Home / Browse projects / Bengaluru Urban, Karnataka / SUYUG'S THE SHALLOT MARQUE

Registration approved No litigation declared Residential/Group Housing project

SUYUG'S THE SHALLOT MARQUE

By SUYUG VENTURES

RG-KA-09739 · RERA PRM/KA/RERA/1251/308/PR/180826/008871 · Last updated on RERA Karnataka portal: 14 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Mar 2028Possession promisedno revision filed
2 of 18Construction stages donefurthest along: Upto Plinth Level, 35%
54 of 54Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 77 documents Report an error

SUYUG'S THE SHALLOT MARQUE is a Residential/Group Housing project by SUYUG VENTURES in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/308/PR/180826/008871 on 18 Aug 2026. Possession is promised by 31 Mar 2028. 0 of the 54 units on this registration are recorded sold or booked, and 2 of 18 construction stages are filed complete.

At a glance

Project

  • NameSUYUG'S THE SHALLOT MARQUE
  • TypeResidential/Group Housing
  • Location
    • Anekal
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/308/PR/180826/008871
  • ReraGenie IDRG-KA-09739

Builder

  • NameSUYUG VENTURES
  • Entity typePartnership Firm
  • GSTIN29AFBFS5577C1ZR
  • Authorized SignatoryKESHAVA G.

Key dates

this monthRegisteredAug 2026PromisedMar 2028

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on18 Aug 2026
  • Promised completion31 Mar 2028
  • Revised completionNone
  • Buildings1 building record
  • Documents filed77 files

Current status

0%0 of 54 units booked
10.1%Of the estimated cost spent so far

Figures as on 14 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Suyug's The Shallot Marque---54054

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 14 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

2 of 18 construction stages are filed complete. The stage furthest along is Upto Plinth Level, at 35%.

Building: 13% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level35%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)0%
Retaining wall (All types)0%
RCC or MS Framed structure0%
Masonry Construction0%
Plastering inside , outside & Ceiling0%
Joinery: Doors, Windows, Ventilators etc0%
Basic work of Water supply, Sanitary and Electrification0%
Dadoing, Skirting, Flooring, Tiles work (All types)0%
Railing and Grill fixing0%
Electrification, Water supply and Sanitary Finishing0%
Painting0%
Fire prevention and fire fighting fitting and fixture with network0%
Weather Proof work(tile,concrete)0%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work0%
Internal and External work including landscapes as per sanctioned drawings0%

Progress on shared amenities40

As on 14 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes0%
Sewage and Drainage SystemYes0%
Water conservation/rain water harvesting/recharge of ground waterYes0%
Energy managementYes0%
Fire protection and fire safety requirementsYes0%
Solid waste management and disposalNoNot applicable
Emergency Evacuation servicesYes0%
Internal Roads & FootpathsYes0%
Electricity supply transformer and substationYes0%
Storm water drainsYes0%
Use of renewable energyYes0%
Sewage Treatment Plant (STP)Yes0%
Parks & Tree plantingYes0%
Street LightingYes0%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityYes0%
Swimming PoolNoNot applicable
GymYes0%
ParksYes0%
Power BackupYes0%
Piped GasNoNot applicable
Water and SanitationYes0%
Air ConditioningNoNot applicable
StaircasesYes0%
LiftsYes0%
Corridor/LobbiesYes0%
Fire escapesYes0%
Common entrance and exit for the building/common portico/foyer/verandahYes0%
BasementYes0%
TerraceYes0%
Outer WallYes0%
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes0%
Common storage spacesNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Named landowners1
LandownerVillageDistrict
SUYUG VENTURES--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 28.21 cr
Cost incurredRs 2.84 cr
Spent of the estimate10.08%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 22.84 crRs 2.22 cr
Principal sum and interest payable to financial institutions-Scheduled BanksRs 2.25 crRs 26.41 lakh
Payment of taxesRs 1.39 crRs 26.10 lakh
On-site expenditure-Salaries of workersRs 51.34 lakhRs 9.55 lakh
On-site expenditure-Consultants FeesRs 45.69 lakh-
On-site expenditure-Site OverheadRs 25.00 lakh-
On-site expenditure-Cost Of Services(Water, Electricity, Sewage)Rs 25.00 lakh-
Payment of cessRs 25.00 lakh-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSACHIN MUTHANNA M. S.
EngineerA. RAMACHANDRAN
Chartered AccountantSHARATH RAO UDUPI

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed77

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/308/PR/180826/008871 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form_4, CA Q2.pdf14 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form-5, Q2.pdf14 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form -6 Q2.pdf14 Oct 2026
Q2 2026-27 Water supply and sewage board14 Oct 2026
Q2 2026-27 KPTCL- BESCOM14 Oct 2026
Q2 2026-27 Fire and Safety14 Oct 2026
Cancellation of Agreement for SaleFile: Cancellation of sale Agreement Sy no 47-2 S Medihalli.pdf11 Aug 2026
Updated EC till todayFile: EC till date.pdf11 Aug 2026
Clarification Letter for QueryFile: Clarificatin Letter for Query.pdf11 Aug 2026
Firm ITR FY 2023-24File: Firm ITR 2023-24.pdf30 Jul 2026
Firm ITR FY 2024-25File: Firm ITR 2024-25.pdf30 Jul 2026
EC upto DateFile: EC.pdf30 Jul 2026
Building LicenseFile: Building License.pdf30 Jul 2026
Project Location details with BoundariesFile: Location Details.png30 Jul 2026
All original sanctioned drawings, floor plan, sectional drawings and elevationsFile: Approved Plan Copies.pdf30 Jul 2026
Commencement CertificateFile: Commencement Certificate.pdf30 Jul 2026
Village Map with Proposed Site AreaFile: Village MAP with Proposed Site Area.pdf30 Jul 2026
KSPCB NOCFile: KSPCB NOC.pdf30 Jul 2026
Details of Project Amenities and FacilitiesFile: Details of Project Amenties & Facilities.pdf30 Jul 2026
Form 6 - EngineerFile: Form- 6.pdf30 Jul 2026
Land Cost Calc as per Guidance ValueFile: Land Cost Calculation.pdf30 Jul 2026
Water NOCFile: WATER NOC.pdf30 Jul 2026
RTC, survey 47/2-
Mutation, survey 47/2-
Encumbrance Certificate, survey 47/2-
Conversion/Alienation Order, survey 47/2-
Sale/Title/Gift Deed, survey 47/2-
Khatha, survey 47/2-
Registration CertificateFile: Partnership Registration Certificate.pdf-
GST CertificateFile: GST Certificate.pdf-
Partnership DeedFile: PartnershipDeed.pdf-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Certificate issued by CA Form 1File: Form - 1.pdf-
Certificate issued by Architect Form 2File: Form -2 Architect.pdf-
Certificate issued by Engineer Form 3File: Form- 3 (Engineer).pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: Affidavit Non Litigation.pdf-
Balance Sheet 2024 - 2025File: Suyug Ventures FY 2024-25.pdf-
Balance Sheet 2023 - 2024File: Suyug Ventures FY 2023-24.pdf-
Audited Profit and Loss Statement 2024 - 2025File: Suyug Ventures FY 2024-25.pdf-
Audited Profit and Loss Statement 2023 - 2024File: Suyug Ventures FY 2023-24.pdf-
Income Tax Return Acknowledgement 2024 - 2025File: Firm ITR 2024-25.pdf-
Income Tax Return Acknowledgement 2023 - 2024File: Firm ITR 2023-24.pdf-
Commencement Certificate-
Approved Plan Copies-
Approved Plan Copies-
Structural Structural Certificate-
Project Specifications-
Proforma of Agreement for Sale-
Proforma of Allotment Letter-
Affidavit Form B-
Affidavit Section 3(1) Violation-
Advocate Search Report-
BESCOM NOC-
WATER NOC-
KSPCB NOC-
Unnamed document-
FIRE FORCE NOC-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
STP Design Drawing by Eng-
Construction Estimation Sheet-
Master Plan with Proposed Site Area-
Single Plot Layout Plan-
Single Plot Layout Order letter-
ADLR Certified Survey Sketch-

How this compares with Bengaluru Urban

0%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep SUYUG'S THE SHALLOT MARQUE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: SUYUG VENTURES

SUYUG VENTURES has 1 registration on RERA Karnataka, including SUYUG'S THE SHALLOT MARQUE. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if SUYUG'S THE SHALLOT MARQUE is delayed beyond 31 Mar 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of SUYUG'S THE SHALLOT MARQUE?

The registered promoter entity is SUYUG VENTURES, a partnership firm as per the filing. Its GSTIN 29AFBFS5577C1ZR can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in SUYUG'S THE SHALLOT MARQUE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SUYUG'S THE SHALLOT MARQUE?

The professionals named in the filing: Architect: SACHIN MUTHANNA M. S.; Engineer: A. RAMACHANDRAN; Chartered Accountant: SHARATH RAO UDUPI. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SUYUG'S THE SHALLOT MARQUE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SUYUG'S THE SHALLOT MARQUE. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SUYUG'S THE SHALLOT MARQUE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.