Dec 2019. Possession was promised by 30 Dec 2024 and is now 22 months past that date.
At a glance
Project
- NameTHANSIT CENTRAL DAFFODIL SECTOR C
- TypeOthers
- Location
- LAHE
- SHAHAPUR
- Thane
- 421603
- Pincode421603
- RERA no.P51700023256
- ReraGenie IDRG-MH-15757
Builder
- NameMITTAL PAINTERIOR REALTY LLP
- Entity typeOthers
- Named personsSGM REALTY LIMITED, MERCHANT BUILDERS LLP, ANIL SHANKARLAL MITTAL, PRATEEK ANIL MITTAL, SHALINI ANIL MITTAL
- Other registrations2 more →
- No longer live3 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusDe-registered
- Registered on9 Dec 2019
- Promised completion30 Dec 2024
- Revised completionNone
- Buildings1 building record
- Documents filed49 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| BUILDING C | NA | 5 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 3 Mar 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
0 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 0%.
BUILDING C: 0% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 3 Mar 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Land and ownership7
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| Manjeet Vasant Raut | Thane (M Corp.) | Thane |
| Poonam Hemant Shetkar | Thane (M Corp.) | Thane |
| Vidya Shashikant Vekhande | Shahapur (CT) | Thane |
| Bharti (Seema) Jagdish Patil | Thane (M Corp.) | Thane |
| Pankaj Suresh Kowli | - | Mumbai City |
| Aparna Vitthal Khade | Shahapur (CT) | Thane |
| Seema Suresh Patil | Thane (M Corp.) | Thane |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Sharif Ahamad AHMAD |
| Engineer | Mahimtura Consultants Pvt. Ltd. |
| Chartered Accountant | Ramesh Shishodia & Associates |
| Chartered Accountant | AJAY KOKATE |
| Chartered Accountant | Ramesh Shishodia & Associates TRIMBAK KOKATE |
| Partner | Role in project |
|---|---|
| MITTAL PAINTERIOR REALTY LLP | - |
Litigation declared1
| Case | Court | Status |
|---|---|---|
| 261/2010 | KALYAN SD COURT | Disposed off |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 1 Nov 2019 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 1 Nov 2019 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 1 Nov 2019 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 1 Nov 2019Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed49
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Foreclosure of the ProjectFile: 47_THANSIT CENTRAL DAFFODIL SECTOR C_P51700023256(Deregistration).pdf | 3 Mar 2025 |
| Other - TechnicalFile: DEREGISTRATION ORDER C.pdf | 20 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD C.pdf | 7 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: mittal form 2A C.pdf | 7 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1C.pdf | 7 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Sector C Engineers Certificate Form 2.pdf | 7 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Thansit Central Sector C form 3.pdf | 7 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1C.pdf | 7 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Thansit Central Sector C form 3.pdf | 7 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Sector C Engineers Certificate Form 2.pdf | 7 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD C.pdf | 7 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: mittal form 2A C.pdf | 7 Oct 2024 |
| Other - LegalFile: MHTH070007282010_3_2024-03-28.pdf | 29 Jun 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: MITTAL C.pdf | 26 Jun 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 MITTAL C.pdf | 26 Jun 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: MITTAL C.pdf | 26 Jun 2024 |
| Disclosure of sold/ booked inventoryFile: BOOKED ABD SOLD -C.pdf | 12 Mar 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Thansit Central Sector C form 3_compressed.pdf | 12 Mar 2024 |
| Other - TechnicalFile: Partners Declaration Certificate C.pdf | 12 Mar 2024 |
| Details of encumbrances concerned to FinanceFile: LEGAL ENCUMBRANCE DRAFT C.pdf | 6 Mar 2024 |
| Details of encumbrances concerned to LegalFile: LEGAL ENCUMBRANCE DRAFT C.pdf | 6 Mar 2024 |
| Declaration about Commencement CertificateFile: Form D CC Sector C.pdf | 6 Mar 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Partners Declaration Certificate C.pdf | 6 Mar 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Partners Declaration Certificate C.pdf | 6 Mar 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Partners Declaration Certificate C.pdf | 6 Mar 2024 |
| CERSAI detailsFile: Cersai Certificate Sector C.pdf | 6 Mar 2024 |
| Proforma of Agreement for saleFile: AFS C.pdf | 6 Mar 2024 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank Declaration Sector C.pdf | 6 Mar 2024 |
| Deviation Report with respect to Allotment letterFile: Deviation Allotment Letter Sector C.pdf | 6 Mar 2024 |
| Deviation Report with respect to model copy of AgreementFile: Deviation Agreement for Sale Sector C.pdf | 6 Mar 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Signed Form 5 Certificate C.pdf | 27 Nov 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Certificate on RERA FORM 5 C.pdf | 6 Dec 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate C Building_compressed.pdf | 1 Apr 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Signed Certificate C_compressed.pdf | 21 Feb 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Building C Signed Certificate.pdf | 15 Feb 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Building C Signed Certificate.pdf | 16 Sep 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A MahaRERA for TCDS Bldg C 001-compressed.pdf | 25 Feb 2020 |
| PAN CardFile: Pan Card Mittal Painterior LLP.pdf | 18 Nov 2019 |
| Details of encumbrancesFile: Encumberance on GAT 346.pdf | 18 Nov 2019 |
| Declaration in FORM BFile: 6.pdf | 4 Nov 2019 |
| Proforma of Allotment letterFile: AFS Daffodil Bldg C.pdf | 4 Nov 2019 |
| Proforma of Allotment letterFile: Letter of Allotment C.pdf | 4 Nov 2019 |
| Layout approvalFile: ADTP Sheet 1.pdf | 1 Nov 2019 |
| Building plan approvalFile: BUILDING PLAN APPROVAL LETTER (ADTP).pdf | 1 Nov 2019 |
| Copy of the legal title reportFile: Title Report - Mttal Painterior Realty LLP.pdf | 1 Nov 2019 |
| Copy of Layout Approval (in case of layout)File: ADTP Sheet 1.pdf | 1 Nov 2019 |
| Building Plan Approval / NA Order for plotted developmentFile: BUILDING PLAN APPROVAL LETTER (ADTP).pdf | 1 Nov 2019 |
| Commencement Certificates / NA Order for plotted developmentFile: CC Scane 27-09-2019.pdf | 1 Nov 2019 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Building C Certificate.pdf | 1 Nov 2019 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 2 other registrations, which the RERA portal never shows together
- All 49 filed documents as one ZIP, foldered, with a manifest
Keep THANSIT CENTRAL DAFFODIL SECTOR C on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near SHAHAPUR7,600+ in Thane
GREEN PARK
M/S. Green Realtors
PREM NARAYAN RESIDENCY
AADINATH BUILDERS AND DEVELOPERS
RAJ RESIDENCY
PARAGON BUILDCON
THANSIT CENTRAL DAFFODIL SECTOR A
MITTAL PAINTERIOR REALTY LLP
THANSIT CENTRAL DAFFODIL SECTOR B
MITTAL PAINTERIOR REALTY LLP
CHADHA RESIDENCY
CHADHA DEVELOPERS AND PROMOTERS
See every Thane project, with the district possession charts
Builder: MITTAL PAINTERIOR REALTY LLP
MITTAL PAINTERIOR REALTY LLP has 3 registrations on MahaRERA, including THANSIT CENTRAL DAFFODIL SECTOR A and THANSIT CENTRAL DAFFODIL SECTOR B. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 2 of its registrations. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What does it mean that THANSIT CENTRAL DAFFODIL SECTOR C shows as de-registered on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if THANSIT CENTRAL DAFFODIL SECTOR C is delayed beyond 30 Dec 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of THANSIT CENTRAL DAFFODIL SECTOR C?
The registered promoter entity is MITTAL PAINTERIOR REALTY LLP, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in THANSIT CENTRAL DAFFODIL SECTOR C?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for THANSIT CENTRAL DAFFODIL SECTOR C?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at THANSIT CENTRAL DAFFODIL SECTOR C?
The professionals named in the filing: Architect: Sharif Ahamad AHMAD; Engineer: Mahimtura Consultants Pvt. Ltd.; Chartered Accountant: Ramesh Shishodia & Associates; Chartered Accountant: AJAY KOKATE; Chartered Accountant: Ramesh Shishodia & Associates TRIMBAK KOKATE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in THANSIT CENTRAL DAFFODIL SECTOR C?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.