Home / Browse projects / Bengaluru Urban, Karnataka / SRI SAI VIHAR

Registration approved No litigation declared Residential/Group Housing project

SRI SAI VIHAR

By SRI SAI VENTURES

RG-KA-02879 · RERA PRM/KA/RERA/1251/308/PR/160124/006554 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Nov 2028Possession promisedno revision filed
13 of 13Construction stages doneevery applicable stage filed complete
38 of 88Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 131 documents Report an error

SRI SAI VIHAR is a Residential/Group Housing project by SRI SAI VENTURES in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/308/PR/160124/006554 on 16 Jan 2024. Possession is promised by 16 Nov 2028. 50 of the 88 units on this registration are recorded sold or booked, and 13 of 13 construction stages are filed complete.

At a glance

Project

  • NameSRI SAI VIHAR
  • TypeResidential/Group Housing
  • Location
    • Anekal
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/308/PR/160124/006554
  • ReraGenie IDRG-KA-02879

Builder

  • NameSRI SAI VENTURES
  • Entity typePartnership Firm
  • GSTIN29AEYFS0783E1ZC
  • Authorized SignatoryYOGESH N
  • Other registrations2 more →

Key dates

this monthRegisteredJan 2024PromisedNov 2028

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on16 Jan 2024
  • Promised completion16 Nov 2028
  • Revised completionNone
  • Buildings1 building record
  • Documents filed131 files

Current status

57%50 of 88 units booked
13.4%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
1---88088

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

13 of 13 construction stages are filed complete.

Building: 100% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)Not applicable
RCC or MS Framed structure100%
Masonry Construction100%
Plastering inside , outside & Ceiling100%
Joinery: Doors, Windows, Ventilators etc100%
Basic work of Water supply, Sanitary and Electrification100%
Dadoing, Skirting, Flooring, Tiles work (All types)100%
Railing and Grill fixing100%
Electrification, Water supply and Sanitary Finishing100%
Painting100%
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation workNot applicable
Internal and External work including landscapes as per sanctioned drawingsNot applicable

Progress on shared amenities40

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes95%
Sewage and Drainage SystemYes95%
Water conservation/rain water harvesting/recharge of ground waterYes95%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalYes95%
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsYes95%
Electricity supply transformer and substationYes95%
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes95%
Parks & Tree plantingYes95%
Street LightingYes95%
ElectricityYes95%
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseYes95%
Community HallYes95%
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolYes95%
GymNoNot applicable
ParksYes95%
Power BackupYes95%
Piped GasNoNot applicable
Water and SanitationNoNot applicable
Air ConditioningNoNot applicable
StaircasesYes95%
LiftsYes95%
Corridor/LobbiesYes95%
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahYes95%
BasementNoNot applicable
TerraceNoNot applicable
Outer WallYes95%
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffYes95%
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Named landowners1
LandownerVillageDistrict
SATHISHA KM--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 17.34 cr
Cost incurredRs 2.33 cr
Spent of the estimate13.43%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 13.16 crRs 2.33 cr
On-site expenditure-Salaries of workersRs 1.50 cr-
On-site expenditure-Cost Of Services(Water, Electricity, Sewage)Rs 1.50 cr-
On-site expenditure-Site OverheadRs 1.00 cr-
On-site expenditure-Consultants FeesRs 18.00 lakh-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSunil B G
EngineerVeeresh Patil
Chartered AccountantJ SESHACHALAPATHI

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed131

As listed on the registration, under the names the promoter filed them with; the newest 80 of 131 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/308/PR/160124/006554 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form -4, CA Q2 SS Vihar_compressed.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: FORM-05 SSV.pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: ENG SSV Q2.pdf15 Oct 2026
Q2 2026-27 Water supply and sewage board15 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Oct 2026
Q2 2026-27 KPTCL- BESCOM15 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: CA VIHAR.pdf14 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: FORM-05 SAI SAI VIHAR_page-0001.pdf14 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Rera certificate_page-0001.pdf14 Jul 2026
Q1 2026-27 Water supply and sewage board14 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)14 Jul 2026
Q1 2026-27 KPTCL- BESCOM14 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Sri Sai Ventures (1).pdf16 May 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: FORM 5.pdf16 May 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Rera_compressed.pdf16 May 2026
Q4 2025-26 Water supply and sewage board16 May 2026
Q4 2025-26 KPTCL- BESCOM16 May 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: FORM 4- SSV (1)_compressed.pdf4 Feb 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Architect's Certificate.pdf4 Feb 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Rera_compressed.pdf4 Feb 2026
Q3 2025-26 Water supply and sewage board4 Feb 2026
Q3 2025-26 KPTCL- BESCOM4 Feb 2026
Architect Certificate - Lienace 08-01-2024File: Architect Certificate - Lienace 08-01-2024.pdf12 Jan 2024
Architect LienaceFile: bgsunil_1383 (2).PDF12 Jan 2024
Mr Sathish 2022-2023File: Mr Sathish 2022-2023_compressed.pdf12 Jan 2024
Mrs Sindhu 2022-2023File: Mrs Sindhu 2022-2023_compressed.pdf12 Jan 2024
Mr Sathish 2021-2022File: Mr Sathish 2021-2022_compressed.pdf12 Jan 2024
Mrs Sindhu 2021-2022File: Mrs Sindhu 2021-2022_compressed.pdf12 Jan 2024
Mr Mohan 2023-2024File: Mr Mohan 2023-2024.pdf12 Jan 2024
Mr Mohan 2021-2022File: Mr Mohan 2021-2022.pdf12 Jan 2024
Mr Mohan 2022-2023File: Mr Mohan 2022-2023.pdf12 Jan 2024
Yogesh IT 2022-2023File: Yogesh IT 2022-2023.pdf12 Jan 2024
CA CertificateFile: S0T1000137_2401111011000.pdf12 Jan 2024
CERTIFICATE BY ARCHITECTFile: CERTIFICATE BY ARCHITECT.pdf12 Jan 2024
CDP mapFile: Sompura 97.pdf12 Jan 2024
sectional drawings and elevationsFile: ELEVATION & TERRACE_compressed.pdf12 Jan 2024
sectional drawings and elevationsFile: SANCTION FLOOR GF+1+2+3+4_compressed.pdf12 Jan 2024
97-1File: 97-1.pdf12 Jan 2024
97-5File: 97-5.pdf12 Jan 2024
Company Reg CertificateFile: Company Reg Certificate.pdf20 Dec 2023
Affidavit Cum Declaration - DDMMYYYYFile: Affidavit Cum Declaration - DDMMYYYY.pdf20 Dec 2023
Section (3) - AffidavitFile: Section (3) - Affidavit.pdf20 Dec 2023
CA - IT Letter - Sri Sai VenturesFile: CA - IT Letter - Sri Sai Ventures.pdf20 Dec 2023
Soures of Funds - Sri Sai VenturesFile: Soures of Funds - Sri Sai Ventures.pdf20 Dec 2023
Sri Sai Ventures Part 1_compressedFile: Sri Sai Ventures Part 1_compressed.pdf20 Dec 2023
Sri Sai Ventures part 2_compressed (1)File: Sri Sai Ventures part 2_compressed (1).pdf20 Dec 2023
Singal Layout Plan Attached- CopyFile: Singal Layout Plan Attached- Copy.pdf20 Dec 2023
Singal Layout ApprovalFile: Singal Layout Approval.pdf20 Dec 2023
Legal OpinionFile: Legal Opinion.pdf20 Dec 2023
GPA GenralFile: GPA Genral.pdf20 Dec 2023
Commencamant CertificateFile: Commencamant Certificate.pdf20 Dec 2023
Building LienceFile: Building Lience.pdf20 Dec 2023
AASR 05112018File: AASR 05112018.pdf20 Dec 2023
ENGINEER CERTIFICATE SRI SAI VIHARFile: ENGINEER CERTIFICATE SRI SAI VIHAR.pdf20 Dec 2023
97-1 97-5 ECFile: 97-1 97-5 EC.pdf20 Dec 2023
97-1 97-5 KathaFile: 97-1 97-5 Katha.pdf20 Dec 2023
97-1 97-5 Paper AdsFile: 97-1 97-5 Paper Ads.pdf20 Dec 2023
97-1 97-5 SY ScatchFile: 97-1 97-5 SY Scatch.pdf20 Dec 2023
97-1 97-5 Village MapFile: 97-1 97-5 Village Map.pdf20 Dec 2023
97-5 AkarbhandFile: 97-5 Akarbhand.pdf20 Dec 2023
97-5 Conformation Deed 1898-21-22File: 97-5 Conformation Deed 1898-21-22.pdf20 Dec 2023
97-5 Confromation Deed 6479-19-20File: 97-5 Confromation Deed 6479-19-20.pdf20 Dec 2023
97-5 Conversion Order 23-11-2022File: 97-5 Conversion Order 23-11-2022.pdf20 Dec 2023
97-5 EC 2File: 97-5 EC 2.pdf20 Dec 2023
97-5 MRFile: 97-5 MR.pdf20 Dec 2023
97-5 RTCFile: 97-5 RTC.pdf20 Dec 2023
97-5 Sale Deed 275-20-21File: 97-5 Sale Deed 275-20-21.pdf20 Dec 2023
97-5 Sale Deed 6022-19-20File: 97-5 Sale Deed 6022-19-20.pdf20 Dec 2023
RTC OldFile: RTC Old.pdf20 Dec 2023
50KLD STRUCTURE-ModelFile: 50KLD STRUCTURE-Model.pdf20 Dec 2023
Affid Cum Del Form BFile: Affid Cum Del Form B.pdf20 Dec 2023
Bank AffidaviteFile: Bank Affidavite.pdf20 Dec 2023
BESCOMSRI SAIFile: BESCOMSRI SAI.pdf20 Dec 2023
BrochureFile: Brochure.pdf20 Dec 2023
Google Maps - Sri Sai vihar & VILLAGE MAPFile: Google Maps - Sri Sai vihar & VILLAGE MAP.pdf20 Dec 2023
Land Affidavit Cum DeclarationFile: Land Affidavit Cum Declaration.pdf20 Dec 2023
No LitigationFile: No Litigation.pdf20 Dec 2023
PROJECT REPORT SRI SAI VENTURES STP ReportFile: PROJECT REPORT SRI SAI VENTURES STP Report.pdf20 Dec 2023
Singal Layout SancitionFile: Singal Layout Sancition.pdf20 Dec 2023
Singal layoutFile: Singal layout.pdf20 Dec 2023

How this compares with Bengaluru Urban

57%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep SRI SAI VIHAR on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: SRI SAI VENTURES

SRI SAI VENTURES has 3 registrations on RERA Karnataka, including SAI KRUPA and SRI SAI VIHAR. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if SRI SAI VIHAR is delayed beyond 16 Nov 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of SRI SAI VIHAR?

The registered promoter entity is SRI SAI VENTURES, a partnership firm as per the filing. Its GSTIN 29AEYFS0783E1ZC can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in SRI SAI VIHAR?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SRI SAI VIHAR?

The professionals named in the filing: Architect: Sunil B G; Engineer: Veeresh Patil; Chartered Accountant: J SESHACHALAPATHI. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SRI SAI VIHAR?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SRI SAI VIHAR. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SRI SAI VIHAR to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.