Home / Browse projects / Buldana, Maharashtra / SUKHKARTA TOWERS
SUKHKARTA TOWERS
By SUKHKARTA BUILDERS AND DEVELOPERS
RG-MH-02562 · RERA P50000029197 · Last updated on MahaRERA portal: 9 Nov 2024
Source: official MahaRERA filing
Red flags
- Completion date moved by 6 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Buldana registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SUKHKARTA TOWERS is a Residential / Group Housing project by SUKHKARTA BUILDERS AND DEVELOPERS in Buldana, Maharashtra, registered with MahaRERA as P50000029197 on 3 May 2021. The registration is recorded completed; possession was promised by 30 Sep 2023. The completion date has moved by 6 months from the original filing.
At a glance
Project
- NameSUKHKARTA TOWERS
- TypeResidential / Group Housing
- Location
- CHIKHLI ROAD
- NEAR KHONDEWADI
- Yelgaon
- Buldana
- 443001
- Pincode443001
- RERA no.P50000029197
- ReraGenie IDRG-MH-02562
Builder
- NameSUKHKARTA BUILDERS AND DEVELOPERS
- Entity typePartnership
- PartnerGOPAL PANDURANG PANDIT
- Other registrations2 more →
- Completed3 of 3
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on3 May 2021
- Promised completion30 Sep 2023
- Revised completionRevised to 30 Sep 2023 (originally 31 Mar 2023)
- Buildings2 building records
- Documents filed27 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SUKHKARTA TOWERS A WING | NA | 5 | 0 | 0 | 0 | 0 |
| SUKHKARTA TOWERS B WING | NA | 5 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 9 Nov 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
22 of 22 construction stages are filed complete across 2 buildings.
SUKHKARTA TOWERS A WING100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
SUKHKARTA TOWERS B WING100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 9 Nov 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 100% |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | ANIKET ASHRUBA SHEWALE |
| Architect | PRAFULLA PUNDLIK NARKHEDE |
| Engineer | ASHVIN AMBADAS SATPUTE |
| Chartered Accountant | SHAH BAHETI CHANDAK AND CO |
| Partner | Role in project |
|---|---|
| SUKHKARTA BUILDERS AND DEVELOPERS | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDue to covid 2nd and 3rd wave ,the work is delay little bit , now the work is almost complete , we have submit complition report to Dy, Director of town planning but yet we have not got accupancy certificate , so we are requisting some period extension ,kindly grant it sir please.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 2 May 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 3 Apr 2021 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 3 Apr 2021 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 3 Apr 2021Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 5 Aug 2023
Documents filed27
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Status of Formation of Legal Entity (Society/Co Op etc.)File: society (1).pdf | 9 Nov 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: SDSM-PRINT124031311080.pdf | 13 Mar 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: G.pdf | 5 Aug 2023 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: B.pdf | 5 Aug 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: UIHIHNUIH.pdf | 20 Apr 2023 |
| Disclosure of sold/ booked inventoryFile: SAADAD.pdf | 20 Apr 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 CERTIFICATE.pdf | 20 Apr 2023 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 11.pdf | 13 Apr 2023 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 11.pdf | 20 Mar 2023 |
| Copy of the legal title reportFile: LEGAL TITAL REPORT.pdf | 2 May 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: C A FORM.pdf | 2 May 2021 |
| Proforma of Allotment letterFile: ALLOTMENT LETTAR.pdf | 2 May 2021 |
| Layout approvalFile: GG.pdf | 3 Apr 2021 |
| Building plan approvalFile: PLAN.pdf | 3 Apr 2021 |
| PAN CardFile: PAN.pdf | 3 Apr 2021 |
| Copy of the legal title reportFile: LIGAL SEARCH REPORT.pdf | 3 Apr 2021 |
| Details of encumbrancesFile: encumbrances.pdf | 3 Apr 2021 |
| Copy of Layout Approval (in case of layout)File: GG.pdf | 3 Apr 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: PLAN.pdf | 3 Apr 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: COM CERT.pdf | 3 Apr 2021 |
| Declaration in FORM BFile: FORM B.pdf | 3 Apr 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certi 001.pdf | 3 Apr 2021 |
| Proforma of Allotment letterFile: img199.pdf | 3 Apr 2021 |
| Proforma of Allotment letterFile: img199.pdf | 3 Apr 2021 |
| OtherFile: 1.pdf | 3 Apr 2021 |
| OtherFile: 2.pdf | 3 Apr 2021 |
| OtherFile: 3.pdf | 3 Apr 2021 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Buldana
Computed across the 58 Buldana projects on ReraGenie, from their own filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 2 other registrations, which the RERA portal never shows together
- All 27 filed documents as one ZIP, foldered, with a manifest
Keep SUKHKARTA TOWERS on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near NEAR KHONDEWADI58 in Buldana
EKDANT RESIDENCY PHASE 4
EKDANT BUILDERS
Anand Mangal
Sumit Sahebrao Sardar
ANAND SAGAR RESIDENCY
ASHOK SATYANARAYAN VYAS
ANAND TOWER
SUMITKUMAR SAHEBRAO SARDAR
BULDANA PRIDE CONSTRUCTION
BULDANA PRIDE CONSTRUCTION
Construction of 268 EWS 20 MIG and 16 HIG T/s
Amravati Housing And Area Development Boar
See every Buldana project, with the district possession charts
Builder: SUKHKARTA BUILDERS AND DEVELOPERS
SUKHKARTA BUILDERS AND DEVELOPERS has 3 registrations on MahaRERA, including DREAM HOME and SUKHAKARTA PRIME CITY ROW HOUSES. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Buldana district page.
Frequently asked questions
What are my rights if SUKHKARTA TOWERS is delayed beyond 30 Sep 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SUKHKARTA TOWERS?
The registered promoter entity is SUKHKARTA BUILDERS AND DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SUKHKARTA TOWERS?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for SUKHKARTA TOWERS?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SUKHKARTA TOWERS?
The professionals named in the filing: Architect: ANIKET ASHRUBA SHEWALE; Architect: PRAFULLA PUNDLIK NARKHEDE; Engineer: ASHVIN AMBADAS SATPUTE; Chartered Accountant: SHAH BAHETI CHANDAK AND CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SUKHKARTA TOWERS?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback