Home / Browse projects / Bengaluru Urban, Karnataka / SRI SAI SAMRUDHI

Registration approved No litigation declared Residential/Group Housing project

SRI SAI SAMRUDHI

By SRI SAI VENTURES

RG-KA-49025 · RERA PRM/KA/RERA/1251/446/PR/280826/008895 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Dec 2030Possession promisedno revision filed
0 of 17Construction stages donefurthest along: Earth work and other leveling..., 90%
0Complaints at RERA Karnatakaon this registration
Jump to the 91 documents Report an error

SRI SAI SAMRUDHI is a Residential/Group Housing project by SRI SAI VENTURES in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/280826/008895 on 28 Aug 2026. Possession is promised by 31 Dec 2030.

At a glance

Project

  • NameSRI SAI SAMRUDHI
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/446/PR/280826/008895
  • ReraGenie IDRG-KA-49025

Builder

  • NameSRI SAI VENTURES
  • Entity typePartnership Firm
  • GSTIN29AEYFS0783E1ZC
  • Authorized SignatorySATHISHA K.M
  • Other registrations2 more →

Key dates

this monthRegisteredAug 2026PromisedDec 2030

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on28 Aug 2026
  • Promised completion31 Dec 2030
  • Revised completionNone
  • Buildings1 building record
  • Documents filed91 files

Current status

7.7%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SRI SAI SAMRUDHI---48048

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 17 construction stages are filed complete. The stage furthest along is Earth work and other leveling preparation work, at 90%.

Building: 18% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work90%
Foundation footing work90%
Upto Plinth Level90%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)30%
Retaining wall (All types)0%
RCC or MS Framed structure0%
Masonry Construction0%
Plastering inside , outside & Ceiling0%
Joinery: Doors, Windows, Ventilators etc0%
Basic work of Water supply, Sanitary and Electrification0%
Dadoing, Skirting, Flooring, Tiles work (All types)0%
Railing and Grill fixing0%
Electrification, Water supply and Sanitary Finishing0%
Painting0%
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)0%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work0%
Internal and External work including landscapes as per sanctioned drawings0%

Progress on shared amenities40

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes0%
Sewage and Drainage SystemYes0%
Water conservation/rain water harvesting/recharge of ground waterYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes0%
Solid waste management and disposalNoNot applicable
Emergency Evacuation servicesYes0%
Internal Roads & FootpathsYes0%
Electricity supply transformer and substationYes0%
Storm water drainsYes0%
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes0%
Parks & Tree plantingYes0%
Street LightingYes0%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseNoNot applicable
Community HallYes0%
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityYes0%
Swimming PoolYes0%
GymYes0%
ParksYes0%
Power BackupYes0%
Piped GasNoNot applicable
Water and SanitationYes0%
Air ConditioningNoNot applicable
StaircasesYes10%
LiftsYes10%
Corridor/LobbiesYes0%
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahYes0%
BasementNoNot applicable
TerraceYes0%
Outer WallYes0%
Open parking areasYes0%
Provision for lodging of management staff and security staffYes0%
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Named landowners1
LandownerVillageDistrict
M. MANJUNATH--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 24.79 cr
Cost incurredRs 1.91 cr
Spent of the estimate7.7%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 22.81 crRs 1.91 cr
Office Admintration expencesRs 1.26 cr-
On-site expenditure-Consultants FeesRs 72.00 lakh-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSunil B G
EngineerVeeresh Patil
Chartered AccountantJ Seshachalapathi

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed91

As listed on the registration, under the names the promoter filed them with; the newest 80 of 91 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/280826/008895 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form -4, CA Q2 SS Samrudhi_compressed.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: FORM-05 SSS Q2.pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: ENG SSS Q2.pdf15 Oct 2026
Q2 2026-27 KPTCL- BESCOM15 Oct 2026
Q2 2026-27 Airport Authority of India15 Oct 2026
Q2 2026-27 BSNL/Telecommunication Department15 Oct 2026
clarify and submit the revised structural stability certificateFile: 5 Stability certificate signed Rajesh (1).pdf5 Aug 2026
valid structural engineer licence of engineer - signed the structural stability certificateFile: eNG.pdf3 Aug 2026
EC from 1-4-2011 to till dateFile: ECC-13072026-3298391 (1).pdf30 Jul 2026
LAND KATHAFile: KHATHA (1).pdf30 Jul 2026
structural engineer licence of engineerFile: eNG lEINCE.pdf30 Jul 2026
AFS UpdatedFile: ASF Agreement.pdf30 Jul 2026
Eng Request LetterFile: REQUEST LEETER ENG.pdf30 Jul 2026
title deed of the current landownerFile: CONFIRMATION DEED FINAL.pdf14 Jul 2026
JDA between land owner and promoterFile: JDA.pdf14 Jul 2026
EC from 1-4-2011 to till dateFile: ECC-19062026-2556444.pdf14 Jul 2026
E khata issued by local bodyFile: KHATHA (1).pdf14 Jul 2026
ADLR Certified survey sketch Certifying the Boundary of the Proposed land-Original survey sketchFile: Singl Layou tletter.pdf14 Jul 2026
ADLR Certified survey sketch CertifyingFile: Layout Plan Single.pdf14 Jul 2026
original sanctioned drawings, floor plan, sectional drawings and elevationsFile: Sanction Plan 01.pdf14 Jul 2026
original sanctioned drawings, floor plan, sectional drawings and elevationsFile: Sanction plan 2.pdf14 Jul 2026
commencement certificate.File: CC Letter.pdf14 Jul 2026
proposed land in Approved Master plan Certified by the competent authority.File: anekal-maps_0 CDp map-3_page-0001.jpg14 Jul 2026
current landowner as per latest transactionFile: SALE DEED.pdf14 Jul 2026
engineer licence validityFile: Doc_7852.pdf14 Jul 2026
Form-6 engineer certificateFile: Form 6.pdf14 Jul 2026
structural stability certificateFile: Structural stability .pdf14 Jul 2026
FIRE NOC EndosmentFile: PDFGallery_20251111_174815.pdf14 Jul 2026
STP drawing/sewer line drawing/soak pit/septic tank / drawing with engineer signature.File: STP DRAWING.pdf14 Jul 2026
brief estimated cost of construction, certified by the registered Civil Engineer.File: Estimate.pdf14 Jul 2026
Land cost calculation sheetFile: GV Letter (3).pdf14 Jul 2026
guidance value(Self-attested copy) along with guidance certifFile: Valuation Report Sub Reg office (3).pdf14 Jul 2026
Proforma of agreement (AFS)File: Proforma of agreement (AFS) Agreement.pdf14 Jul 2026
Proforma Allotment letterFile: Allotment Letter.pdf14 Jul 2026
RTC, survey 78/1-
Mutation, survey 78/1-
Encumbrance Certificate, survey 78/1-
Conversion/Alienation Order, survey 78/1-
Sale/Title/Gift Deed, survey 78/1-
JDA, survey 78/1-
Khatha, survey 78/1-
Registration CertificateFile: Company Reg Certificate.pdf-
GST CertificateFile: SRI SAI VENTURES GST Certificate.pdf-
Partnership DeedFile: Compnay Partnership Deed.pdf-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Certificate issued by CA Form 1File: Form1 CA.pdf-
Certificate issued by Architect Form 2File: CERTIFICATE OF ARCHITECT-1.pdf-
Certificate issued by Engineer Form 3File: Form 03.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: NO LITIGATION_compressed.pdf-
Balance Sheet 2024 - 2025File: Financial year 2024-25.pdf-
Balance Sheet 2023 - 2024File: Financial year 2023-24.pdf-
Balance Sheet 2022 - 2023File: Balance sheet 2022-23.pdf-
Audited Profit and Loss Statement 2024 - 2025File: Financial year 2024-25.pdf-
Audited Profit and Loss Statement 2023 - 2024File: Financial year 2023-24.pdf-
Audited Profit and Loss Statement 2022 - 2023File: Balance sheet 2022-23.pdf-
Income Tax Return Acknowledgement 2024 - 2025File: Financial year 2024-25.pdf-
Income Tax Return Acknowledgement 2023 - 2024File: Financial year 2023-24.pdf-
Income Tax Return Acknowledgement 2022 - 2023File: DocScanner 17-Feb-2026 12-16 PM.pdf-
CC Letter-
Sanction Plan 01-
Sanction plan 2-
Will Submit later-
Specification-
Will Submit later-
Will Submit later-
Will Submit later-
Form B Af-
Sri Sai Ventures 1-
JD AFFI-
Legal Report-
BESCOM (1)-
watwe noc-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep SRI SAI SAMRUDHI on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: SRI SAI VENTURES

SRI SAI VENTURES has 3 registrations on RERA Karnataka, including SAI KRUPA and SRI SAI VIHAR. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if SRI SAI SAMRUDHI is delayed beyond 31 Dec 2030?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of SRI SAI SAMRUDHI?

The registered promoter entity is SRI SAI VENTURES, a partnership firm as per the filing. Its GSTIN 29AEYFS0783E1ZC can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in SRI SAI SAMRUDHI?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SRI SAI SAMRUDHI?

The professionals named in the filing: Architect: Sunil B G; Engineer: Veeresh Patil; Chartered Accountant: J Seshachalapathi. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SRI SAI SAMRUDHI?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SRI SAI SAMRUDHI. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SRI SAI SAMRUDHI to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.