Red flags
- Completion date moved by 12 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
Saved.
SRI SAI SAROVAR is a Residential/Group Housing project by SRI SAI CONSTRUCTIONS in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/100423/005856 on 10 Apr 2023. Possession is promised by 31 Dec 2026. The completion date has moved by 12 months from the original filing. 118 of the 155 units on this registration are recorded sold or booked, and 16 of 16 construction stages are filed complete.
At a glance
Project
- NameSRI SAI SAROVAR
- TypeResidential/Group Housing
- Location
- Bengaluru East
- Bengaluru Urban
- PincodeNot stated
- RERA no.PRM/KA/RERA/1251/446/PR/100423/005856
- ReraGenie IDRG-KA-68819
Builder
- NameSRI SAI CONSTRUCTIONS
- Entity typePartnership Firm
- GSTIN29ACVFS9402P1ZY
- Authorized SignatoryG.RAMESH
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on10 Apr 2023
- Promised completion31 Dec 2026
- Revised completionRevised to 31 Dec 2026 (originally 31 Dec 2025)
- Buildings1 building record
- Documents filed179 files
Current status
Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Sri Sai Sarovar | - | - | - | 155 | 0 | 155 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
16 of 16 construction stages are filed complete.
Building: 100% average across the applicable activities
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | 100% |
| Foundation footing work | 100% |
| Retaining wall (All types) | 100% |
| Plinth level Beam | 100% |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | 100% |
| RCC or MS Framed structure | 100% |
| Masonry construction: Bricks, Concrete blocks etc | 100% |
| Plastering inside , outside & Ceiling | 100% |
| Joinery: Doors, Windows, Ventilators etc | 100% |
| Basic work of Water supply, Sanitary and Electrification | 100% |
| Dadoing, Skirting, Flooring, Tiles work (All types) | 100% |
| Railing and Grill fixing | 100% |
| Electrification, Water supply and Sanitary Finishing | 100% |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Fire prevention and fire fighting fitting and fixture with network | Not applicable |
| Weather Proof work(tile,concrete) | 100% |
| Painting | 100% |
| Elevation work | 100% |
| Internal and External work including landscapes as per santioned drawings | Not applicable |
Progress on shared amenities41
As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | 98% |
| Internal Roads & Footpaths | Yes | 95% |
| Sewage and Drainage System | Yes | 100% |
| Parks & Tree planting | Yes | 50% |
| Street Lighting | No | Not applicable |
| Provision for community buildings and for treatment and disposal of sewage and sullage water | No | Not applicable |
| Solid waste management and disposal | Yes | 100% |
| Water conservation | No | Not applicable |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Education/Health/Other public amenities | No | Not applicable |
| Electricity supply transformer and substation | Yes | 100% |
| Emergency Evacuation services | Yes | 100% |
| Storm water drains | Yes | 100% |
| Use of renewable energy | No | Not applicable |
| Water conservation/rain water harvesting/recharge of ground water | Yes | 100% |
| Electricity | Yes | 50% |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | 100% |
| Club House | No | Not applicable |
| Community Hall | Yes | 0% |
| Outdoor Sports facility | Yes | 0% |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | Yes | 0% |
| Gym | Yes | 0% |
| Parks | Yes | 0% |
| Power Backup | Yes | 100% |
| Gas | No | Not applicable |
| Water and Sanitation | Yes | 100% |
| Air Conditioning And incerntion | No | Not applicable |
| Staircases | Yes | 100% |
| Lifts | Yes | 100% |
| Staircases and Lift lobbies, corridor,lobbies, corridor | Yes | 100% |
| Fire escapes | No | Not applicable |
| Common entrance and exit for the building / common portico/foyer/verandah | No | Not applicable |
| Basement | Yes | 100% |
| Terrace | Yes | 100% |
| Outer Wall | Yes | 100% |
| Open parking areas and common storage spaces | Yes | 50% |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | No | Not applicable |
Land and ownership2
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Chundi Narashimulu Reddy | - | - |
| Chundi Narashimulu Reddy | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 32.90 cr | Rs 71.08 cr |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | VIJAY ASSOCIATES - E ROSHINI |
| Engineer | Kumar C G |
| Chartered Accountant | V S KRISHNA MURTHY |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDelay in Approvals
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed179
As listed on the registration, under the names the promoter filed them with; the newest 80 of 179 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/100423/005856 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form-4 CA.pdf | 15 Oct 2026 |
| Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form-5 Architect Q2 2026 27.pdf | 15 Oct 2026 |
| Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form-6 Engineer.pdf | 15 Oct 2026 |
| Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA.pdf | 12 Jul 2026 |
| Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form 5 Architect.pdf | 12 Jul 2026 |
| Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form 6 Engineer.pdf | 12 Jul 2026 |
| Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form-4, Chartered Accountant Q4 2025-26.pdf | 12 Apr 2026 |
| Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form-5 Architect Q4.pdf | 12 Apr 2026 |
| Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form-6, Engineer Q4 2025-26.pdf | 12 Apr 2026 |
| Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA Q3 2025-26.pdf | 19 Feb 2026 |
| Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5 Architect Q3 2025-26.pdf | 19 Feb 2026 |
| Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6 Engineer Q3 2025-26.pdf | 19 Feb 2026 |
| SOLD AND UNSOLD UNITS LETTERFile: sold & unsold letter.pdf | 2 Feb 2026 |
| SOLD UNITS WITH NAMESFile: sold units with names.pdf | 2 Feb 2026 |
| UNSOLD UNITSFile: Unsold units.pdf | 2 Feb 2026 |
| NOC AFFIDAVITFile: Affidavit (2).pdf | 2 Feb 2026 |
| EC latestFile: EC Latest1.pdf | 29 Jan 2026 |
| Renewed Approved Building planFile: BBMP approvals and CC.pdf | 29 Jan 2026 |
| Renewed Approved Building plan order letterFile: BBMP building license B+G+4 New.pdf | 29 Jan 2026 |
| engineer licenceFile: Engineer BBMP-LICENSE RENEWAL-CERTIFICATE-002.pdf | 29 Jan 2026 |
| sold & unsold units lettersFile: sold & unsold letter.pdf | 29 Jan 2026 |
| sold units with allottee namesFile: sold units with names.pdf | 29 Jan 2026 |
| unsold unitsFile: unsold units.pdf | 29 Jan 2026 |
| NOC's affidavitFile: Affidavit for NOCs.pdf | 29 Jan 2026 |
| NocsFile: KSPCB, Bwssb & Bescom NOCs.pdf | 29 Jan 2026 |
| Upload sold and unsold units details with signature.File: Area statement Land owner share Total 16 Units.pdf | 24 Sep 2025 |
| Upload sold and unsold units details with signature.File: Area Statement Land owner sold flats .pdf | 24 Sep 2025 |
| Upload sold and unsold units details with signature.File: Area Statement Land owner Unsold flats .pdf | 24 Sep 2025 |
| Upload sold and unsold units details with signature.File: AREA STATMENT(BUILDER SHARE) - UNSOLD FLATS.pdf | 24 Sep 2025 |
| Upload sold and unsold units details with signature.File: AREA STATEMENT(BUILDER SHARE)- SOLD FLATS.pdf | 24 Sep 2025 |
| Upload sold and unsold units details with signature.File: AREA STATEMENT(BUILDER SHARE) - TOTAL .pdf | 24 Sep 2025 |
| Before modification Flats Sold and unsold units total is not matching to total number of units in thFile: Area statement before modification 124 units.pdf | 24 Sep 2025 |
| After Modification Flats Sold and unsold units total is not matching to total number of units in theFile: Area Statement for Total 155 Units- After Modification.pdf | 24 Sep 2025 |
| Sold and unsold units total is not matching to total number of units in the project,kindly clarify.File: letter.pdf | 24 Sep 2025 |
| Balance Sheet for PROMOTERS CONTRIBUTION - InvestmentsFile: Balance Sheet - Promoter Contribution.pdf | 5 Apr 2023 |
| Sources of FundsFile: Source of Funds - Sri Sai Sarovar.pdf | 5 Apr 2023 |
| SOURCES OF FUND DETAILSFile: Source of Funds - Sri Sai Sarovar.pdf | 5 Mar 2023 |
| Sources of FundFile: Source of Funds.pdf | 22 Feb 2023 |
| 2019-20 P AND L Blance sheet with CA UDINFile: 2019-20 P and L and Balance Sheet with UDIN.pdf | 17 Feb 2023 |
| 2020-21 P AND L Blance sheet with CA UDINFile: 2020-21 P and L Balance Sheet - with UDIN.pdf | 17 Feb 2023 |
| 2021-22 P AND L Blance sheet with CA UDINFile: 2021-22 Balance sheet and P and L with CA UDIN.pdf | 17 Feb 2023 |
| CDP PlanFile: CDP PLAN.pdf | 17 Feb 2023 |
| Village Map DemarcationFile: Kodigehalli Village Map Demarcation.pdf | 17 Feb 2023 |
| Clarification for CC FAR and No of unitsFile: Clarification For CC FAR.pdf | 17 Feb 2023 |
| Estimated Cost for summary of Civil WorksFile: Sri Sai Sarovar - Estimated Cost.pdf | 17 Feb 2023 |
| Engineer CertificateFile: Form - 3 Engineer.pdf | 17 Feb 2023 |
| STP DrawingFile: STP Drawing.pdf | 17 Feb 2023 |
| STP DemarcationFile: STP Demarcation.pdf | 17 Feb 2023 |
| Affidavit 3-1File: Affidavit 3-1.pdf | 17 Feb 2023 |
| Ageeement for sale Proforma RevisedFile: Agreement for sale Final RERA-Revised.pdf | 17 Feb 2023 |
| Allotment LetterFile: Allotment letter Sai sarovar.pdf | 17 Feb 2023 |
| BESCOM NOC Fees Paid ReceiptFile: BESCOM NOC - FEES PAID RECEIPT.pdf | 17 Feb 2023 |
| BWSSB NOC Fees Paid ReceiptFile: BWSSB NOC - FEES PAID RECEIPT.pdf | 17 Feb 2023 |
| RTC, survey 47 | - |
| Mutation, survey 47 | - |
| Encumbrance Certificate, survey 47 | - |
| Conversion/Alienation Order, survey 47 | - |
| JDA, survey 47 | - |
| Khatha, survey 47 | - |
| RTC, survey 48 | - |
| Mutation, survey 48 | - |
| Encumbrance Certificate, survey 48 | - |
| Conversion/Alienation Order, survey 48 | - |
| JDA, survey 48 | - |
| Khatha, survey 48 | - |
| Registration CertificateFile: Partnership registration certificates.pdf | - |
| Partnership DeedFile: Partnership Deed (Reconstitution deed).pdf | - |
| Partner Details | - |
| Partner Details | - |
| Partner Details | - |
| Partner Details | - |
| Partner Details | - |
| Certificate issued by CA Form 1File: FORM 4 CA.pdf | - |
| Certificate issued by Architect Form 2File: FORM 5 ARCHITECHT.pdf | - |
| Certificate issued by Engineer Form 3File: FORM 6 ENGINEER.pdf | - |
| Project Chartered Accountant | - |
| Project Engineer | - |
| Project Architect | - |
| AffidavitFile: Affidavit for no Litigation.pdf | - |
| Certificate from Chartered AccountFile: FORM 4 CA.pdf | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep SRI SAI SAROVAR on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Prestige Park Grove
PRESTIGE PROJECTS PRIVATE LIMITED
Prestige Lakeside Habitat
Prestige Habitat Ventures
LivingTree by Kalyani Developers
Kalyani Tech Park Private Limited
PRESTIGE FALCON CITY
PRESTIGE NOTTINGHILL INVESTMENTS
SATTVA CITY
SATTVA CITY PRIVATE LIMITED
GM AMBITIOUS ENCLAVE
M/s. Allam Infinite India Private Limited
See every Bengaluru Urban project, with the district possession charts
Builder: SRI SAI CONSTRUCTIONS
SRI SAI CONSTRUCTIONS has 1 registration on RERA Karnataka, including SRI SAI SAROVAR. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if SRI SAI SAROVAR is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of SRI SAI SAROVAR?
The registered promoter entity is SRI SAI CONSTRUCTIONS, a partnership firm as per the filing. Its GSTIN 29ACVFS9402P1ZY can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in SRI SAI SAROVAR?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at SRI SAI SAROVAR?
The professionals named in the filing: Architect: VIJAY ASSOCIATES - E ROSHINI; Engineer: Kumar C G; Chartered Accountant: V S KRISHNA MURTHY. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SRI SAI SAROVAR?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback