RG-KA-46636 · RERA PRM/KA/RERA/1251/309/PR/271026/009041 · Last updated on RERA Karnataka portal: 18 Aug 2026
Source: official RERA Karnataka filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
Stonebridge Grand Maxoria is a Residential/Group Housing project by M/s Stonne Bridge Constructions Private Limited in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/309/PR/271026/009041 on 27 Oct 2026. Possession is promised by 15 Jul 2029.
At a glance
Project
- NameStonebridge Grand Maxoria
- TypeResidential/Group Housing
- Location
- Bengaluru North
- Bengaluru Urban
- 560064
- Pincode560064
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1251/309/PR/271026/009041
- ReraGenie IDRG-KA-46636
Builder
- NameM/s Stonne Bridge Constructions Private Limited
- Entity typeCompany
- CINU68200KA2024PTC187341
- GSTIN29ABNCS2169K1ZM
- Authorized SignatoryMr. NAVEEN KUMAR
- Managing DirectorMrs. ASWINI SATHISH
- DirectorsMr. NAVEEN KUMAR, Mrs. ASWINI SATHISH
- Project HeadMr. NAVEEN KUMAR
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on27 Oct 2026
- Promised completion15 Jul 2029
- Revised completionNone
- Buildings1 building record
- Documents filed96 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Stonebridge Grand Maxoria | - | - | - | 88 | 0 | 88 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 18 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building:
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Upto Plinth Level | - |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | - |
| Retaining wall (All types) | Not applicable |
| RCC or MS Framed structure | - |
| Masonry Construction | - |
| Plastering inside , outside & Ceiling | - |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Painting | - |
| Fire prevention and fire fighting fitting and fixture with network | - |
| Weather Proof work(tile,concrete) | - |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Elevation work | - |
| Internal and External work including landscapes as per sanctioned drawings | - |
Progress on shared amenities40
As on 18 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Sewage and Drainage System | Yes | - |
| Water conservation/rain water harvesting/recharge of ground water | Yes | - |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | Yes | - |
| Solid waste management and disposal | Yes | - |
| Emergency Evacuation services | Yes | - |
| Internal Roads & Footpaths | Yes | - |
| Electricity supply transformer and substation | Yes | - |
| Storm water drains | Yes | - |
| Use of renewable energy | No | Not applicable |
| Sewage Treatment Plant (STP) | Yes | - |
| Parks & Tree planting | Yes | - |
| Street Lighting | Yes | - |
| Electricity | Yes | - |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | - |
| Club House | Yes | - |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | Yes | - |
| Indoor Sports facility | Yes | - |
| Swimming Pool | Yes | - |
| Gym | Yes | - |
| Parks | No | Not applicable |
| Power Backup | Yes | - |
| Piped Gas | No | Not applicable |
| Water and Sanitation | Yes | - |
| Air Conditioning | No | Not applicable |
| Staircases | Yes | - |
| Lifts | Yes | - |
| Corridor/Lobbies | Yes | - |
| Fire escapes | No | Not applicable |
| Common entrance and exit for the building/common portico/foyer/verandah | Yes | - |
| Basement | No | Not applicable |
| Terrace | Yes | - |
| Outer Wall | No | Not applicable |
| Open parking areas | No | Not applicable |
| Provision for lodging of management staff and security staff | Yes | - |
| Water conservation and renewable energy | No | Not applicable |
| Common storage spaces | No | Not applicable |
Land and ownership1
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Stonne Bridge Constructions Private Limited | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 42.50 cr | - |
| Payment of taxes | Rs 5.00 cr | - |
| On-site expenditure-Site Overhead | Rs 2.00 cr | - |
| On-site expenditure-Consultants Fees | Rs 1.00 cr | - |
| Principal sum and interest payable to financial institutions-Scheduled Banks | Rs 1.00 cr | - |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Mr. Tata Vittala Srinivas |
| Engineer | Mr. Mandhadi Venkataramana Reddy |
| Chartered Accountant | Mr. Thatipi Badrinath |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed96
As listed on the registration, under the names the promoter filed them with; the newest 80 of 96 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/309/PR/271026/009041 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Updated total area of land is not matching to approved planFile: TOTAL OPEN AREA Stone.pdf | 18 Aug 2026 |
| Once again informed to kindly upload elaborated structural stability certificate clearly stating theFile: structural stability certificate stone.pdf | 18 Aug 2026 |
| Kindly clarify the total extent of land considered in land cost calculation sheet,which is not matchFile: Valuation report stone new.pdf | 18 Aug 2026 |
| Once again informed to kindly upload the STP/septic tank/soak pit/sewer line drawing with full projFile: stp stone.pdf | 18 Aug 2026 |
| Once again informed to kindly upload brief project estimation with licenced engineer signature.File: estimate valuation stone.pdf | 18 Aug 2026 |
| Upload chartered accountant certificate (CA) in prescribed format form -01.File: form 1 stone (1).pdf | 5 Aug 2026 |
| Upload the bank affidavit in the prescribed format documents.File: bank aff stone.pdf | 5 Aug 2026 |
| Upload the Notarized Non Litigation AffidavitFile: non liti stone.pdf | 5 Aug 2026 |
| What are all the sources of funds to complete the project? With supporting documentsFile: Naveen ITR (1)_merged.pdf | 5 Aug 2026 |
| Upload profit and loss account and balance sheet for 2022-23 and 2023-24 CA certification with scheFile: profit and loss letter stone.pdf | 5 Aug 2026 |
| notarized affidavit in form-BFile: form b stone.pdf | 5 Aug 2026 |
| Notarized affidavit regarding all pending or cleared litigations /non-litigation by clearly mentioniFile: non liti stone.pdf | 5 Aug 2026 |
| Single Plot layout/Development plan Approved by the competent authority (Original and clearly visiblFile: single plot (1) (1).pdf | 5 Aug 2026 |
| Single Plot layout/Development plan order Approved by the competent authority(Original and clearlyFile: single plot (5).pdf | 5 Aug 2026 |
| Building License from Local Authority Original Copy.File: cc_BBMP_EoDB_CH_36711_25-26 (1)_260122_205726 (1).pdf | 5 Aug 2026 |
| Upload all original sanctioned drawings, floor plan, sectional drawings and elevationsFile: PRJ_5847_25-26_260122_205553 (1).pdf | 5 Aug 2026 |
| Upload commencement certificateFile: CC stone.pdf | 5 Aug 2026 |
| Demarcation of proposed land in original Village map certified by the competent authorityFile: village map stone.pdf | 5 Aug 2026 |
| Details of amenities and facilities provided as per plan. thereof including fire fighting facilitiesFile: fire stone.pdf | 5 Aug 2026 |
| Brochure of the project with amenities detailsFile: Stone Bridge Brochure - V - 2.pdf | 5 Aug 2026 |
| Kindly correct the taluk details in project address section as per approved plan.File: taluk stone.pdf | 5 Aug 2026 |
| Cost shown in engineer certificate form-3 is not matching to cost entered in portal as well to CAFile: DocScanner 2 Aug 2026 13-29.pdf | 5 Aug 2026 |
| Kindly upload project specifications with signature.File: Document 137.pdf | 5 Aug 2026 |
| Upload the Proforma of agreement (AFS) for sale with duly filling all the required details (designaFile: Sale Agreement Proforma STONEBRIDGE GRAND MAXORIA.pdf | 5 Aug 2026 |
| Upload Proforma Allotment letter as per the prescribed format duly fill all applicable fields withoFile: allotment letter stone.pdf | 5 Aug 2026 |
| Kindly upload the project section 3(1) notarised affidavit with project name and project address.File: Document 137 (2).pdf | 5 Aug 2026 |
| Kindly upload elaborated structural stability certificate clearly stating the number of floors consiFile: NA6 (4).pdf | 5 Aug 2026 |
| Kindly upload the Land cost calculation sheet as per the guidance value(Self-attested copy) along wiFile: ilovepdf_merged (88).pdf | 5 Aug 2026 |
| Kindly clarify the main source of water supply to the project along with the supporting documents anFile: water supply noc stone.pdf | 5 Aug 2026 |
| Kindly upload the STP/septic tank/soak pit/sewer line drawing with full project name and address aloFile: NA6 (4).pdf | 5 Aug 2026 |
| Kindly upload brief project estimation with licenced engineer signature.File: NA6 (4).pdf | 5 Aug 2026 |
| RTC, survey 29/2 | - |
| Mutation, survey 29/2 | - |
| Encumbrance Certificate, survey 29/2 | - |
| Conversion/Alienation Order, survey 29/2 | - |
| Sale/Title/Gift Deed, survey 29/2 | - |
| Khatha, survey 29/2 | - |
| Registration CertificateFile: SPICE + Part B_Approval Letter_AA7353991.pdf | - |
| Memorandum of AssociationFile: MOA.pdf | - |
| Article of AssociationFile: aoa.pdf | - |
| GST CertificateFile: GST.pdf | - |
| Organization StructureFile: NA6 (4).pdf | - |
| Certificate issued by CA Form 1File: form 1 stone (1).pdf | - |
| Certificate issued by Architect Form 2File: DocScanner 2 Aug 2026 13-40.pdf | - |
| Certificate issued by Engineer Form 3File: DocScanner 2 Aug 2026 13-29.pdf | - |
| Project Chartered Accountant | - |
| Project Engineer | - |
| Project Architect | - |
| AffidavitFile: NA6 (4).pdf | - |
| Balance Sheet 2024 - 2025File: stonnebridge Balance sheet_compressed.pdf | - |
| Balance Sheet 2023 - 2024File: NA6 (4).pdf | - |
| Balance Sheet 2022 - 2023File: NA6 (4).pdf | - |
| Audited Profit and Loss Statement 2024 - 2025File: stonnebridge Balance sheet_compressed.pdf | - |
| Audited Profit and Loss Statement 2023 - 2024File: NA6 (4).pdf | - |
| Audited Profit and Loss Statement 2022 - 2023File: NA6 (4).pdf | - |
| Income Tax Return Acknowledgement 2024 - 2025File: Financials F Y 2024-25.pdf | - |
| Income Tax Return Acknowledgement 2023 - 2024File: NA6 (4).pdf | - |
| Income Tax Return Acknowledgement 2022 - 2023File: NA6 (4).pdf | - |
| Director's Report 2024 - 2025File: stonnebridge Balance sheet_compressed.pdf | - |
| Director's Report 2023 - 2024File: NA6 (4).pdf | - |
| Director's Report 2022 - 2023File: NA6 (4).pdf | - |
| Cash Flow Statement 2024 - 2025File: stonnebridge Balance sheet_compressed.pdf | - |
| Cash Flow Statement 2023 - 2024File: NA6 (4).pdf | - |
| Auditor's Report 2024 - 2025File: stonnebridge Balance sheet_compressed.pdf | - |
| Auditor's Report 2023 - 2024File: NA6 (4).pdf | - |
| Auditor's Report 2022 - 2023File: NA6 (4).pdf | - |
| NA6 (4) | - |
| cc_BBMP_EoDB_CH_36711_25-26 (1)_260122_205726 | - |
| PRJ_5847_25-26_260122_205553 | - |
| NA6 (4) | - |
| NA6 (4) | - |
| NA6 (4) | - |
| NA6 (4) | - |
| NA6 (4) | - |
| NA6 (4) | - |
| NA6 (4) | - |
| NA6 (4) | - |
| NA6 (4) | - |
| suriya law associates | - |
| NOC-ELE | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep Stonebridge Grand Maxoria on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Filed coordinates, straight-line distance. 26 registered projects within 2 km.
LivingTree by Kalyani Developers
Kalyani Tech Park Private Limited
Sattva Lumina
Sattva Resi Private Limited
Brigade Eternia
Brigade Enterprises Ltd
Nikoo Homes V - Phase - 1
Bhartiya Urban Private Limited
GODREJ AVELINE
GODREJ SSPDL GREEN ACRES PRIVATE LIMITED
ORCHID SALISBURY
GOYAL HARIYANA ENTERPRISES
See every Bengaluru Urban project, with the district possession charts
Builder: M/s Stonne Bridge Constructions Private Limited
M/s Stonne Bridge Constructions Private Limited has 1 registration on RERA Karnataka, including Stonebridge Grand Maxoria. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if Stonebridge Grand Maxoria is delayed beyond 15 Jul 2029?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of Stonebridge Grand Maxoria?
The registered promoter entity is M/s Stonne Bridge Constructions Private Limited, a company as per the filing. Its CIN U68200KA2024PTC187341 and GSTIN 29ABNCS2169K1ZM can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in Stonebridge Grand Maxoria?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at Stonebridge Grand Maxoria?
The professionals named in the filing: Architect: Mr. Tata Vittala Srinivas; Engineer: Mr. Mandhadi Venkataramana Reddy; Chartered Accountant: Mr. Thatipi Badrinath. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Stonebridge Grand Maxoria?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.