Home / Browse projects / Bengaluru Urban, Karnataka / Surbacon Cedar

Registration approved Residential/Group Housing project

Surbacon Cedar

By Surbacon Development Pvt. Ltd

RG-KA-43449 · RERA PRM/KA/RERA/1251/308/PR/200117/003174 · Last updated on RERA Karnataka portal: 30 Dec 2019

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 21 months
  • 2 extensions taken

Clear

  • No complaints on record
  • Separate project account declared
Aug 2024Possession promisedmoved 21 months from the original
0Complaints at RERA Karnatakaon this registration
Jump to the 61 documents Report an error

Surbacon Cedar is a Residential/Group Housing project by Surbacon Development Pvt. Ltd in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/308/PR/200117/003174 on 17 Jan 2020. Possession is promised by 1 Aug 2024. The completion date has moved by 21 months from the original filing.

At a glance

Project

  • NameSurbacon Cedar
  • TypeResidential/Group Housing
  • Location
    • Anekal
    • Bengaluru Urban
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/308/PR/200117/003174
  • ReraGenie IDRG-KA-43449

Builder

  • NameSurbacon Development Pvt. Ltd
  • Entity typeCompany
  • Authorized SignatoryArjun Ravi Kumar
  • DirectorsG K Ravi Kumar, Arjun Ravi Kumar
  • Other registrations1 more →
  • Declared earlier projects1 →

Key dates

this monthRegisteredJan 2020First promiseNov 2022Revised toAug 2024

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on17 Jan 2020
  • Promised completion1 Aug 2024
  • Revised completionRevised to 1 Aug 2024 (originally 1 Nov 2022)
  • Buildings1 building record
  • Documents filed61 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
1---1560156

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 30 Dec 2019, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)Not applicable
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)Not applicable
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
Painting-
Elevation workNot applicable
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

As on 30 Dec 2019, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsYes-
Sewage and Drainage SystemYes-
Parks & Tree plantingYes-
Street LightingYes-
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes-
Solid waste management and disposalYes-
Water conservationYes-
Energy managementYes-
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesYes-
Electricity supply transformer and substationYes-
Emergency Evacuation servicesNoNot applicable
Storm water drainsNoNot applicable
Use of renewable energyYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseYes-
Community HallYes-
Outdoor Sports facilityYes-
Indoor Sports facilityYes-
Swimming PoolYes-
GymYes-
ParksYes-
Power BackupYes-
GasNoNot applicable
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesNoNot applicable
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesYes-
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes-

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area9,109 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 20.00 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectG.K Ravi Kumar Associates
EngineerManohar Consulants

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionNov 2022 → Aug 2023

No reason recorded in the filing

EX/PRM/KA/RERA/1251/308/PR/230725/003174Aug 2023 → Aug 2024

Reason as filed by the promoterothers

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed61

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/308/PR/200117/003174 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
BESCOM NOCFile: BESCOM NOC Letter.pdf30 Dec 2019
BESCOM NOCFile: RERA Letter for BESCOM NOC.pdf17 Dec 2019
Local Panchayath NOC for WaterFile: Water NOC.pdf10 Dec 2019
Directors Report 2016-2017File: Surbacon Director Report 2017.pdf10 Dec 2019
CertificateFile: Surbacon Registration Certificate.pdf-
Architect Certificate for Work Completion Schedule till DateFile: Architect's Certificate (Form EX1).pdf-
Engineer Certificate for Work Completion Schedule till DateFile: Engineer's Certificate (Form Ex5).pdf-
CA Certificate for Funds UtilizationFile: Form ex3_compressed.pdf-
Architect Certificate for Pending Work Completion Schedule.File: Architect's Certificate (Form Ex2).pdf-
Engineer Certificate for Pending Work Completion Schedule.File: Engineer's Certificate (Form Ex6).pdf-
CA Certificate for Funds required for Project CompletionFile: Form Ex4_compressed.pdf-
AffidavitFile: Affidavit Form Ex7.pdf-
Latest Encumbrance CertificateFile: SC EC_compressed.pdf-
Consent letter from 2/3rd of AllotteesFile: Filler Document.pdf-
Details Of Sold/ Un-sold UnitsFile: SoldUnsoldDetails.xlsx-
Document 1File: Consent Letter Merged.pdf-
Plan Approval Letter BMRDA-
SC Sheet 3 Reduced-
Approved Plan Full-
1Place Holder Document-
1Place Holder Document-
Land Docs 51-5-
SC Sheet 6 Reduced-
SC Sheet 1 Reduced-
1Place Holder Document-
1Place Holder Document-
Hebbagodi CMC NOC-
Cedar Specifications-
Kammasandra Sy No 51-5 EC-
Notarized Affidavit-
Joint affidavit-
Khatha Extract-
Cedar JD 14-7-14-
Conversion Order RERA-
S Cedar Relinquishment Deed 27-7-19-
KSPCB CFE-
EC SEIAA Page 1-
1Place Holder Document-
1Place Holder Document-
Conversion Order RERA-
Balance Sheet 2017 - 2018File: Surbacon Balance Sheet 17-18.pdf-
Balance Sheet 2016 - 2017File: Surbacon Balance Sheet 16-17.pdf-
Balance Sheet 2015 - 2016File: Surbacon Balance Sheet 15-16.pdf-
Audited Profit and Loss Statement 2017 - 2018File: Surbacon Profit Loss 17-18.pdf-
Audited Profit and Loss Statement 2016 - 2017File: Surbacon Profit Loss 16-17.pdf-
Audited Profit and Loss Statement 2015 - 2016File: Surbacon Profit Loss 15-16.pdf-
Director's Report 2017 - 2018File: Director Report - Surbacon development Pvt Ltd New Format 2017-18.pdf-
Director's Report 2016 - 2017File: Surbacon Directors Report 16-17.pdf-
Director's Report 2015 - 2016File: Surbacon Directors Report 15-16.pdf-
Cash Flow Statement 2017 - 2018File: Surbacon Cash Flow 17-18.pdf-
Cash Flow Statement 2016 - 2017File: Surbacon Cash Flow 16-17.pdf-
Auditor's Report 2017 - 2018File: Auditors Report - Surbacon Development 17-18.pdf-
Auditor's Report 2016 - 2017File: Surbacon Auditor Report 16-17.pdf-
Auditor's Report 2015 - 2016File: Surbacon Auditor Report 15-16.pdf-
Income Tax Return Acknowledgement 2017 - 2018File: Surbacon ITR 18-19.pdf-
Income Tax Return Acknowledgement 2016 - 2017File: Surbacon ITR 17-18.pdf-
Income Tax Return Acknowledgement 2015 - 2016File: Surbacon ITR 16-17.pdf-
Form B-
Prospectus/BrochureFile: Cedar Mobile March 20.pdf-
Advertisement Copy 1File: No Advertisement Done so far.pdf-
Tower Excel SheetFile: PRM_KA_RERA_1251_308_PR_200117_003174.xlsx-

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
Surbacon Aspen-Completed-No date filed

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one moved by 21 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Surbacon Cedar on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmSurbacon CedarOther 18Dot size: filed unitsN

Filed coordinates, straight-line distance. 18 registered projects within 2 km.

Builder: Surbacon Development Pvt. Ltd

Surbacon Development Pvt. Ltd has 2 registrations on RERA Karnataka, including Surbacon Cedar and Surbacon Aspen. Its filings declare 1 earlier project, 1 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Surbacon Cedar is delayed beyond 1 Aug 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Surbacon Cedar?

The registered promoter entity is Surbacon Development Pvt. Ltd, a company as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Surbacon Cedar?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Surbacon Cedar?

The professionals named in the filing: Architect: G.K Ravi Kumar Associates; Engineer: Manohar Consulants. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Surbacon Cedar?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Surbacon Cedar. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Surbacon Cedar to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.