Home / Browse projects / Bengaluru Urban, Karnataka / Stonebridge Grand Maxoria

Registration approved No litigation declared Residential/Group Housing project

Stonebridge Grand Maxoria

By M/s Stonne Bridge Constructions Private Limited

RG-KA-46636 · RERA PRM/KA/RERA/1251/309/PR/271026/009041 · Last updated on RERA Karnataka portal: 18 Aug 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Jul 2029Possession promisedno revision filed
0Complaints at RERA Karnatakaon this registration
Jump to the 96 documents Report an error

Stonebridge Grand Maxoria is a Residential/Group Housing project by M/s Stonne Bridge Constructions Private Limited in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/309/PR/271026/009041 on 27 Oct 2026. Possession is promised by 15 Jul 2029.

At a glance

Project

  • NameStonebridge Grand Maxoria
  • TypeResidential/Group Housing
  • Location
    • Bengaluru North
    • Bengaluru Urban
    • 560064
  • Pincode560064
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/309/PR/271026/009041
  • ReraGenie IDRG-KA-46636

Builder

  • NameM/s Stonne Bridge Constructions Private Limited
  • Entity typeCompany
  • CINU68200KA2024PTC187341
  • GSTIN29ABNCS2169K1ZM
  • Authorized SignatoryMr. NAVEEN KUMAR
  • Managing DirectorMrs. ASWINI SATHISH
  • DirectorsMr. NAVEEN KUMAR, Mrs. ASWINI SATHISH
  • Project HeadMr. NAVEEN KUMAR

Key dates

this monthRegisteredOct 2026PromisedJul 2029

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on27 Oct 2026
  • Promised completion15 Jul 2029
  • Revised completionNone
  • Buildings1 building record
  • Documents filed96 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Stonebridge Grand Maxoria---88088

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 18 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Upto Plinth Level-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
Retaining wall (All types)Not applicable
RCC or MS Framed structure-
Masonry Construction-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Painting-
Fire prevention and fire fighting fitting and fixture with network-
Weather Proof work(tile,concrete)-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work-
Internal and External work including landscapes as per sanctioned drawings-

Progress on shared amenities40

As on 18 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Sewage and Drainage SystemYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes-
Solid waste management and disposalYes-
Emergency Evacuation servicesYes-
Internal Roads & FootpathsYes-
Electricity supply transformer and substationYes-
Storm water drainsYes-
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes-
Parks & Tree plantingYes-
Street LightingYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseYes-
Community HallNoNot applicable
Outdoor Sports facilityYes-
Indoor Sports facilityYes-
Swimming PoolYes-
GymYes-
ParksNoNot applicable
Power BackupYes-
Piped GasNoNot applicable
Water and SanitationYes-
Air ConditioningNoNot applicable
StaircasesYes-
LiftsYes-
Corridor/LobbiesYes-
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahYes-
BasementNoNot applicable
TerraceYes-
Outer WallNoNot applicable
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffYes-
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,980 sq m
Named landowners1
LandownerVillageDistrict
Stonne Bridge Constructions Private Limited--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 51.50 cr
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 42.50 cr-
Payment of taxesRs 5.00 cr-
On-site expenditure-Site OverheadRs 2.00 cr-
On-site expenditure-Consultants FeesRs 1.00 cr-
Principal sum and interest payable to financial institutions-Scheduled BanksRs 1.00 cr-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMr. Tata Vittala Srinivas
EngineerMr. Mandhadi Venkataramana Reddy
Chartered AccountantMr. Thatipi Badrinath

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed96

As listed on the registration, under the names the promoter filed them with; the newest 80 of 96 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/309/PR/271026/009041 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Updated total area of land is not matching to approved planFile: TOTAL OPEN AREA Stone.pdf18 Aug 2026
Once again informed to kindly upload elaborated structural stability certificate clearly stating theFile: structural stability certificate stone.pdf18 Aug 2026
Kindly clarify the total extent of land considered in land cost calculation sheet,which is not matchFile: Valuation report stone new.pdf18 Aug 2026
Once again informed to kindly upload the STP/septic tank/soak pit/sewer line drawing with full projFile: stp stone.pdf18 Aug 2026
Once again informed to kindly upload brief project estimation with licenced engineer signature.File: estimate valuation stone.pdf18 Aug 2026
Upload chartered accountant certificate (CA) in prescribed format form -01.File: form 1 stone (1).pdf5 Aug 2026
Upload the bank affidavit in the prescribed format documents.File: bank aff stone.pdf5 Aug 2026
Upload the Notarized Non Litigation AffidavitFile: non liti stone.pdf5 Aug 2026
What are all the sources of funds to complete the project? With supporting documentsFile: Naveen ITR (1)_merged.pdf5 Aug 2026
Upload profit and loss account and balance sheet for 2022-23 and 2023-24 CA certification with scheFile: profit and loss letter stone.pdf5 Aug 2026
notarized affidavit in form-BFile: form b stone.pdf5 Aug 2026
Notarized affidavit regarding all pending or cleared litigations /non-litigation by clearly mentioniFile: non liti stone.pdf5 Aug 2026
Single Plot layout/Development plan Approved by the competent authority (Original and clearly visiblFile: single plot (1) (1).pdf5 Aug 2026
Single Plot layout/Development plan order Approved by the competent authority(Original and clearlyFile: single plot (5).pdf5 Aug 2026
Building License from Local Authority Original Copy.File: cc_BBMP_EoDB_CH_36711_25-26 (1)_260122_205726 (1).pdf5 Aug 2026
Upload all original sanctioned drawings, floor plan, sectional drawings and elevationsFile: PRJ_5847_25-26_260122_205553 (1).pdf5 Aug 2026
Upload commencement certificateFile: CC stone.pdf5 Aug 2026
Demarcation of proposed land in original Village map certified by the competent authorityFile: village map stone.pdf5 Aug 2026
Details of amenities and facilities provided as per plan. thereof including fire fighting facilitiesFile: fire stone.pdf5 Aug 2026
Brochure of the project with amenities detailsFile: Stone Bridge Brochure - V - 2.pdf5 Aug 2026
Kindly correct the taluk details in project address section as per approved plan.File: taluk stone.pdf5 Aug 2026
Cost shown in engineer certificate form-3 is not matching to cost entered in portal as well to CAFile: DocScanner 2 Aug 2026 13-29.pdf5 Aug 2026
Kindly upload project specifications with signature.File: Document 137.pdf5 Aug 2026
Upload the Proforma of agreement (AFS) for sale with duly filling all the required details (designaFile: Sale Agreement Proforma STONEBRIDGE GRAND MAXORIA.pdf5 Aug 2026
Upload Proforma Allotment letter as per the prescribed format duly fill all applicable fields withoFile: allotment letter stone.pdf5 Aug 2026
Kindly upload the project section 3(1) notarised affidavit with project name and project address.File: Document 137 (2).pdf5 Aug 2026
Kindly upload elaborated structural stability certificate clearly stating the number of floors consiFile: NA6 (4).pdf5 Aug 2026
Kindly upload the Land cost calculation sheet as per the guidance value(Self-attested copy) along wiFile: ilovepdf_merged (88).pdf5 Aug 2026
Kindly clarify the main source of water supply to the project along with the supporting documents anFile: water supply noc stone.pdf5 Aug 2026
Kindly upload the STP/septic tank/soak pit/sewer line drawing with full project name and address aloFile: NA6 (4).pdf5 Aug 2026
Kindly upload brief project estimation with licenced engineer signature.File: NA6 (4).pdf5 Aug 2026
RTC, survey 29/2-
Mutation, survey 29/2-
Encumbrance Certificate, survey 29/2-
Conversion/Alienation Order, survey 29/2-
Sale/Title/Gift Deed, survey 29/2-
Khatha, survey 29/2-
Registration CertificateFile: SPICE + Part B_Approval Letter_AA7353991.pdf-
Memorandum of AssociationFile: MOA.pdf-
Article of AssociationFile: aoa.pdf-
GST CertificateFile: GST.pdf-
Organization StructureFile: NA6 (4).pdf-
Certificate issued by CA Form 1File: form 1 stone (1).pdf-
Certificate issued by Architect Form 2File: DocScanner 2 Aug 2026 13-40.pdf-
Certificate issued by Engineer Form 3File: DocScanner 2 Aug 2026 13-29.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: NA6 (4).pdf-
Balance Sheet 2024 - 2025File: stonnebridge Balance sheet_compressed.pdf-
Balance Sheet 2023 - 2024File: NA6 (4).pdf-
Balance Sheet 2022 - 2023File: NA6 (4).pdf-
Audited Profit and Loss Statement 2024 - 2025File: stonnebridge Balance sheet_compressed.pdf-
Audited Profit and Loss Statement 2023 - 2024File: NA6 (4).pdf-
Audited Profit and Loss Statement 2022 - 2023File: NA6 (4).pdf-
Income Tax Return Acknowledgement 2024 - 2025File: Financials F Y 2024-25.pdf-
Income Tax Return Acknowledgement 2023 - 2024File: NA6 (4).pdf-
Income Tax Return Acknowledgement 2022 - 2023File: NA6 (4).pdf-
Director's Report 2024 - 2025File: stonnebridge Balance sheet_compressed.pdf-
Director's Report 2023 - 2024File: NA6 (4).pdf-
Director's Report 2022 - 2023File: NA6 (4).pdf-
Cash Flow Statement 2024 - 2025File: stonnebridge Balance sheet_compressed.pdf-
Cash Flow Statement 2023 - 2024File: NA6 (4).pdf-
Auditor's Report 2024 - 2025File: stonnebridge Balance sheet_compressed.pdf-
Auditor's Report 2023 - 2024File: NA6 (4).pdf-
Auditor's Report 2022 - 2023File: NA6 (4).pdf-
NA6 (4)-
cc_BBMP_EoDB_CH_36711_25-26 (1)_260122_205726-
PRJ_5847_25-26_260122_205553-
NA6 (4)-
NA6 (4)-
NA6 (4)-
NA6 (4)-
NA6 (4)-
NA6 (4)-
NA6 (4)-
NA6 (4)-
NA6 (4)-
suriya law associates-
NOC-ELE-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Stonebridge Grand Maxoria on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmStonebridge Grand MaxoriOther 26Dot size: filed unitsN

Filed coordinates, straight-line distance. 26 registered projects within 2 km.

Builder: M/s Stonne Bridge Constructions Private Limited

M/s Stonne Bridge Constructions Private Limited has 1 registration on RERA Karnataka, including Stonebridge Grand Maxoria. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Stonebridge Grand Maxoria is delayed beyond 15 Jul 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Stonebridge Grand Maxoria?

The registered promoter entity is M/s Stonne Bridge Constructions Private Limited, a company as per the filing. Its CIN U68200KA2024PTC187341 and GSTIN 29ABNCS2169K1ZM can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Stonebridge Grand Maxoria?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Stonebridge Grand Maxoria?

The professionals named in the filing: Architect: Mr. Tata Vittala Srinivas; Engineer: Mr. Mandhadi Venkataramana Reddy; Chartered Accountant: Mr. Thatipi Badrinath. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Stonebridge Grand Maxoria?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Stonebridge Grand Maxoria. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Stonebridge Grand Maxoria to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.