Home / Browse projects / Bengaluru Urban, Karnataka / SYNERGY
SYNERGY
RG-KA-50315 · RERA PRM/KA/RERA/1251/446/PR/091025/008154 · Last updated on RERA Karnataka portal: 15 Oct 2026
Source: official RERA Karnataka filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
SYNERGY is a Residential/Group Housing project by TRENDSQUARES DEVELOPERS in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/091025/008154 on 9 Oct 2025. Possession is promised by 30 Sep 2028. 20 of the 115 units on this registration are recorded sold or booked, and 5 of 17 construction stages are filed complete.
At a glance
Project
- NameSYNERGY
- TypeResidential/Group Housing
- Location
- Bengaluru East
- Bengaluru Urban
- 560035
- Pincode560035
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1251/446/PR/091025/008154
- ReraGenie IDRG-KA-50315
Builder
- NameTRENDSQUARES DEVELOPERS
- Entity typePartnership Firm
- GSTIN29AAXFT7946D3Z9
- Authorized SignatoryR. RAJASEKHAR REDDY
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on9 Oct 2025
- Promised completion30 Sep 2028
- Revised completionNone
- Buildings1 building record
- Documents filed101 files
Current status
Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| NA | - | - | - | 115 | 0 | 115 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
5 of 17 construction stages are filed complete. The stage furthest along is RCC or MS Framed structure, at 75%.
Building: 39% average across the applicable activities
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | 100% |
| Foundation footing work | 100% |
| Upto Plinth Level | 100% |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | 100% |
| Retaining wall (All types) | 100% |
| RCC or MS Framed structure | 75% |
| Masonry Construction | 40% |
| Plastering inside , outside & Ceiling | 0% |
| Joinery: Doors, Windows, Ventilators etc | 0% |
| Basic work of Water supply, Sanitary and Electrification | 0% |
| Dadoing, Skirting, Flooring, Tiles work (All types) | 0% |
| Railing and Grill fixing | 0% |
| Electrification, Water supply and Sanitary Finishing | 0% |
| Painting | 0% |
| Fire prevention and fire fighting fitting and fixture with network | 48% |
| Weather Proof work(tile,concrete) | Not applicable |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Elevation work | 0% |
| Internal and External work including landscapes as per sanctioned drawings | 0% |
Progress on shared amenities40
As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | 25% |
| Sewage and Drainage System | Yes | - |
| Water conservation/rain water harvesting/recharge of ground water | Yes | - |
| Energy management | Yes | - |
| Fire protection and fire safety requirements | Yes | - |
| Solid waste management and disposal | Yes | - |
| Emergency Evacuation services | Yes | - |
| Internal Roads & Footpaths | Yes | 0% |
| Electricity supply transformer and substation | Yes | 25% |
| Storm water drains | Yes | 0% |
| Use of renewable energy | Yes | 0% |
| Sewage Treatment Plant (STP) | Yes | 0% |
| Parks & Tree planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Electricity | Yes | 0% |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | 25% |
| Club House | No | Not applicable |
| Community Hall | Yes | 0% |
| Outdoor Sports facility | Yes | 0% |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | Yes | 50% |
| Gym | Yes | 0% |
| Parks | Yes | 0% |
| Power Backup | Yes | 50% |
| Piped Gas | No | Not applicable |
| Water and Sanitation | Yes | 0% |
| Air Conditioning | No | Not applicable |
| Staircases | Yes | 40% |
| Lifts | Yes | 0% |
| Corridor/Lobbies | Yes | 0% |
| Fire escapes | Yes | 0% |
| Common entrance and exit for the building/common portico/foyer/verandah | Yes | 0% |
| Basement | Yes | 80% |
| Terrace | Yes | 0% |
| Outer Wall | Yes | 0% |
| Open parking areas | Yes | 0% |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | No | Not applicable |
| Common storage spaces | No | Not applicable |
Land and ownership2
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| R. RAJASEKHAR REDDY | - | - |
| B. MANJUNATHA REDDY | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 57.12 cr | Rs 3.65 cr |
| Payment of taxes | Rs 4.20 cr | Rs 24.00 lakh |
| Principal sum and interest payable to financial institutions-Non Banking financial institution (NBFC) | Rs 2.40 cr | Rs 1.15 cr |
| On-site expenditure-Salaries of workers | Rs 55.00 lakh | Rs 62.78 lakh |
| On-site expenditure-Consultants Fees | Rs 20.00 lakh | Rs 10.00 lakh |
| On-site expenditure-Site Overhead | Rs 12.00 lakh | Rs 9.50 lakh |
| On-site expenditure-Cost Of Services(Water, Electricity, Sewage) | Rs 8.00 lakh | Rs 3.21 lakh |
| Payment of Premiums | Rs 5.00 lakh | Rs 5.48 lakh |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | MAHESH P |
| Engineer | VARAPRASAD REDDY S |
| Chartered Accountant | I.V.S SURYANARAYANA RAJU |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed101
As listed on the registration, under the names the promoter filed them with; the newest 80 of 101 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/091025/008154 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 Synergy.pdf | 15 Oct 2026 |
| Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form-5 SYNERGY Q2 2026-27 Architect.pdf | 15 Oct 2026 |
| Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form-6 SYNERGY Q2 2026-27 Engineer.pdf | 15 Oct 2026 |
| Q2 2026-27 Water supply and sewage board | 15 Oct 2026 |
| Q2 2026-27 KPTCL- BESCOM | 15 Oct 2026 |
| Q2 2026-27 Fire and Safety | 15 Oct 2026 |
| Q2 2026-27 Airport Authority of India | 15 Oct 2026 |
| Q2 2026-27 BSNL/Telecommunication Department | 15 Oct 2026 |
| Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form - 4 - CA Certificate.pdf | 14 Jul 2026 |
| Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form-5 SYNERGY Q4 2026-27 Architect.pdf | 14 Jul 2026 |
| Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form-6 SYNERGY Q1 2026-27 Engineer.pdf | 14 Jul 2026 |
| Q1 2026-27 Water supply and sewage board | 14 Jul 2026 |
| Q1 2026-27 KPTCL- BESCOM | 14 Jul 2026 |
| Q1 2026-27 Fire and Safety | 14 Jul 2026 |
| Q1 2026-27 Airport Authority of India | 14 Jul 2026 |
| Q1 2026-27 BSNL/Telecommunication Department | 14 Jul 2026 |
| Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form-4-Q4-FY2025-26 (CA).pdf | 15 Apr 2026 |
| Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form-5 SYNERGY Q4 2025-26 Architect.pdf | 15 Apr 2026 |
| Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form-6 SYNERGY Q4 2025-26 Engineer.pdf | 15 Apr 2026 |
| Q4 2025-26 Water supply and sewage board | 15 Apr 2026 |
| Q4 2025-26 KPTCL- BESCOM | 15 Apr 2026 |
| Q4 2025-26 Fire and Safety | 15 Apr 2026 |
| Q4 2025-26 Airport Authority of India | 15 Apr 2026 |
| Q4 2025-26 BSNL/Telecommunication Department | 15 Apr 2026 |
| Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form-4-Q3-FY2025-26 (RERA)- TRENDSQUARES DEVELOPERS.pdf | 30 Jan 2026 |
| Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form-5 SYNERGY Q3 2025-26 Architect.pdf | 30 Jan 2026 |
| Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form-6 SYNERGY Q3 2025-26 Engineer.pdf | 30 Jan 2026 |
| Q3 2025-26 Water supply and sewage board | 30 Jan 2026 |
| Q3 2025-26 KPTCL- BESCOM | 30 Jan 2026 |
| Q3 2025-26 Fire and Safety | 30 Jan 2026 |
| Q3 2025-26 Airport Authority of India | 30 Jan 2026 |
| Q3 2025-26 BSNL/Telecommunication Department | 30 Jan 2026 |
| Structural Stability Certificate- EngFile: Structural Stability Certificate- Eng.pdf | 4 Oct 2025 |
| STP DETAILS_SignedFile: STP DETAILS_Signed.pdf | 4 Oct 2025 |
| Source of WaterFile: Source of Water.pdf | 4 Oct 2025 |
| Section 3(1) AffidavvitFile: Section 3(1) Affidavvit.pdf | 4 Oct 2025 |
| Project Brief EstimationFile: Project Brief Estimation.pdf | 4 Oct 2025 |
| Proforma Agreement for SaleFile: Proforma Agreement for Sale.pdf | 4 Oct 2025 |
| Model form of allotement letterFile: Model form of allotement letter.pdf | 4 Oct 2025 |
| HAL NOCFile: HAL NOC.pdf | 4 Oct 2025 |
| Form3_ Engineer CertificateFile: Form3_ Engineer Certificate.pdf | 4 Oct 2025 |
| Engineer LicenceFile: Engineer Licence.pdf | 4 Oct 2025 |
| Cost of land clarificationFile: Cost of land clarification.pdf | 4 Oct 2025 |
| EC 15 YearsFile: EC 15 Years.pdf | 4 Oct 2025 |
| Title Deed CATHERINE to Present Land OwnerFile: Title Deed CATHERINE to Present Land Owner.pdf | 4 Oct 2025 |
| Title deed 2003File: Title deed 2003.pdf | 4 Oct 2025 |
| Financial Documents_compressedFile: Financial Documents_compressed.pdf | 4 Oct 2025 |
| Basement & GF approvalFile: Basement & GF approval.pdf | 4 Oct 2025 |
| FF TF plan approval (1)File: FF TF plan approval (1).pdf | 4 Oct 2025 |
| RTC, survey 72, Old NO.53/1 | - |
| Mutation, survey 72, Old NO.53/1 | - |
| Encumbrance Certificate, survey 72, Old NO.53/1 | - |
| Conversion/Alienation Order, survey 72, Old NO.53/1 | - |
| JDA, survey 72, Old NO.53/1 | - |
| Khatha, survey 72, Old NO.53/1 | - |
| Registration CertificateFile: Crtificate.pdf | - |
| GST CertificateFile: GST Certificate.pdf | - |
| Partnership DeedFile: Partnership deed.pdf | - |
| Partner Details | - |
| Partner Details | - |
| Partner Details | - |
| Partner Details | - |
| Partner Details | - |
| Certificate issued by CA Form 1File: Form -1 CA .pdf | - |
| Certificate issued by Architect Form 2File: Form-2 Architect-SYNERGY.pdf | - |
| Certificate issued by Engineer Form 3File: Form-3 Engineer-SYNERGY.pdf | - |
| Project Chartered Accountant | - |
| Project Engineer | - |
| Project Architect | - |
| AffidavitFile: Non Litigation.pdf | - |
| Balance Sheet 2023 - 2024File: Not Application.pdf | - |
| Balance Sheet 2022 - 2023File: Not Application.pdf | - |
| Balance Sheet 2021 - 2022File: Not Application.pdf | - |
| Audited Profit and Loss Statement 2023 - 2024File: Not Application.pdf | - |
| Audited Profit and Loss Statement 2022 - 2023File: Not Application.pdf | - |
| Audited Profit and Loss Statement 2021 - 2022File: Not Application.pdf | - |
| Income Tax Return Acknowledgement 2023 - 2024File: Not Application.pdf | - |
| Income Tax Return Acknowledgement 2022 - 2023File: Not Application.pdf | - |
| Income Tax Return Acknowledgement 2021 - 2022File: Not Application.pdf | - |
| BDA Licence | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep SYNERGY on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Filed coordinates, straight-line distance. 74 registered projects within 2 km.
BIRLA EVARA
VARDHITA PROPERTIES PRIVATE LIMITED
DSR HIGHLAND GREENZ
DSR INFRA PROJECTS
TRIFECTA VANTO PHASE-1
TRIFECTA PROJECTS PRIVATE LIMITED
GODREJ LAKESIDE ORCHARD
Godrej Properties Limited
Adarsh Tropica (Phase-2)
ORCHIDS APARTMENTS PVT LTD
East Park Residences
Ramsons Trendsquares Realty LLP
See every Bengaluru Urban project, with the district possession charts
Builder: TRENDSQUARES DEVELOPERS
TRENDSQUARES DEVELOPERS has 1 registration on RERA Karnataka, including SYNERGY. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if SYNERGY is delayed beyond 30 Sep 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of SYNERGY?
The registered promoter entity is TRENDSQUARES DEVELOPERS, a partnership firm as per the filing. Its GSTIN 29AAXFT7946D3Z9 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in SYNERGY?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at SYNERGY?
The professionals named in the filing: Architect: MAHESH P; Engineer: VARAPRASAD REDDY S; Chartered Accountant: I.V.S SURYANARAYANA RAJU. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SYNERGY?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback