RG-KA-88645 · RERA PRM/KA/RERA/1251/309/PR/210804/004238 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 28 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
Dec 2026Possession promisedmoved 28 months from the original
4 of 17Construction stages donefurthest along: Retaining wall (All types), 95%
60 of 175Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 128 documents Report an error

SUBRAM JADE GARDENS is a Residential/Group Housing project by SUBRAM BUILDERS in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/309/PR/210804/004238 on 4 Aug 2021. Possession is promised by 31 Dec 2026. The completion date has moved by 28 months from the original filing. 115 of the 175 units on this registration are recorded sold or booked, and 4 of 17 construction stages are filed complete.

At a glance

Project

  • NameSUBRAM JADE GARDENS
  • TypeResidential/Group Housing
  • Location
    • Bengaluru North
    • Bengaluru Urban
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/309/PR/210804/004238
  • ReraGenie IDRG-KA-88645

Builder

  • NameSUBRAM BUILDERS
  • Entity typeProprietorship Firm
  • Authorized SignatoryBALAJI SUBRAMANYAM
  • OthersBALAJI SUBRAMANYAM

Key dates

this monthRegisteredAug 2021First promiseAug 2024Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on4 Aug 2021
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 31 Aug 2024)
  • Buildings3 building records
  • Documents filed128 files

Current status

66%115 of 175 units booked
10.1%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Block A---70070
Block B---10010
Block C---95095

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 17 construction stages are filed complete. The stage furthest along is Retaining wall (All types), at 95%.

Building: 79% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Retaining wall (All types)95%
Plinth level Beam100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)90%
RCC or MS Framed structure100%
Masonry construction: Bricks, Concrete blocks etc95%
Plastering inside , outside & Ceiling95%
Joinery: Doors, Windows, Ventilators etc70%
Basic work of Water supply, Sanitary and Electrification35%
Dadoing, Skirting, Flooring, Tiles work (All types)75%
Railing and Grill fixing60%
Electrification, Water supply and Sanitary Finishing65%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)60%
Painting60%
Elevation work95%
Internal and External work including landscapes as per santioned drawings50%

Progress on shared amenities41

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes70%
Internal Roads & FootpathsYes50%
Sewage and Drainage SystemYes80%
Parks & Tree plantingYes20%
Street LightingYes0%
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes35%
Solid waste management and disposalYes0%
Water conservationYes25%
Energy managementYes25%
Fire protection and fire safety requirementsYes0%
Education/Health/Other public amenitiesNoNot applicable
Electricity supply transformer and substationYes0%
Emergency Evacuation servicesNoNot applicable
Storm water drainsYes0%
Use of renewable energyYes0%
Water conservation/rain water harvesting/recharge of ground waterYes0%
ElectricityYes40%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes30%
Club HouseYes40%
Community HallYes60%
Outdoor Sports facilityYes0%
Indoor Sports facilityYes0%
Swimming PoolYes0%
GymYes0%
ParksYes0%
Power BackupYes0%
GasNoNot applicable
Water and SanitationYes0%
Air Conditioning And incerntionNoNot applicable
StaircasesYes80%
LiftsYes55%
Staircases and Lift lobbies, corridor,lobbies, corridorYes55%
Fire escapesNoNot applicable
Common entrance and exit for the building / common portico/foyer/verandahYes60%
BasementYes80%
TerraceNoNot applicable
Outer WallYes90%
Open parking areas and common storage spacesYes60%
Provision for lodging of management staff and security staffYes25%
Water conservation and renewable energyYes0%

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area12,241 sq m
Named landowners1
LandownerVillageDistrict
India--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 72.00 cr
Cost incurredRs 7.26 cr
Spent of the estimate10.08%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 45.00 crRs 4.00 cr
Payment of PremiumsRs 11.00 cr-
On-site expenditure-Consultants FeesRs 5.00 crRs 78.85 lakh
On-site expenditure-Site OverheadRs 3.00 crRs 10.94 lakh
On-site expenditure-Cost Of Services(Water, Electricity, Sewage)Rs 2.50 crRs 2.54 lakh
Payment of feesRs 2.50 crRs 2.20 lakh
On-site expenditure-Salaries of workersRs 2.00 crRs 6.36 lakh
Payment of taxesRs 50.00 lakhRs 67.13 lakh
Payment of cessRs 50.00 lakh-

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMrs.Shailaja Srinath
EngineerMr.Papanna Setty T N

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EX/PRM/KA/RERA/1251/309/PR/241030/004238Aug 2024 → Aug 2025

Reason as filed by the promoterForce Majeure; Force Majeure; Applied for modification

ExtensionAug 2025 → Dec 2026

No reason recorded in the filing

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed128

As listed on the registration, under the names the promoter filed them with; the newest 80 of 128 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/309/PR/210804/004238 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: CA Certificate.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Architect Certificate.pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Engineer Certificate.pdf15 Oct 2026
Q2 2026-27 Water supply and sewage board15 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Oct 2026
Q2 2026-27 KSPCB- MOEF (Above 50 Acres)15 Oct 2026
Q2 2026-27 KPTCL- BESCOM15 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: CA Certificate.pdf14 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Architect Certificate.pdf14 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Engineer Certificate.pdf14 Jul 2026
Q1 2026-27 Water supply and sewage board14 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)14 Jul 2026
Q1 2026-27 KSPCB- MOEF (Above 50 Acres)14 Jul 2026
Q1 2026-27 KPTCL- BESCOM14 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: CA Certificate.pdf25 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Architect Certificate.pdf25 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Engineer Certificate.pdf25 Apr 2026
Q4 2025-26 Water supply and sewage board25 Apr 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)25 Apr 2026
Q4 2025-26 KSPCB- MOEF (Above 50 Acres)25 Apr 2026
Q4 2025-26 KPTCL- BESCOM25 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: CA Certificate.pdf14 Feb 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Architect Certificate.pdf14 Feb 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Engineer Certificate.pdf14 Feb 2026
Q3 2025-26 Water supply and sewage board14 Feb 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)14 Feb 2026
Q3 2025-26 KSPCB- MOEF (Above 50 Acres)14 Feb 2026
Q3 2025-26 KPTCL- BESCOM14 Feb 2026
For BWSSB NOCFile: For BWSSB NOC Req.pdf6 Jul 2021
For KSPCB NOCFile: For KSPCB NOC Req.pdf6 Jul 2021
KSPCB NOCFile: KSPCB NOC Online.pdf26 Jun 2021
BWSSB NOCFile: BWSSB NOC Online and Acknowledgment.pdf26 Jun 2021
1.CA UDIN number for financial year 2019-20File: Balance sheet AY 20-21 with UDIN.pdf12 Jun 2021
2.Conversion OrderFile: Conversion Order.pdf12 Jun 2021
3.Ground Floor PlanFile: Ground Floor Plan.pdf12 Jun 2021
4.Basement PlanFile: Basement Plan.pdf12 Jun 2021
5.Site PlanFile: Site Plan.pdf12 Jun 2021
6.BWSSB Noc NAFile: BWSSB NOC.pdf12 Jun 2021
7.Project Member detailsFile: Project Key Members.pdf12 Jun 2021
CertificateFile: GST Certificate.pdf-
Project Details-
Modified plan details site plan, floor plans, Plan Licence LetterFile: JADE GARDENS cc_BBMP_EoDB_CH_26927_24-25.pdf-
Elevation, Sections, Specifications ( If changes are there )File: Plan Drawing - Site Plan.pdf-
List Of AllotteesFile: CA Certificate.pdf-
Consent LetterFile: Submitted at the earliest.pdf-
Chartered Accountant CertificateFile: CA Certificate.pdf-
Notarized AffidavitFile: Affidavit RERA.pdf-
Engineer CertificateFile: Engineer Certificate.pdf-
Architect CertificateFile: Architect Certificate.pdf-
Structural Engineer Certificate for stability of structureFile: Structure Certificate.pdf-
Modification of Plan DetailsFile: BBMP Sanction Plan.pdf-
Modification of Plan DetailsFile: Plan Drawing - Site Plan.pdf-
Modification of Plan DetailsFile: BBMP Commencement Certificate.pdf-
Modification of Plan DetailsFile: BBMP Commencement Certificate.pdf-
Modification of Plan DetailsFile: Unit List.xlsx-
Modification of Plan DetailsFile: Unit List.xlsx-
Document 1File: BESCOM NOC.pdf-
Document 2File: BWSSB NOC.pdf-
Document 3File: KSPCB.pdf-
Document 4File: MOEF NOC_compressed.pdf-
Architect Certificate for Work Completion Schedule till DateFile: Architect Certificate - Work Completed.pdf-
Engineer Certificate for Work Completion Schedule till DateFile: Engineer Certificate - Work Completed.pdf-
CA Certificate for Funds UtilizationFile: CA Certificate - Funds Spent - Compressed.pdf-
Architect Certificate for Pending Work Completion Schedule.File: Architect Certificate - Pending Work.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: Engineer Certificate - Pending Work.pdf-
CA Certificate for Funds required for Project CompletionFile: CA Certificate - Funds Required.pdf-
AffidavitFile: Affidavit Form EX7.pdf-
Latest Encumbrance CertificateFile: Encumbrance Certificate.pdf-
Consent letter from 2/3rd of AllotteesFile: Allottees Consent.pdf-
Details Of Sold/ Un-sold UnitsFile: SoldUnsoldDetails Format.xlsx-
BBMP Commencement Certificate-
Approved Layout Plan Gfloor-
Sale Deed Draft-
Proforma SALE Agreement Draft-
Sale deed 1987 Gift Deed and RTC-
Section drawing of Apartments-
Area Development Plan typical-
Performa Allotment Letter-
Subram Jade Gardens Brochure-
Project Specification-

How this compares with Bengaluru Urban

66%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one moved by 28 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep SUBRAM JADE GARDENS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmSUBRAM JADE GARDENSOther 11Dot size: filed unitsN

Filed coordinates, straight-line distance. 11 registered projects within 2 km.

Builder: SUBRAM BUILDERS

SUBRAM BUILDERS has 1 registration on RERA Karnataka, including SUBRAM JADE GARDENS. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if SUBRAM JADE GARDENS is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of SUBRAM JADE GARDENS?

The registered promoter entity is SUBRAM BUILDERS, a proprietorship firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in SUBRAM JADE GARDENS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SUBRAM JADE GARDENS?

The professionals named in the filing: Architect: Mrs.Shailaja Srinath; Engineer: Mr.Papanna Setty T N. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SUBRAM JADE GARDENS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SUBRAM JADE GARDENS. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SUBRAM JADE GARDENS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.