Home / Browse projects / Bengaluru Urban, Karnataka / SUKALPA LEGACY

Registration approved No litigation declared Residential/Group Housing project

SUKALPA LEGACY

By SUKALPA PARK VIEW

RG-KA-66426 · RERA PRM/KA/RERA/1251/310/PR/141026/009024 · Last updated on RERA Karnataka portal: 9 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Dec 2028Possession promisedno revision filed
0Complaints at RERA Karnatakaon this registration
Jump to the 56 documents Report an error

SUKALPA LEGACY is a Residential/Group Housing project by SUKALPA PARK VIEW in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/141026/009024 on 14 Oct 2026. Possession is promised by 31 Dec 2028.

At a glance

Project

  • NameSUKALPA LEGACY
  • TypeResidential/Group Housing
  • Location
    • Bengaluru South
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/310/PR/141026/009024
  • ReraGenie IDRG-KA-66426

Builder

  • NameSUKALPA PARK VIEW
  • Entity typePartnership Firm
  • GSTIN29AFSFS8787D1ZY
  • Authorized SignatoryB. RAMESH

Key dates

this monthRegisteredOct 2026PromisedDec 2028

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on14 Oct 2026
  • Promised completion31 Dec 2028
  • Revised completionNone
  • Buildings1 building record
  • Documents filed56 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Sukalpa Legacy---54054

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 9 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Upto Plinth Level-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
Retaining wall (All types)-
RCC or MS Framed structure-
Masonry Construction-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Painting-
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work-
Internal and External work including landscapes as per sanctioned drawings-

Progress on shared amenities40

As on 9 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Sewage and Drainage SystemYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
Energy managementYes-
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalYes-
Emergency Evacuation servicesYes-
Internal Roads & FootpathsNoNot applicable
Electricity supply transformer and substationYes-
Storm water drainsYes-
Use of renewable energyYes-
Sewage Treatment Plant (STP)NoNot applicable
Parks & Tree plantingNoNot applicable
Street LightingYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymYes-
ParksYes-
Power BackupNoNot applicable
Piped GasNoNot applicable
Water and SanitationYes-
Air ConditioningNoNot applicable
StaircasesYes-
LiftsYes-
Corridor/LobbiesYes-
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes-
Common storage spacesNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Named landowners1
LandownerVillageDistrict
Sukalpa Park View--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 28.79 cr
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 25.99 cr-
Principal sum and interest payable to financial institutions-Scheduled BanksRs 1.50 cr-
On-site expenditure-Site OverheadRs 40.00 lakh-
On-site expenditure-Cost Of Services(Water, Electricity, Sewage)Rs 40.00 lakh-
On-site expenditure-Consultants FeesRs 30.00 lakh-
On-site expenditure-Salaries of workersRs 20.00 lakh-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDisha K. N.
EngineerArun Kumar S. R.
Chartered AccountantL. Sathish Kumar

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed56

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/141026/009024 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Affidavit for Water supply assurance to allotteesFile: Affidavit.pdf9 Oct 2026
Project - Sewer Line Drawing along with Eng SignatureFile: Sewer Line Drawing.pdf9 Oct 2026
EC Till UptodateFile: EC till uptodate.pdf30 Sep 2026
Land Calculation Sheet_Guidance ValueFile: Land Calc Sheet_Guidance Value.pdf30 Sep 2026
RTC, survey 13/5B-
Mutation, survey 13/5B-
Encumbrance Certificate, survey 13/5B-
Conversion/Alienation Order, survey 13/5B-
Sale/Title/Gift Deed, survey 13/5B-
Khatha, survey 13/5B-
Registration CertificateFile: Form C.pdf-
GST CertificateFile: GST Certificate.pdf-
Partnership DeedFile: Partnership Deed.pdf-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Certificate issued by CA Form 1File: Form 1.pdf-
Certificate issued by Architect Form 2File: Form 2.pdf-
Certificate issued by Engineer Form 3File: Form 3.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: Notarised Affidavit for Non Litigation.pdf-
Approved Letter-
Approved Building Plan-
Sectional Drawing-
Structural Stability Certificate-
Project Specification and Amenities-
Proforma of Agreement for Sale-
Proforma of Allotment Letter-
Notarised Declaration Form B-
Section 3(1) Notarized Affidavit-
Advocate Search Report-
BESCOM NOC-
Water-
CFE-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Estimated Construction Sheet-
Master Plan with Proposed Site Area-
Village MAP with Proposed Site Area-
BDA Residential Layout Plan-
Land Calc Sheet-
Property Tax Receipt-
Form 6-
Project Amenities & Facilities-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep SUKALPA LEGACY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: SUKALPA PARK VIEW

SUKALPA PARK VIEW has 1 registration on RERA Karnataka, including SUKALPA LEGACY. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if SUKALPA LEGACY is delayed beyond 31 Dec 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of SUKALPA LEGACY?

The registered promoter entity is SUKALPA PARK VIEW, a partnership firm as per the filing. Its GSTIN 29AFSFS8787D1ZY can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in SUKALPA LEGACY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SUKALPA LEGACY?

The professionals named in the filing: Architect: Disha K. N.; Engineer: Arun Kumar S. R.; Chartered Accountant: L. Sathish Kumar. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SUKALPA LEGACY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SUKALPA LEGACY. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SUKALPA LEGACY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.