Red flags

  • No red flags in this filing

Clear

  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Dec 2023Possession promisedno revision filed
0Complaints at RERA Karnatakaon this registration
Jump to the 43 documents Report an error

SUNRISE SERENITY is a Residential/Group Housing project by SUNRISE DEVELOPERS in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/210219/003915 on 19 Feb 2021. Possession is promised by 30 Dec 2023.

At a glance

Project

  • NameSUNRISE SERENITY
  • TypeResidential/Group Housing
  • Location
    • Bengaluru South
    • Bengaluru Urban
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/310/PR/210219/003915
  • ReraGenie IDRG-KA-17288

Builder

  • NameSUNRISE DEVELOPERS
  • Entity typePartnership Firm
  • Authorized SignatoryMr.A.SRINIVASULU
  • OthersMr.A.SRINIVASULU
  • Declared earlier projects1 →

Key dates

this monthRegisteredFeb 2021PromisedDec 2023

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on19 Feb 2021
  • Promised completion30 Dec 2023
  • Revised completionNone
  • Buildings1 building record
  • Documents filed43 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SUNRISE SERENITY---44044

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 12 Feb 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

As on 12 Feb 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsNoNot applicable
Sewage and Drainage SystemYes-
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
Provision for community buildings and for treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes-
Water conservationNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesYes-
Electricity supply transformer and substationYes-
Emergency Evacuation servicesNoNot applicable
Storm water drainsYes-
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupNoNot applicable
GasNoNot applicable
Water and SanitationNoNot applicable
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesNoNot applicable
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementNoNot applicable
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,934 sq m
Named landowners1
LandownerVillageDistrict
Mr.D.VENKATESH--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 14.50 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectLakshmikanth
EngineerA.RAMCHANDRAN

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed43

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/210219/003915 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Pass BookFile: Pass book in project name.pdf12 Feb 2021
Audited StatementFile: bank documents.pdf12 Feb 2021
Bank DocumentsFile: Bank Statement Audited.pdf12 Feb 2021
KSPCBFile: kspcb.pdf5 Feb 2021
PLAN LICENCE LETTERFile: Plan Licence Letter.pdf5 Feb 2021
PROJECT SPECIFICATINFile: Specifications.pdf5 Feb 2021
BWSSBFile: bwssb.pdf5 Feb 2021
BANK DOCUMENTSFile: bank documents.pdf5 Feb 2021
CertificateFile: Comp.pdf-
Plan all-
Plan all-
Sale Deed (3)-
sanction letter-
EC 2004 to 2020R R nagar-
affidavit 3 (1)-
aff cum dec jd-
Katha Latest-
JDA-
PCB NOC_compressed-
conv_compressed (2)-
Unnamed document-
Unnamed document-
Unnamed document-
sanction letter-
Balance Sheet 2019 - 2020File: Audit report for R R nagar.pdf-
Balance Sheet 2018 - 2019File: Audit report for R R nagar.pdf-
Balance Sheet 2017 - 2018File: Audit report for R R nagar.pdf-
Audited Profit and Loss Statement 2019 - 2020File: Audit report for R R nagar.pdf-
Audited Profit and Loss Statement 2018 - 2019File: Audit report for R R nagar.pdf-
Audited Profit and Loss Statement 2017 - 2018File: Audit report for R R nagar.pdf-
Director's Report 2019 - 2020File: Audit report for R R nagar.pdf-
Director's Report 2018 - 2019File: Audit report for R R nagar.pdf-
Director's Report 2017 - 2018File: Audit report for R R nagar.pdf-
Cash Flow Statement 2019 - 2020File: Audit report for R R nagar.pdf-
Cash Flow Statement 2018 - 2019File: Audit report for R R nagar.pdf-
Auditor's Report 2019 - 2020File: Audit report for R R nagar.pdf-
Auditor's Report 2018 - 2019File: Audit report for R R nagar.pdf-
Auditor's Report 2017 - 2018File: Audit report for R R nagar.pdf-
Income Tax Return Acknowledgement 2019 - 2020File: Audit report for R R nagar.pdf-
Income Tax Return Acknowledgement 2018 - 2019File: Audit report for R R nagar.pdf-
Income Tax Return Acknowledgement 2017 - 2018File: Audit report for R R nagar.pdf-
form b (2)_compressed-
Tower Excel SheetFile: PRM_KA_RERA_1251_310_PR_210219_003915.xlsx-

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
Ashoka Legend BLock-A-Completed-No date filed

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep SUNRISE SERENITY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: SUNRISE DEVELOPERS

SUNRISE DEVELOPERS has 1 registration on RERA Karnataka, including SUNRISE SERENITY. Its filings declare 1 earlier project, 1 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if SUNRISE SERENITY is delayed beyond 30 Dec 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of SUNRISE SERENITY?

The registered promoter entity is SUNRISE DEVELOPERS, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in SUNRISE SERENITY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SUNRISE SERENITY?

The professionals named in the filing: Architect: Lakshmikanth; Engineer: A.RAMCHANDRAN. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SUNRISE SERENITY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SUNRISE SERENITY. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SUNRISE SERENITY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.