ReraGenieLog inGet a buyer report

Home / Browse projects / Bengaluru Urban, Karnataka / SUVRITH SHELTER

Registration approved No litigation declared Residential/Group Housing project

SUVRITH SHELTER

By SUVRITH STRUCTURES

RG-KA-21095 · RERA PRM/KA/RERA/1251/310/PR/151124/007230 · Last updated on RERA Karnataka portal: 30 Sep 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Sep 2026Possession promisedno revision filed
16 of 16Construction stages doneevery applicable stage filed complete
0 of 124Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 135 documents Report an error

SUVRITH SHELTER is a Residential/Group Housing project by SUVRITH STRUCTURES in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/151124/007230 on 15 Nov 2024. Possession is promised by 30 Sep 2026. 124 of the 124 units on this registration are recorded sold or booked, and 16 of 16 construction stages are filed complete.

At a glance

Project

  • NameSUVRITH SHELTER
  • TypeResidential/Group Housing
  • Location
    • Bengaluru South
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/310/PR/151124/007230
  • ReraGenie IDRG-KA-21095

Builder

  • NameSUVRITH STRUCTURES
  • Entity typePartnership Firm
  • GSTIN29ACHFS8024P2ZB
  • Authorized SignatoryShekar R.
  • Other registrations1 more →
  • Declared earlier projects2 →

Key dates

this monthRegisteredNov 2024PromisedSep 2026

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on15 Nov 2024
  • Promised completion30 Sep 2026
  • Revised completionNone
  • Buildings1 building record
  • Documents filed135 files

Current status

100%124 of 124 units booked
11.2%Of the estimated cost spent so far

Figures as on 30 Sep 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SUVRITH SHELTER---1240124

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 30 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

16 of 16 construction stages are filed complete.

Building: 100% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)Not applicable
RCC or MS Framed structure100%
Masonry Construction100%
Plastering inside , outside & Ceiling100%
Joinery: Doors, Windows, Ventilators etc100%
Basic work of Water supply, Sanitary and Electrification100%
Dadoing, Skirting, Flooring, Tiles work (All types)100%
Railing and Grill fixing100%
Electrification, Water supply and Sanitary Finishing100%
Painting100%
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)100%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work100%
Internal and External work including landscapes as per sanctioned drawings100%

Progress on shared amenities40

As on 30 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes100%
Sewage and Drainage SystemYes100%
Water conservation/rain water harvesting/recharge of ground waterYes100%
Energy managementYes100%
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalNoNot applicable
Emergency Evacuation servicesYes100%
Internal Roads & FootpathsYes100%
Electricity supply transformer and substationYes100%
Storm water drainsYes100%
Use of renewable energyYes100%
Sewage Treatment Plant (STP)Yes100%
Parks & Tree plantingYes100%
Street LightingYes100%
ElectricityYes100%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes100%
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupNoNot applicable
Piped GasNoNot applicable
Water and SanitationNoNot applicable
Air ConditioningNoNot applicable
StaircasesYes100%
LiftsYes100%
Corridor/LobbiesYes100%
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahYes100%
BasementNoNot applicable
TerraceYes100%
Outer WallYes100%
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Named landowners1
LandownerVillageDistrict
Suvirth Structures--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 60.17 cr
Cost incurredRs 6.71 cr
Spent of the estimate11.15%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 50.19 crRs 6.71 cr
Principal sum and interest payable to financial institutions-Scheduled BanksRs 5.00 cr-
On-site expenditure-Cost Of Services(Water, Electricity, Sewage)Rs 2.00 cr-
On-site expenditure-Site OverheadRs 1.20 cr-
On-site expenditure-Salaries of workersRs 60.00 lakh-
On-site expenditure-Consultants FeesRs 58.40 lakh-
Payment of cessRs 50.00 lakh-
Payment of feesRs 10.00 lakh-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectG. BHANUMATHY
EngineerARUN KUMAR S R
Chartered AccountantB. Mallaiah

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed135

As listed on the registration, under the names the promoter filed them with; the newest 80 of 135 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/151124/007230 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 Q2.pdf30 Sep 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form 5 Q2.pdf30 Sep 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form 6 Q2.pdf30 Sep 2026
Q2 2026-27 Water supply and sewage board30 Sep 2026
Q2 2026-27 KPTCL- BESCOM30 Sep 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4.pdf15 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form 5.pdf15 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form 6.pdf15 Jul 2026
Q1 2026-27 Water supply and sewage board15 Jul 2026
Q1 2026-27 KPTCL- BESCOM15 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4_.pdf15 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5.pdf15 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6.pdf15 Apr 2026
Q4 2025-26 Water supply and sewage board15 Apr 2026
Q4 2025-26 KPTCL- BESCOM15 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA Q3.pdf15 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5 Arc Q3.pdf15 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6 Eng Q3.pdf15 Jan 2026
Q3 2025-26 Water supply and sewage board15 Jan 2026
Q3 2025-26 KPTCL- BESCOM15 Jan 2026
Details about Source of FundsFile: Details of Source of Funds.pdf13 Nov 2024
Auction Sale DeedFile: Auction Sale Deed.pdf13 Nov 2024
All Floor Sanction Plan - Clear CopiesFile: All Floor Plan Rescan Copies.pdf13 Nov 2024
Extract of Master Plan proposed AreaFile: Master Plan - CDP.pdf13 Nov 2024
ZR Copy with HighlightedFile: Zonal Regulation - Highlighted.pdf13 Nov 2024
ADLR Survey SketchFile: ADLR Survey Sketch.pdf13 Nov 2024
Layout Plan CopiesFile: Layout Plan.pdf13 Nov 2024
Form 6 - Engineer CertificateFile: Form 6 - Eng Certificate.pdf13 Nov 2024
Commencement CertificateFile: Commencement Certificate.pdf13 Nov 2024
Water NOCFile: Water NOC.pdf13 Nov 2024
SBI Loan Confirmation LetterFile: SBI Loan Confirmation Letter.pdf13 Nov 2024
Borewell - 1File: Borewell 1.jpg22 Oct 2024
Borewell - 2File: Borewell 2.jpg22 Oct 2024
Borewell - 3File: Borewell 3.jpg22 Oct 2024
Latest Khata CertificateFile: Khata.pdf23 Sep 2024
Building Approval LetterFile: Building Letter.pdf23 Sep 2024
Proforma Allotment LetterFile: Allotment Letter.pdf23 Sep 2024
BDA Approved PlanFile: BDA Plan.pdf23 Sep 2024
Land SketchFile: Sketch.pdf23 Sep 2024
BDA Plan Approved LetterFile: Plan License.pdf23 Sep 2024
ZR CopyFile: ZR Copy.pdf23 Sep 2024
Details for Not Govt LandFile: Clarification about Not Govt Land.pdf18 Aug 2024
Sale DeedFile: Sale Deed and Rectifed Sale Deed.pdf18 Aug 2024
Proforma of Sale AgreementFile: Proforma of Sale Agreement.pdf18 Aug 2024
STP DrawingFile: STP Drawing.pdf18 Aug 2024
Building Approval LetterFile: Building Approval Letter.pdf18 Aug 2024
Project Image 1File: IMG-20240808-WA0025.jpg18 Aug 2024
Project Image 2File: IMG-20240808-WA0029.jpg18 Aug 2024
Project Image 3File: IMG-20240808-WA0027.jpg18 Aug 2024
Water NOCFile: Water NOC.pdf18 Aug 2024
BESCOM Fee ReceiptFile: BESCOM Receipt.jpg18 Aug 2024
BESCOM NOCFile: BESCOM Noc.pdf18 Aug 2024
Certified Carpet Area, Common Area and Amenities detailsFile: Certified Carpet, Amenities & Common Area Statement.pdf18 Aug 2024
Site PlanFile: Site Plan.pdf18 Aug 2024
Typical Floor PlanFile: Typical Floor Plan.pdf18 Aug 2024
Ground Floor PlanFile: Ground Floor Plan.pdf18 Aug 2024
ZR CopyFile: ZR Copy.pdf18 Aug 2024
Certified Project SpecificationsFile: Certified Project Specs.pdf18 Aug 2024
Land Cost CalculationFile: Land Cost Calc.pdf18 Aug 2024
RTC, survey 11-
Mutation, survey 11-
Encumbrance Certificate, survey 11-
Conversion/Alienation Order, survey 11-
Sale/Title/Gift Deed, survey 11-
Khatha, survey 11-
Registration CertificateFile: Form C.pdf-
Partnership DeedFile: Partnership Deed.pdf-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Certificate issued by CA Form 1File: CA Reg - Shelter.pdf-
Certificate issued by Architect Form 2File: ARC Reg.pdf-
Certificate issued by Engineer Form 3File: ENG Reg.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
SUVRITH SADANSite No. 751, Sy. No. 129/1A, Hemmigepura, Kengeri Sub Zone, Ward No. 198Completed-No date filed

How this compares with Bengaluru Urban

100%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep SUVRITH SHELTER on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: SUVRITH STRUCTURES

SUVRITH STRUCTURES has 2 registrations on RERA Karnataka, including SUVRITH SADAN and SUVRITH SHELTER. Its filings declare 2 earlier projects, 1 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if SUVRITH SHELTER is delayed beyond 30 Sep 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of SUVRITH SHELTER?

The registered promoter entity is SUVRITH STRUCTURES, a partnership firm as per the filing. Its GSTIN 29ACHFS8024P2ZB can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in SUVRITH SHELTER?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SUVRITH SHELTER?

The professionals named in the filing: Architect: G. BHANUMATHY; Engineer: ARUN KUMAR S R; Chartered Accountant: B. Mallaiah. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SUVRITH SHELTER?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SUVRITH SHELTER. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SUVRITH SHELTER to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.