Home / Browse projects / Bengaluru Urban, Karnataka / SUMADHURA SUSHANTHAM PHASE II

Registration approved Residential/Group Housing project

SUMADHURA SUSHANTHAM PHASE II

By SUMADHURA INFRACON PRIVATE LIMITED

RG-KA-15483 · RERA PRM/KA/RERA/1251/309/PR/200205/003253 · Last updated on RERA Karnataka portal: 6 May 2022

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 21 months
  • 2 extensions taken

Clear

  • No complaints on record
  • Separate project account declared
Dec 2024Possession promisedmoved 21 months from the original
0Complaints at RERA Karnatakaon this registration
Jump to the 147 documents Report an error

SUMADHURA SUSHANTHAM PHASE II is a Residential/Group Housing project by SUMADHURA INFRACON PRIVATE LIMITED in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/309/PR/200205/003253 on 5 Feb 2020. Possession is promised by 30 Dec 2024. The completion date has moved by 21 months from the original filing.

At a glance

Project

  • NameSUMADHURA SUSHANTHAM PHASE II
  • TypeResidential/Group Housing
  • Location
    • Bengaluru North
    • Bengaluru Urban
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/309/PR/200205/003253
  • ReraGenie IDRG-KA-15483

Builder

  • NameSUMADHURA INFRACON PRIVATE LIMITED
  • Entity typeCompany
  • CINU45200KA2012PTC062071
  • Authorized SignatorySri BHARAT KUMAR KANDUKURI
  • OthersSri K VENKAT RAO
  • Other registrations20 more →
  • Declared earlier projects16 →

Key dates

this monthRegisteredFeb 2020First promiseMar 2023Revised toDec 2024

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on5 Feb 2020
  • Promised completion30 Dec 2024
  • Revised completionRevised to 30 Dec 2024 (originally 31 Mar 2023)
  • Buildings3 building records
  • Documents filed147 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
WING B---84084
WING C---98098
WING D---70070

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 6 May 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level BeamNot applicable
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etcNot applicable
Plastering inside , outside & CeilingNot applicable
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network-
Weather Proof work(tile,concrete)-
Painting-
Elevation workNot applicable
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities34

As on 6 May 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsYes-
Sewage and Drainage SystemYes-
Parks & Tree plantingYes-
Street LightingYes-
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes-
Solid waste management and disposalYes-
Water conservationYes-
Energy managementYes-
Fire protection and fire safety requirementsYes-
Education/Health/Other public amenitiesYes-
Electricity supply transformer and substationYes-
Emergency Evacuation servicesNoNot applicable
Storm water drainsYes-
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseYes-
Community HallYes-
Outdoor Sports facilityYes-
Indoor Sports facilityYes-
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesYes-
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesYes-
Provision for lodging of management staff and security staffYes-
Water conservation and renewable energyYes-

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area8,053 sq m
Named landowners1
LandownerVillageDistrict
Sri N PRAKASH and OTHERS--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 80.25 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSri A Dellibabu
EngineerShri H G NAIKAR

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionMar 2023 → Dec 2023

No reason recorded in the filing

EX/PRM/KA/RERA/1251/309/PR/231207/003253Dec 2023 → Dec 2024

Reason as filed by the promoterShortage of Building Materials, Concrete, Jalli etc

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed147

As listed on the registration, under the names the promoter filed them with; the newest 80 of 147 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/309/PR/200205/003253 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
AAI NOCFile: AAI NOC for SS Phase-II.pdf6 May 2022
BESCOM NOCFile: NOC BESCOM.pdf6 May 2022
Certificate from Registered Engineer indicating the structural safety of the buildingFile: Certificate from Registered Engineer indicating the structural safety of the building.pdf6 May 2022
commencement certificateFile: Commencement Certificate.pdf19 Feb 2022
BESCOM NOCFile: NOC BESCOM - Phase II.pdf19 Feb 2022
AAI NOCFile: NOC AAI.pdf19 Feb 2022
Certificate from Registered EngineerFile: Structural Engineer Certificate.pdf19 Feb 2022
Modified Approved PlansFile: Modified Approved Plans.PDF4 Feb 2022
NOC BBMP ModifiedFile: NOC BBMP Modified.pdf4 Feb 2022
Commencement CertificateFile: Commencement Certificate.pdf4 Feb 2022
Development DetailsFile: Development Details.pdf4 Feb 2022
Total Land-Site Area DetailsFile: Total Land-Site Area Details.pdf4 Feb 2022
NOC BESCOM - Phase IIFile: NOC BESCOM - Phase II.pdf4 Feb 2022
Certificate from Registered Engineer Certificate,File: Certificate from Registered Engineer Certificate,.pdf4 Feb 2022
CA CertificateFile: Form 4 CA Certificate Modification.pdf14 Jan 2022
Architect CertificateFile: Form 5 Architect Certificate Modifications.pdf14 Jan 2022
Engineer CertificateFile: Form 6 Engineer Certificate Modification.pdf14 Jan 2022
Quarterly Update DetailsFile: Quarterly Update Details.pdf14 Jan 2022
Designated Bank Account DetailsFile: Designated Bank Account Details.pdf14 Jan 2022
Commencement CertificateFile: Commencement Certificate.pdf14 Jan 2022
NOC KSPCBFile: NOC KSPCB.pdf14 Jan 2022
Modified Plan B&D Block or WingsFile: Modified Plan B&D Block or Wings.pdf14 Jan 2022
Sold and Unsold units detailsFile: Sold and Unsold units details.pdf14 Jan 2022
Structural Engineer CertificateFile: Structural Engineer Certificate.pdf14 Jan 2022
Block C Development DetailsFile: Block C Development Details.pdf14 Jan 2022
Balance Sheet for the year 2018-19File: Balance Sheet 2018-19.pdf23 Jan 2020
Notarized form-BFile: Form-B, Affidavit Notarized.pdf23 Jan 2020
Form B NoatarisedFile: Form B Affidavit Notarized.pdf23 Jan 2020
Balance Sheet 2018-19File: Directors Report.pdf18 Jan 2020
Directors Report 2017File: Director Report 2016-17.pdf18 Jan 2020
Directors Report 2018File: Directors Report.pdf18 Jan 2020
Directors Report 2019-File: Directors Report 2018-19.pdf18 Jan 2020
Bank Pass BoolFile: Bank Pass Book.pdf18 Jan 2020
Sale Deed 3/9 & 3/10File: Sale Deed-3-9 & 3-10.pdf18 Jan 2020
Notarized form-BFile: Form-B, Declaration Notarized.pdf18 Jan 2020
BBMP License CopyFile: BBMP License.pdf18 Jan 2020
Approved Sanction PlanFile: Approved Sanction Plan of Sushantham Phase-II.pdf18 Jan 2020
KSPCB NocFile: NOC KSPCB.pdf18 Jan 2020
Already registered project ongoing detailsFile: REGISTRATION CERTIFICATE.pdf-
Modified plan details site plan, floor plans, Plan Licence LetterFile: Modified Plan B&D Block-Wings (Existing).pdf-
Elevation, Sections, Specifications ( If changes are there )File: Elevations,Specifications if changes any.pdf-
List Of AllotteesFile: List Of Allottes.pdf-
List Of ComplaintsFile: list of compliants.pdf-
Consent LetterFile: Consent Letter.pdf-
List Of Pending LitigationsFile: List of pending Litigations.pdf-
Chartered Accountant CertificateFile: Form -4, CA Certificate Modification.pdf-
Notarized AffidavitFile: Affdavit.pdf-
Engineer CertificateFile: Form -6, Engineer Certificate Modification.pdf-
Architect CertificateFile: Form -5, Architect Certificate Modifications.pdf-
Structural Engineer Certificate for stability of structureFile: Form -6, Engineer Certificate Modification.pdf-
Modification of Plan DetailsFile: Approved Building Plan.pdf-
Modification of Plan DetailsFile: Approved Sanction Plan B&D Block-Wings (Existing).pdf-
Modification of Plan DetailsFile: Commencment Certificate.pdf-
Modification of Plan DetailsFile: Commencment Certificate.pdf-
Modification of Plan DetailsFile: Total units, Sold and Unsold units details.pdf-
Modification of Plan DetailsFile: Total units, Sold and Unsold units details.pdf-
Architect Certificate for Work Completion Schedule till DateFile: Form-Ex1 Architect Certificate For Status of Work As On Date.pdf-
Engineer Certificate for Work Completion Schedule till DateFile: Form-Ex5 Engineers Certificate for Status of Work as on date.pdf-
CA Certificate for Funds UtilizationFile: Form-Ex3 Chartered Accountant Certificate For Fund Utilization.pdf-
Architect Certificate for Pending Work Completion Schedule.File: Form-Ex2 Architect Certificate For Pending Work As On Date.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: Form-Ex6 Engineers Certifictae for Pending work as on date.pdf-
CA Certificate for Funds required for Project CompletionFile: Form-Ex4 Chartered Accountant Certificate For Fund Required.pdf-
AffidavitFile: Form-Ex7 Affidavit for seeking extension of registered project.pdf-
Latest Encumbrance CertificateFile: Encumbrance Certificate (2).pdf-
Details Of Sold/ Un-sold UnitsFile: Units Sold and Unsold Details.xlsx-
Document 1File: ENCUMBRANCE CERTIFICATE.pdf-
Document 2File: COMMENCEMENT CERTIFICATE (PRJ -5953).pdf-
Document 3File: NOC BWSSB.pdf-
Document 4File: NOC MOEF.pdf-
Commencement Certificate-
Approved Layout Plans-
Proforma of Sale Deed-
Proforma of Agreement of Sale-
Sale Deed - RTC-
Approved Section of Building-
Area Development Plan of Project area-
Proforma Of Allotment Letter-
Brochure-
Project Specification-
Encrumbrance Certificate-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one moved by 21 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep SUMADHURA SUSHANTHAM PHASE II on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmSUMADHURA SUSHANTHAM PHAOther 45Dot size: filed unitsN

Filed coordinates, straight-line distance. 45 registered projects within 2 km.

Builder: SUMADHURA INFRACON PRIVATE LIMITED

SUMADHURA INFRACON PRIVATE LIMITED has 21 registrations on RERA Karnataka, including Sumadhura Belfort and SUMADHURA SUSHANTHAM PHASE I. Its filings declare 16 earlier projects, 11 of them declared completed. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if SUMADHURA SUSHANTHAM PHASE II is delayed beyond 30 Dec 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of SUMADHURA SUSHANTHAM PHASE II?

The registered promoter entity is SUMADHURA INFRACON PRIVATE LIMITED, a company as per the filing. Its CIN U45200KA2012PTC062071 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in SUMADHURA SUSHANTHAM PHASE II?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SUMADHURA SUSHANTHAM PHASE II?

The professionals named in the filing: Architect: Sri A Dellibabu; Engineer: Shri H G NAIKAR. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SUMADHURA SUSHANTHAM PHASE II?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SUMADHURA SUSHANTHAM PHASE II. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SUMADHURA SUSHANTHAM PHASE II to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.