ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / Swastik Onyx

Registration lapsed No litigation declared Residential / Group Housing project

Swastik Onyx

By SUVASYA BUILDERS AND DEVELOPERS LLP

RG-MH-39253 · RERA P51800034346 · Last updated on MahaRERA portal: 22 Apr 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date
  • Rs 0.20 crore secured on the land, in favour of BAJAJ HOSING FINANCE LIMITED
  • The declared charge does not appear in the CERSAI report on the filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 completed earlier projects delivered on promise

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
9 of 11Construction stages donefurthest along: Sanitary Fittings within the flats /..., 95%
0 of 123Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 61 documents Report an error

Swastik Onyx is a Residential / Group Housing project by SUVASYA BUILDERS AND DEVELOPERS LLP in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800034346 on 4 Apr 2022. Possession was promised by 31 Dec 2025 and is now 10 months past that date. 123 of the 123 units on this registration are recorded sold or booked, and 9 of 11 construction stages are filed complete.

At a glance

Project

  • NameSwastik Onyx
  • TypeResidential / Group Housing
  • Location
    • vikhroli market road
    • tagore nagar
    • Kurla
    • Mumbai Suburban
    • 400083
  • Pincode400083
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800034346
  • ReraGenie IDRG-MH-39253

Builder

  • NameSUVASYA BUILDERS AND DEVELOPERS LLP
  • Entity typePartnership
  • PartnersHIREN DINESH SHAH, SANDEEP GANESHLAL JAIN, MANOJ VALJIBHAI DAISARIA
  • Other registrations3 more →
  • Completed1 of 4
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects4 →

Key dates

10 months past promisethis monthRegisteredApr 2022PromisedDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on4 Apr 2022
  • Promised completion31 Dec 2025
  • Revised completionNone
  • Buildings1 building record
  • Documents filed61 files

Current status

100%123 of 123 units booked
98.0%Work done, per cost certificate

Figures as on 22 Apr 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Swastik OnyxNA24201230123

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 22 Apr 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 11 construction stages are filed complete. The stage furthest along is Sanitary Fittings within the flats / premises, at 95%.

Swastik Onyx: 90% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 22 Apr 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed87

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots87
Closed/Covered87

Land and ownership1

MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area935 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared present
Charge in favour ofBAJAJ HOSING FINANCE LIMITED
Secured amountRs 0.20 crore
CERSAI search filedYes
Declared on23 Jul 2025
LandownerVillageDistrict
Tagore Nagar Neel Kamal chslKurlaMumbai Suburban

Approvals and building plan

Sanctioning authorityMHADA
Permissible FSI8102.34
Proposed, not sanctioned7,802 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchLBS Marg Ghatkoper West Branch
Estimated costRs 38.71 cr
Cost incurredRs 37.94 cr
Work done98.0%
BuildingWingEstimatedIncurred
Swastik OnyxNARs 38.71 crRs 37.94 cr

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMs Sai Sampada DBS
EngineerDanish Ansari
Chartered AccountantMH Jain & Company
Chartered AccountantJ N Mehta & Associates
PartnerRole in project
SUVASYA BUILDERS AND DEVELOPERS LLP-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 9 Mar 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 2 Mar 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 2 Mar 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 14 Feb 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed61

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Onyx_Architects Certificate MAR-25.pdf22 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Swastik Onyx Mar 25 .pdf21 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Onyx MAR '25 .pdf18 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Swastik Onyx Dec 24 signed .pdf18 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architects Certificate DEC-24.pdf6 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Onyx DEC '24 .pdf6 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A FY 2023 24.pdf17 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Swastik Onyx June 24 signed .pdf27 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Swastik Onyx Sep 24 signed .pdf27 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ONYX RERA CERTIFICATE JUN 24.pdf20 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Onyx_Architects Certificate SEP 24.pdf20 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Onyx JUN'24.pdf20 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Onyx SEP'24.pdf20 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ONYX RERA CERTIFICATE MAR-2024.pdf14 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Onyx _ Form 3 _ Mar 24 _ Signed.pdf14 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Onyx MAR 24 .pdf14 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: ONYX FORM 5 MAR 24.pdf4 Dec 2024
Declaration about Commencement CertificateFile: Declaration about CC_Onyx.pdf14 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architects Certificate DEC-23.pdf6 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ONYX FORM-2 DEC'23.pdf6 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ONYX FORM-3 DEC'23 .pdf6 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ONYX RERA CERTIFICATE JUN 23.pdf15 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ONYX RERA CERTIFICATE SEPT 23.pdf15 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ONYX ENGINEER CERTIFICATE JUN 23.pdf15 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ONYX ENGINEER CERTIFICATE SEPT 23.pdf15 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: ONYX FORM 2A MAR 23.pdf15 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ONYX FORM 3 JUN 23.pdf15 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ONYX FORM 3 SEPT 23.pdf15 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: ONYX FORM 5 MAR 23.pdf29 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Onyx Mar23.pdf16 Jun 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Mar'23 Onyx.pdf16 Jun 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: JUN 22.pdf19 May 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SEPT 22.pdf19 May 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: DEC 22.pdf19 May 2023
Declaration about Commencement CertificateFile: FORMAT D - FCC.pdf18 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 June 22.pdf18 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Sep 22.pdf18 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Dec 22.pdf18 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 March 23.pdf18 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate JUNE-22.pdf18 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate SEP-22.pdf18 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate DEC-22.pdf18 Apr 2023
Commencement Certificates / NA Order for plotted developmentFile: Further CC 18th Floor.pdf14 Feb 2023
Status of Formation of Legal Entity (Society/Co Op etc.)File: Tagore Nagar 9_Registration Certificate.pdf20 Jan 2023
Details of encumbrancesFile: Encumbrance Bajaj Onyx.pdf25 Jul 2022
Commencement Certificates / NA Order for plotted developmentFile: Plinth CC.pdf29 Mar 2022
Declaration about Commencement CertificateFile: Form D.pdf29 Mar 2022
CERSAI detailsFile: Self Declaration Encrumbrances Cersai.pdf29 Mar 2022
Proforma of Allotment letterFile: Allotment Letter.pdf29 Mar 2022
Proforma of Allotment letterFile: Draft AFS Swastik Onyx.pdf15 Mar 2022
Copy of the legal title reportFile: RERA Title Report_compressed.pdf9 Mar 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 March 22_compressed.pdf8 Mar 2022
CERSAI detailsFile: Cersai Report Building No 9.pdf3 Mar 2022
Building plan approvalFile: 1ST PAGE IOA.pdf2 Mar 2022
Layout approvalFile: IOA PLAN.pdf2 Mar 2022
Details of encumbrancesFile: Self Declaration Reg Encumbrances.pdf2 Mar 2022
Copy of Layout Approval (in case of layout)File: IOA PLAN.pdf2 Mar 2022
Building Plan Approval / NA Order for plotted developmentFile: 1ST PAGE IOA.pdf2 Mar 2022
Declaration in FORM BFile: Form B_compressed.pdf2 Mar 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate_compressed.pdf2 Mar 2022
PAN CardFile: SUVASYA LLP PAN CARD.pdf28 Feb 2022

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise2 under way, not due yet
ProjectLocationFlatsRegisteredStatusPromisedDelivered
Swastik IrisP51800076792Bhandup west, Mumbai Suburban164Jun 2024OngoingJun 2029Not due yet
Swastik PlatinumP51800045216Tagore Nagar, Mumbai Suburban273May 2022OngoingDec 2026Not due yet
SWASTIK PEARLP51800024910TAGORE NAGAR, Mumbai Suburban98Mar 2020CompletedDec 2024Sep 2023

How this compares with Mumbai Suburban

100%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one has not
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Swastik Onyx on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near tagore nagar6,700+ in Mumbai Suburban

2 kmSwastik OnyxCompleted 25Lapsed / revoked 24Other 88Dot size: filed unitsN

Filed coordinates, straight-line distance. 137 registered projects within 2 km.

Builder: SUVASYA BUILDERS AND DEVELOPERS LLP

SUVASYA BUILDERS AND DEVELOPERS LLP has 4 registrations on MahaRERA, including SWASTIK PEARL and Swastik Onyx. Its filings disclose 4 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that Swastik Onyx shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Swastik Onyx is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Swastik Onyx?

The registered promoter entity is SUVASYA BUILDERS AND DEVELOPERS LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Swastik Onyx?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Swastik Onyx?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Swastik Onyx?

The professionals named in the filing: Architect: Ms Sai Sampada DBS; Engineer: Danish Ansari; Chartered Accountant: MH Jain & Company; Chartered Accountant: J N Mehta & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Swastik Onyx?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Swastik Onyx. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Swastik Onyx to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.