ReraGenieLog inGet a buyer report

Home / Browse projects / Bengaluru Urban, Karnataka / Sterling Villa Grande Phase-III

Registration approved No litigation declared Residential/Group Housing project

Sterling Villa Grande Phase-III

By Sterling Urban Developments Private Limited

RG-KA-86455 · RERA PRM/KA/RERA/1251/446/PR/030623/005969 · Last updated on RERA Karnataka portal: 12 Jan 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Jun 2026Possession promisedno revision filed
16 of 16Construction stages doneevery applicable stage filed complete
8 of 25Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 199 documents Report an error

Sterling Villa Grande Phase-III is a Residential/Group Housing project by Sterling Urban Developments Private Limited in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/030623/005969 on 3 Jun 2023. Possession is promised by 30 Jun 2026. 17 of the 25 units on this registration are recorded sold or booked, and 16 of 16 construction stages are filed complete.

At a glance

Project

  • NameSterling Villa Grande Phase-III
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/446/PR/030623/005969
  • ReraGenie IDRG-KA-86455

Builder

  • NameSterling Urban Developments Private Limited
  • Entity typeCompany
  • CINU07010KA2002PTC030626
  • GSTIN29AAACF9183C1ZJ
  • Authorized SignatorySASTRI VENKAT RAMANI
  • CeoSASTRI VENKAT RAMANI
  • DirectorsSASTRI VENKAT RAMANI, Gowri Shankar Sastri
  • Project HeadSASTRI VENKAT RAMANI
  • Other registrations1 more →
  • Declared earlier projects2 →

Key dates

this monthRegisteredJun 2023PromisedJun 2026

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on3 Jun 2023
  • Promised completion30 Jun 2026
  • Revised completionNone
  • Buildings1 building record
  • Documents filed199 files

Current status

68%17 of 25 units booked
0.0%Of the estimated cost spent so far

Figures as on 12 Jan 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Sterling Villas Grande Phase-3---25025

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 12 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

16 of 16 construction stages are filed complete.

Building: 100% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)Not applicable
RCC or MS Framed structure100%
Masonry Construction100%
Plastering inside , outside & Ceiling100%
Joinery: Doors, Windows, Ventilators etc100%
Basic work of Water supply, Sanitary and Electrification100%
Dadoing, Skirting, Flooring, Tiles work (All types)100%
Railing and Grill fixing100%
Electrification, Water supply and Sanitary Finishing100%
Painting100%
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)100%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work100%
Internal and External work including landscapes as per sanctioned drawings100%

Progress on shared amenities40

As on 12 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes100%
Sewage and Drainage SystemYes100%
Water conservation/rain water harvesting/recharge of ground waterYes100%
Energy managementYes100%
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalYes100%
Emergency Evacuation servicesYes100%
Internal Roads & FootpathsYes100%
Electricity supply transformer and substationYes100%
Storm water drainsYes100%
Use of renewable energyYes100%
Sewage Treatment Plant (STP)NoNot applicable
Parks & Tree plantingYes100%
Street LightingYes100%
ElectricityYes100%
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupNoNot applicable
Piped GasNoNot applicable
Water and SanitationNoNot applicable
Air ConditioningNoNot applicable
StaircasesYes100%
LiftsNoNot applicable
Corridor/LobbiesNoNot applicable
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahNoNot applicable
BasementNoNot applicable
TerraceNoNot applicable
Outer WallNoNot applicable
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership11

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Named landowners11
LandownerVillageDistrict
Sterling Urban Developments Private Limited--
Sterling Urban Developments Private Limited--
Sterling Urban Developments Private Limited--
Sterling Urban Developments Private Limited--
Sterling Urban Developments Private Limited--
Sterling Urban Developments Private Limited--
Sterling Urban Developments Private Limited--
Sterling Urban Developments Private Limited--
Sterling Urban Developments Private Limited--
Sterling Urban Developments Private Limited--
Sterling Urban Developments Private Limited--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 42.29 cr
Spent of the estimate0.0%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 23.13 cr-
On-site expenditure-Salaries of workersRs 2.75 cr-
On-site expenditure-Consultants FeesRs 2.75 cr-
On-site expenditure-Site OverheadRs 2.75 cr-
On-site expenditure-Cost Of Services(Water, Electricity, Sewage)Rs 2.75 cr-
Principal sum and interest payable to financial institutions-Scheduled BanksRs 1.33 cr-
Principal sum and interest payable to financial institutions-Non Banking financial institution (NBFC)Rs 1.33 cr-
Principal sum and interest payable to financial institutions-Money Lenders on construction funding or money borrowed for constructionRs 1.33 cr-
Payment of taxesRs 83.27 lakh-
Payment of cessRs 83.27 lakh-
Payment of feesRs 83.27 lakh-
Payment of chargesRs 83.27 lakh-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVENKATRAMANAN ASSOCIATES
EngineerPRAKASH B V
Chartered AccountantM Padmanabha Bhat

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed199

As listed on the registration, under the names the promoter filed them with; the newest 80 of 199 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/030623/005969 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: CA SVG Phase 3 Form 4 31122025.pdf12 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: AC SVG Phase 3 Form 5 31122025.pdf12 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: EC SVG Phase 3 from 6 31122025.pdf12 Jan 2026
Q3 2025-26 Water supply and sewage board12 Jan 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)12 Jan 2026
Q3 2025-26 KSPCB- MOEF (Above 50 Acres)12 Jan 2026
Q3 2025-26 KPTCL- BESCOM12 Jan 2026
Q3 2025-26 Fire and Safety12 Jan 2026
Q3 2025-26 Airport Authority of India12 Jan 2026
Sources of fundsFile: 1-Source of Fund.pdf26 May 2023
Assignment Agreement ACREFile: Assignment Agrement ACRE.pdf26 May 2023
Loan Ledger Statement ACREFile: ACRE Loan.pdf26 May 2023
Resized Financials 20-21File: Financials 2021.pdf26 May 2023
Financials 19-20File: 2Financials 1920.pdf26 May 2023
Financials 20-21File: 2Financials 2021.pdf26 May 2023
Financials 21-22File: 2Financials 2122.pdf26 May 2023
Area details the projects detailsFile: 1Area details the projects details are not matchi (1).pdf26 May 2023
Break up of type of units (BHK) wiseFile: 2Break up of type of units BHK wise (1).pdf26 May 2023
Built-Up AreaFile: 4Built Up Area (1).pdf26 May 2023
Number of Parking.File: 5Number of Parking (1).pdf26 May 2023
Carpet Area Calculation to be Certified by EngineerFile: 6Carpet Area Calculation to be Certified by Engin (1).pdf26 May 2023
CDP MAPFile: 7CDP MAP (1).pdf26 May 2023
KSPCB CFEFile: 9Upload Renewed KSPCB CFE.pdf26 May 2023
Renewal Engineer CertificateFile: 12Engineer Certificate (1).pdf26 May 2023
Demarcated PlanFile: Demarcated Plan.pdf26 May 2023
BWSSB NOC (Panchayath)File: BWSSB NOC Panchayat.pdf26 May 2023
Brief estimated cost of construction for civil works certified by the EngineerFile: 12Engineer Certificate (1).pdf26 May 2023
Sectional Sanctioned PlanFile: Sectional Sanctioned Plan Revised (1).pdf26 May 2023
Inventory DetailsFile: Inventory and Area Details.pdf26 May 2023
Annual Audit Form-7File: Form 7 Annual Return.pdf18 May 2023
Mr.Gowri Shankar KYCFile: II-KYC.pdf18 May 2023
Source of FundFile: III-Source of Fund.pdf18 May 2023
profit and loss account and balance sheetFile: IV-SUDPL Financials 19-20.pdf18 May 2023
profit and loss account and balance sheetFile: IV-SUDPL Financials 20-21.pdf18 May 2023
profit and loss account and balance sheetFile: IV-SUDPL Financials 21-22.pdf18 May 2023
land cost in ``Source of Fund details''File: CA Certificate.pdf18 May 2023
Guidance value certificate issued by the concerned sub-registrarFile: 2-Guideline Value Certificate.pdf18 May 2023
Form-9 (Rule 28) RDPR registrar page upload only 8 sy nos. in project sy no is 11 sy no.sFile: 3-Letter dated Upload Form-9.pdf18 May 2023
Area details the project details page not matching with the Approved Plan (total area , covers areaFile: 1-Area details the projects details are not matching.pdf18 May 2023
Break up of types of Units (BHKwise)File: 2-Break up of type of units (BHK) wise.pdf18 May 2023
Built up area Mentioned in the project details Page not matching with the sanction plan clarify / upFile: 4-Built-Up Area.pdf18 May 2023
Number of parking mentioned in the project details page not matching with the sanction plan clarifyFile: 5-Number of Parking.pdf18 May 2023
certified Carpet area calculationFile: 6-Carpet Area Calculation to be Certified by Engineer.pdf18 May 2023
CDP map showing the proposed site.File: 7-CDP MAP.pdf18 May 2023
village map showing the proposed siteFile: 8-Village MAP.pdf18 May 2023
Renewed KSPCB CFEFile: 9-Upload Renewed KSPCB CFE.pdf18 May 2023
Building LicenseFile: 10-Building License.pdf18 May 2023
Renewed SEIAA NOCFile: 11-SEIAA_NOC Affidavit.pdf18 May 2023
Clear and legible sanctioned sectional drawings and elevationsFile: 12-Sectional Sanctioned Plan.pdf18 May 2023
Built up area / Number of units/ number of floors in the SEIAA NOC is not matching with the sanctionFile: 11-SEIAA_NOC Affidavit.pdf18 May 2023
Built up area / Number of units in the KSPCB NOC is not matching with the sanction Plan.File: 9-Upload Renewed KSPCB CFE.pdf18 May 2023
Please upload the renewed Engineer license certificate on the project detail pageFile: 3-Registration certificate from Structural Engineer B V Prakash.pdf18 May 2023
project name and project address and upload the signed copy of the project specifFile: 8-SVG - SPECIFICATIONS.pdf18 May 2023
fee receipt paid towards Power supply NOCFile: 9-BESCOM.pdf18 May 2023
NOC issued by Water supply authority along with the copy of fee receipt paid towarFile: 10-BWSSB Letter.pdf18 May 2023
STP design drawing and STP demarcation drawing as per the guidelines of KSPCB NOC.File: 11-STP Drawings.pdf18 May 2023
brief estimated cost of construction for civil works certified by the EngineerFile: 12-Engineer Certificate.pdf18 May 2023
Covering letterFile: Covering Letter.pdf18 May 2023
RTC, survey 104 [28 G]-
Mutation, survey 104 [28 G]-
Encumbrance Certificate, survey 104 [28 G]-
Conversion/Alienation Order, survey 104 [28 G]-
Sale/Title/Gift Deed, survey 104 [28 G]-
Khatha, survey 104 [28 G]-
RTC, survey 107 [27 G]-
Mutation, survey 107 [27 G]-
Encumbrance Certificate, survey 107 [27 G]-
Conversion/Alienation Order, survey 107 [27 G]-
Sale/Title/Gift Deed, survey 107 [27 G]-
Khatha, survey 107 [27 G]-
RTC, survey 108 [2 A 34 G]-
Mutation, survey 108 [2 A 34 G]-
Encumbrance Certificate, survey 108 [2 A 34 G]-
Conversion/Alienation Order, survey 108 [2 A 34 G]-
Sale/Title/Gift Deed, survey 108 [2 A 34 G]-
Khatha, survey 108 [2 A 34 G]-
RTC, survey 109 [6 A 37G]-
Mutation, survey 109 [6 A 37G]-
Encumbrance Certificate, survey 109 [6 A 37G]-
Conversion/Alienation Order, survey 109 [6 A 37G]-

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 not delivered by the promised date1 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
Sterling Villa Grande Phase-IISurvey no. 104(P), 107(P), 108, 109, 110(P), 111(P), 112(P), 113, 114, 115 & 116, , Seegehalii Village, Bidarahalli Hobli, Bengaluru - 560067OngoingMar 2024Not delivered
Sterling Villa Grande Phase-ISurvey no. 104(P), 107(P), 108, 109, 110(P), 111(P), 112(P), 113, 114, 115 & 116, , Seegehalii Village, Bidarahalli Hobli, Bengaluru - 560067Completed-No date filed

How this compares with Bengaluru Urban

68%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Sterling Villa Grande Phase-III on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: Sterling Urban Developments Private Limited

Sterling Urban Developments Private Limited has 2 registrations on RERA Karnataka, including Sterling Villa Grande Phase-III and Sterling Villa Grande Phase II. Its filings declare 2 earlier projects, 1 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Sterling Villa Grande Phase-III is delayed beyond 30 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Sterling Villa Grande Phase-III?

The registered promoter entity is Sterling Urban Developments Private Limited, a company as per the filing. Its CIN U07010KA2002PTC030626 and GSTIN 29AAACF9183C1ZJ can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Sterling Villa Grande Phase-III?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Sterling Villa Grande Phase-III?

The professionals named in the filing: Architect: VENKATRAMANAN ASSOCIATES; Engineer: PRAKASH B V; Chartered Accountant: M Padmanabha Bhat. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Sterling Villa Grande Phase-III?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Sterling Villa Grande Phase-III. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Sterling Villa Grande Phase-III to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.