SRI VENKATESHWARA COLONY

By K SRINIVAS

RG-KA-92118 · RERA PRM/KA/RERA/1669/440/PR/211024/007158 · Last updated on RERA Karnataka portal: 2 Sep 2024

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Dec 2025Possession promisedno revision filed
0Complaints at RERA Karnatakaon this registration
Jump to the 92 documents Report an error

SRI VENKATESHWARA COLONY is a Plotted Development project by K SRINIVAS in Vijayanagara, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1669/440/PR/211024/007158 on 21 Oct 2024. Possession is promised by 31 Dec 2025.

At a glance

Project

  • NameSRI VENKATESHWARA COLONY
  • TypePlotted Development
  • Location
    • Hospet
    • Vijayanagara
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1669/440/PR/211024/007158
  • ReraGenie IDRG-KA-92118

Builder

  • NameK SRINIVAS
  • Entity typeProprietorship
  • Authorized SignatoryK SRINIVAS
  • Declared earlier projects1 →

Key dates

this monthRegisteredOct 2024PromisedDec 2025

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on21 Oct 2024
  • Promised completion31 Dec 2025
  • Revised completionNone
  • BuildingsNot stated in filing
  • Documents filed92 files

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Named landowners1
LandownerVillageDistrict
Y ESHWARAMMA--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 70.00 lakh
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 70.00 lakh-

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
EngineerAmith Parangi
Chartered AccountantSYED MAHAMED K

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed92

As listed on the registration, under the names the promoter filed them with; the newest 80 of 92 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1669/440/PR/211024/007158 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Final ApprovalFile: Final Approval.pdf2 Sep 2024
Final layout planFile: Final Layout plan.pdf2 Sep 2024
Water NOCFile: Water NOC.pdf2 Sep 2024
Electricity NOCFile: Electricity NOC.pdf2 Sep 2024
Road and UGD NOCFile: Road & UGD NOC.pdf2 Sep 2024
Reliquishment deedFile: Relinquishment deed.pdf2 Sep 2024
Reply letterFile: Reply letter.pdf2 Sep 2024
MRFile: MR.pdf1 Jul 2024
Reliquishment deedFile: Reliquishment deed.pdf1 Jul 2024
CA Site DeedFile: CA Site Deed.pdf1 Jul 2024
Work orderFile: Work order.pdf1 Jul 2024
CDP MapFile: CDP Map.pdf1 Jul 2024
Village MapFile: Village Map.pdf1 Jul 2024
CLU Order ClarificationFile: Change of land use.pdf1 Jul 2024
Bank AffidavitFile: Bank Affidavit.pdf24 May 2024
ITR & Balance sheet 2021-22File: ITR & Balance sheet with UDIN 2021-22.pdf24 May 2024
ITR & Balance sheet 2022-23File: ITR & Balance Sheet with UDIN 2022-23.pdf24 May 2024
CA Membership certificateFile: CA Membership Certificate.pdf24 May 2024
Source of fundFile: Sources of fund.pdf24 May 2024
Proprietorship GST registration certificateFile: GST Certificate.pdf24 May 2024
MRFile: MR.pdf24 May 2024
Legal opinionFile: legal opinion.pdf24 May 2024
Work orderFile: Work order.pdf24 May 2024
CDP MapFile: CDP map.pdf24 May 2024
ZR copyFile: ZR Copy.pdf24 May 2024
Change of land useFile: Change of land use.pdf24 May 2024
BESCOM NOC Self attestedFile: GESCOM NOC.pdf24 May 2024
Water NOC Self attestedFile: Water NOC.pdf24 May 2024
Water Supporting documentsFile: Water supply supporting documents.jpeg24 May 2024
Abstract EstimateFile: Abstract Estimate.pdf24 May 2024
Common Area detailsFile: Comman area details.pdf24 May 2024
Previous project final approvalFile: Vinayakpura Final Approval.pdf24 May 2024
Reply letterFile: reply letter.pdf24 May 2024
RTC, survey 3/6-
Mutation, survey 3/6-
Encumbrance Certificate, survey 3/6-
Conversion/Alienation Order, survey 3/6-
Sale/Title/Gift Deed, survey 3/6-
JDA, survey 3/6-
Khatha, survey 3/6-
Registration CertificateFile: GSTIN No.pdf-
Certificate issued by CA Form 1File: Form 1.pdf-
Project Chartered Accountant-
Project Engineer-
AffidavitFile: Affidavit Non litigation.pdf-
Certificate from Chartered AccountFile: Form 1.pdf-
Balance Sheet 2022 - 2023File: Balace sheet & P & L account 2023-24.pdf-
Balance Sheet 2021 - 2022File: Balace sheet & P & L account 2022-23.pdf-
Balance Sheet 2020 - 2021File: Balace sheet & P & L account 2021-22.pdf-
Audited Profit and Loss Statement 2022 - 2023File: Balace sheet & P & L account 2023-24.pdf-
Audited Profit and Loss Statement 2021 - 2022File: Balace sheet & P & L account 2022-23.pdf-
Audited Profit and Loss Statement 2020 - 2021File: Balace sheet & P & L account 2021-22.pdf-
Income Tax Return Acknowledgement 2020 - 2021File: ITR 2021-22.pdf-
Plan Approval-
Water NOC-
Layout plan-
Layout plan-
Project Specification-
JDA-
agreement for sale-
Allotment letter-
Form B-
Affidavit 3(1)-
Affidavit JDA-
Water NOC-
Horticulture department NOC-
Agreement Letter-
Agreement Panduranga Setty-
Civil Work NOC-
GPA-
Shivappa Sale deed-
Sketch-
Guidence Value-
CDP Map-
Change of land use-
CD format-
Land cost calculation sheet-
Comman area details-
Abstract Estimate-
Plot Excel SheetFile: CD Report Formate.xlsx-

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
VINAYAKA PURASy.No:130/4 at Nagenahalli Village, , Hospet Taluk, Bellary DistrictCompleted-No date filed

How this compares with Vijayanagara

7%of Vijayanagara projects moved their completion datethis one has not
0%of Vijayanagara registrations are shown as withdrawn or revokedthis one is not

Computed across the 110+ Vijayanagara projects on ReraGenie, from their own filings.

Keep SRI VENKATESHWARA COLONY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Vijayanagara110+ in Vijayanagara

Builder: K SRINIVAS

K SRINIVAS has 1 registration on RERA Karnataka, including SRI VENKATESHWARA COLONY. Its filings declare 1 earlier project, 1 of them declared completed. Read the full track record. See more projects on the Vijayanagara district page.

Frequently asked questions

What are my rights if SRI VENKATESHWARA COLONY is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of SRI VENKATESHWARA COLONY?

The registered promoter entity is K SRINIVAS, a proprietorship as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in SRI VENKATESHWARA COLONY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SRI VENKATESHWARA COLONY?

The professionals named in the filing: Engineer: Amith Parangi; Chartered Accountant: SYED MAHAMED K. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SRI VENKATESHWARA COLONY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SRI VENKATESHWARA COLONY. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SRI VENKATESHWARA COLONY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.