Home / Browse projects / Bengaluru Urban, Karnataka / SUMADHURA SOHAM PHASE II
SUMADHURA SOHAM PHASE II
By SUMADHURA INFRACON PRIVATE LIMITED
RG-KA-68696 · RERA PRM/KA/RERA/1251/446/PR/190423/002529
Source: official RERA Karnataka filing
Red flags
- No red flags in this filing
Clear
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
SUMADHURA SOHAM PHASE II is a Residential/Group Housing project by SUMADHURA INFRACON PRIVATE LIMITED in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/190423/002529 on 23 Apr 2019. Possession is promised by 30 Sep 2019.
At a glance
Project
- NameSUMADHURA SOHAM PHASE II
- TypeResidential/Group Housing
- Location
- Bengaluru East
- Bengaluru Urban
- PincodeNot stated
- RERA no.PRM/KA/RERA/1251/446/PR/190423/002529
- ReraGenie IDRG-KA-68696
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on23 Apr 2019
- Promised completion30 Sep 2019
- Revised completionNone
- Buildings2 building records
- Documents filed69 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| WING A | - | - | - | 20 | 0 | 20 |
| WING P | - | - | - | 20 | 0 | 20 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building:
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Retaining wall (All types) | - |
| Plinth level Beam | - |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | - |
| RCC or MS Framed structure | - |
| Masonry construction: Bricks, Concrete blocks etc | - |
| Plastering inside , outside & Ceiling | - |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Fire prevention and fire fighting fitting and fixture with network | Not applicable |
| Weather Proof work(tile,concrete) | - |
| Painting | - |
| Elevation work | - |
| Internal and External work including landscapes as per santioned drawings | - |
Progress on shared amenities41
Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Internal Roads & Footpaths | Yes | - |
| Sewage and Drainage System | Yes | - |
| Parks & Tree planting | Yes | - |
| Street Lighting | Yes | - |
| Provision for community buildings and for treatment and disposal of sewage and sullage water | Yes | - |
| Solid waste management and disposal | Yes | - |
| Water conservation | Yes | - |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | Yes | - |
| Education/Health/Other public amenities | Yes | - |
| Electricity supply transformer and substation | Yes | - |
| Emergency Evacuation services | No | Not applicable |
| Storm water drains | Yes | - |
| Use of renewable energy | Yes | - |
| Water conservation/rain water harvesting/recharge of ground water | Yes | - |
| Electricity | Yes | - |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | - |
| Club House | Yes | - |
| Community Hall | Yes | - |
| Outdoor Sports facility | Yes | - |
| Indoor Sports facility | Yes | - |
| Swimming Pool | Yes | - |
| Gym | Yes | - |
| Parks | Yes | - |
| Power Backup | Yes | - |
| Gas | No | Not applicable |
| Water and Sanitation | Yes | - |
| Air Conditioning And incerntion | Yes | - |
| Staircases | Yes | - |
| Lifts | Yes | - |
| Staircases and Lift lobbies, corridor,lobbies, corridor | Yes | - |
| Fire escapes | No | Not applicable |
| Common entrance and exit for the building / common portico/foyer/verandah | Yes | - |
| Basement | Yes | - |
| Terrace | Yes | - |
| Outer Wall | Yes | - |
| Open parking areas and common storage spaces | Yes | - |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | Yes | - |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | DELLIBABU A |
| Engineer | D.SRINIVAS & ASSOCIATES |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed69
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/190423/002529 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| CertificateFile: Certificate of incorporation.pdf | - |
| Commencement Certificate | - |
| Approved Building Sanction Plans for Query Reply | - |
| Approved layout Plan | - |
| Proforma of Sale Deed | - |
| Proform of Agreement of Sale | - |
| Sale Deed & RTC | - |
| Approved building Plotting plan | - |
| Area Development Plan | - |
| Proforma of Allotment Letter | - |
| Brochure | - |
| All Noc Doc | - |
| Project Specification | - |
| Encumbrance Certificate | - |
| Notarised Affidavit 3(1) query relied | - |
| JD AFFIDAVIT CUM DECLARATION | - |
| Katha&Extract -SIPL | - |
| Land Doc & Location | - |
| Land Doc & Location | - |
| Conversion Order 7-2007-08 | - |
| Noc BBMP License | - |
| TDR Utilisation Certificates | - |
| TDR Certificates | - |
| Relianquishment Deed | - |
| Noc Bwssb | - |
| Noc Kspcb (CFO) | - |
| Noc EC | - |
| Letter for Clarification of Area diffrence | - |
| Approved Section of Building | - |
| Approved layout Plan | - |
| Approved Section of Building | - |
| Conversion Order 7-2007-08 | - |
| Advocate Search Report | - |
| Balance Sheet 2017 - 2018File: Balance Sheet.pdf | - |
| Balance Sheet 2016 - 2017File: Balance Sheet 2016-17.pdf | - |
| Balance Sheet 2015 - 2016File: Balance Sheet 2015-16.pdf | - |
| Audited Profit and Loss Statement 2017 - 2018File: Audit & Profit & Loss AC.pdf | - |
| Audited Profit and Loss Statement 2016 - 2017File: Audit P&L 2016-17.pdf | - |
| Audited Profit and Loss Statement 2015 - 2016File: Audit P&L 2015-16.pdf | - |
| Director's Report 2017 - 2018File: Directors Report.pdf | - |
| Director's Report 2016 - 2017File: Director Report 2016-17.pdf | - |
| Director's Report 2015 - 2016File: Directors Report-2015-16.pdf | - |
| Cash Flow Statement 2017 - 2018File: Cash Flow Statement.pdf | - |
| Cash Flow Statement 2016 - 2017File: Cash Flow Statement-FY 2016-17.pdf | - |
| Auditor's Report 2017 - 2018File: Auditors Report.pdf | - |
| Auditor's Report 2016 - 2017File: Audit Report 2016-17.pdf | - |
| Auditor's Report 2015 - 2016File: Auditor Report-2015-16.pdf | - |
| Income Tax Return Acknowledgement 2017 - 2018File: IT Acknowledgement.pdf | - |
| Income Tax Return Acknowledgement 2016 - 2017File: Income Tax Ack 2016-17.pdf | - |
| Income Tax Return Acknowledgement 2015 - 2016File: IT Return Ack 2015-16.pdf | - |
| Declaration Form-B | - |
| Prospectus/BrochureFile: Brochure (Phase-II).pdf | - |
| Advertisement Copy 1File: Advertisement Copy.pdf | - |
| Tower Excel SheetFile: PRM_KA_RERA_1251_446_PR_190423_002529.xlsx | - |
| Stability CertificateFile: Structural Stability Certificate-Soham-II.pdf | - |
| Road cutting permission letter issued by the planning Authority for laying Water supply line, sanitary line, UFile: 01 SITE PLAN.pdf | - |
| NOC issued by the Fire Force department after completion of workFile: NOC issued by the Fire Force.pdf | - |
| Occupancy CertificateFile: Occupancy Certificate Phase-II.pdf | - |
| Consent for operation issued by KSPCBFile: NOC Kspcb (CFO).pdf | - |
| Certificate of operation for lifts issued by the Chief of Department of Electrical inspectorate Government of File: LIFT Erection Approval.pdf | - |
| Sanctioned Letter issued by concerned ESCOM of Power sanction and details of transformer installed and whetherFile: Electrical Power Installation Approval.pdf | - |
| Sanctioned letter issued by concerned water supply and sanitary board for the projectFile: NOC Bwssb.PDF | - |
| Details of external infrastructure work such as drive way, play area, park, STP and water treatment plant, WheFile: 01 SITE PLAN.pdf | - |
| Common Area and other amenities facilities are completed or not and details of handling over of the same to asFile: DOD.pdf | - |
| Details of undivided share of land handed over to the association of allotteesFile: DOD.pdf | - |
| Architect certificate for having completed the work(in format no 5)File: Form-5 Architect Certificate-Soham-II.pdf | - |
| Chartered Accountant certificate for having completed the work(in format no 4)File: Form-4 CA Certfct for CC.pdf | - |
| Affidavit cum declaration from promoter for having completed the project as per specification and as per adverFile: Affidavit.pdf | - |
| Guideline Value Whitefiled Village ECC RoadFile: Guideline Value Whitefiled Village.pdf | - |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Status | Promised | Delivered |
|---|---|---|---|---|
| Sumadhura Nandanam | - | Ongoing | Dec 2021 | Not delivered |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep SUMADHURA SOHAM PHASE II on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Prestige Park Grove
PRESTIGE PROJECTS PRIVATE LIMITED
Prestige Lakeside Habitat
Prestige Habitat Ventures
LivingTree by Kalyani Developers
Kalyani Tech Park Private Limited
PRESTIGE FALCON CITY
PRESTIGE NOTTINGHILL INVESTMENTS
SATTVA CITY
SATTVA CITY PRIVATE LIMITED
GM AMBITIOUS ENCLAVE
M/s. Allam Infinite India Private Limited
See every Bengaluru Urban project, with the district possession charts
Builder: SUMADHURA INFRACON PRIVATE LIMITED
SUMADHURA INFRACON PRIVATE LIMITED has 21 registrations on RERA Karnataka, including Sumadhura Belfort and SUMADHURA SUSHANTHAM PHASE I. Its filings declare 16 earlier projects, 11 of them declared completed. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if SUMADHURA SOHAM PHASE II is delayed beyond 30 Sep 2019?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of SUMADHURA SOHAM PHASE II?
The registered promoter entity is SUMADHURA INFRACON PRIVATE LIMITED, a company as per the filing. Its CIN U45200KA2012PTC062071 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in SUMADHURA SOHAM PHASE II?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at SUMADHURA SOHAM PHASE II?
The professionals named in the filing: Architect: DELLIBABU A; Engineer: D.SRINIVAS & ASSOCIATES. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SUMADHURA SOHAM PHASE II?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback