SOVEN SACHI is a Residential/Group Housing project by Soven Buildtech LLP in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/472/PR/250325/007616 on 25 Mar 2025. Possession is promised by 30 Dec 2026. 28 of the 58 units on this registration are recorded sold or booked, and 16 of 18 construction stages are filed complete.
At a glance
Project
- NameSOVEN SACHI
- TypeResidential/Group Housing
- Location
- Yelahanka
- Bengaluru Urban
- PincodeNot stated
- RERA no.PRM/KA/RERA/1251/472/PR/250325/007616
- ReraGenie IDRG-KA-87562
Builder
- NameSoven Buildtech LLP
- Entity typePartnership Firm
- LLPINABB-9867
- GSTIN29AETFS9820F1ZB
- Authorized SignatorySATISH KUMAR
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on25 Mar 2025
- Promised completion30 Dec 2026
- Revised completionNone
- Buildings1 building record
- Documents filed72 files
Current status
Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A1 | - | - | - | 58 | 0 | 58 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
16 of 18 construction stages are filed complete. The stage furthest along is Electrification, at 98%.
Building: 100% average across the applicable activities
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | 100% |
| Foundation footing work | 100% |
| Upto Plinth Level | 100% |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | 100% |
| Retaining wall (All types) | 100% |
| RCC or MS Framed structure | 100% |
| Masonry Construction | 100% |
| Plastering inside , outside & Ceiling | 100% |
| Joinery: Doors, Windows, Ventilators etc | 100% |
| Basic work of Water supply, Sanitary and Electrification | 100% |
| Dadoing, Skirting, Flooring, Tiles work (All types) | 100% |
| Railing and Grill fixing | 100% |
| Electrification, Water supply and Sanitary Finishing | 98% |
| Painting | 100% |
| Fire prevention and fire fighting fitting and fixture with network | 100% |
| Weather Proof work(tile,concrete) | 100% |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Elevation work | 100% |
| Internal and External work including landscapes as per sanctioned drawings | 98% |
Progress on shared amenities40
As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | 100% |
| Sewage and Drainage System | Yes | 100% |
| Water conservation/rain water harvesting/recharge of ground water | Yes | 100% |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Solid waste management and disposal | Yes | 100% |
| Emergency Evacuation services | No | Not applicable |
| Internal Roads & Footpaths | Yes | 98% |
| Electricity supply transformer and substation | Yes | 100% |
| Storm water drains | Yes | 100% |
| Use of renewable energy | No | Not applicable |
| Sewage Treatment Plant (STP) | Yes | 100% |
| Parks & Tree planting | Yes | 98% |
| Street Lighting | Yes | 98% |
| Electricity | Yes | 100% |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | 98% |
| Club House | No | Not applicable |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | Yes | 100% |
| Gym | No | Not applicable |
| Parks | Yes | 100% |
| Power Backup | Yes | 100% |
| Piped Gas | No | Not applicable |
| Water and Sanitation | Yes | 100% |
| Air Conditioning | No | Not applicable |
| Staircases | Yes | 100% |
| Lifts | Yes | 100% |
| Corridor/Lobbies | Yes | 100% |
| Fire escapes | Yes | 100% |
| Common entrance and exit for the building/common portico/foyer/verandah | Yes | 100% |
| Basement | Yes | 100% |
| Terrace | Yes | 98% |
| Outer Wall | Yes | 100% |
| Open parking areas | No | Not applicable |
| Provision for lodging of management staff and security staff | Yes | 100% |
| Water conservation and renewable energy | No | Not applicable |
| Common storage spaces | Yes | 100% |
Land and ownership1
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| SATISH KUMAR | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 34.26 cr | Rs 41.21 cr |
| On-site expenditure-Salaries of workers | Rs 1.25 cr | Rs 2.31 cr |
| On-site expenditure-Consultants Fees | Rs 79.01 lakh | - |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Nitin S Kamath |
| Engineer | Chetan Megharaj Sidgiddi |
| Chartered Accountant | MADHUSUDHAN N HIREMATH |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed72
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/472/PR/250325/007616 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: CA2 Certificate Q2 26-27.pdf | 15 Oct 2026 |
| Q2 2026-27 Form-5 Certificate issued by ArchitectFile: A1 FORM 5 Architect Q2 26-27.pdf | 15 Oct 2026 |
| Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: E2 Form-6, Engineer Q2 26-27 (1).pdf | 15 Oct 2026 |
| Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres) | 15 Oct 2026 |
| Q2 2026-27 KPTCL- BESCOM | 15 Oct 2026 |
| Q2 2026-27 Fire and Safety | 15 Oct 2026 |
| Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: CA1 Certificate Q1 26-27.pdf | 13 Jul 2026 |
| Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form-5, Architect Q1 26 27.pdf | 13 Jul 2026 |
| Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: E1 Form-6, Engineer Q1 26-27.pdf | 13 Jul 2026 |
| Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres) | 13 Jul 2026 |
| Q1 2026-27 KPTCL- BESCOM | 13 Jul 2026 |
| Q1 2026-27 Fire and Safety | 13 Jul 2026 |
| Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: CA3 Certificate Q3 25-26.pdf | 14 May 2026 |
| Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Q3 (25-26) Certificate - Architect (1).pdf | 14 May 2026 |
| Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form -6, Engineer Q3 2025-26.pdf | 14 May 2026 |
| Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres) | 14 May 2026 |
| Q3 2025-26 KPTCL- BESCOM | 14 May 2026 |
| Q3 2025-26 Fire and Safety | 14 May 2026 |
| Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: CA4 Certificate Q4 25-26.pdf | 14 May 2026 |
| Q4 2025-26 Form-5 Certificate issued by ArchitectFile: A4 Form 5 Architect Q4 25-26.pdf | 14 May 2026 |
| Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: E4 Form-6, Engineer Q4 25-26.pdf | 14 May 2026 |
| Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres) | 14 May 2026 |
| Q4 2025-26 KPTCL- BESCOM | 14 May 2026 |
| Q4 2025-26 Fire and Safety | 14 May 2026 |
| EC from 1/4/2010 to 31/3/2022File: EC 2008-2022.pdf | 21 Mar 2025 |
| KSPCB NOCFile: KSPCB NOC.pdf | 21 Mar 2025 |
| Building License OriginalFile: cc_BBMP BUILDING LIEANCE.pdf | 21 Mar 2025 |
| Approved building plan - Plan Base & Ground FloorFile: Plan Base & Ground Floor (1).pdf | 21 Mar 2025 |
| Plan First & Second FloorFile: Plan First & Second Floor (1).pdf | 21 Mar 2025 |
| Plan Third & Fourth FloorFile: Plan Third & Fourth Floor (1).pdf | 21 Mar 2025 |
| Plan Fifth & Terrace FloorFile: Plan Fifth & Terrace Floor (1).pdf | 21 Mar 2025 |
| CC Request Letter 21-03-2025File: CC Request Letter 21-03-2025.pdf | 21 Mar 2025 |
| RTC, survey Sy. No. 19/2 (Old Sy. No 19) | - |
| Mutation, survey Sy. No. 19/2 (Old Sy. No 19) | - |
| Encumbrance Certificate, survey Sy. No. 19/2 (Old Sy. No 19) | - |
| Conversion/Alienation Order, survey Sy. No. 19/2 (Old Sy. No 19) | - |
| Sale/Title/Gift Deed, survey Sy. No. 19/2 (Old Sy. No 19) | - |
| Khatha, survey Sy. No. 19/2 (Old Sy. No 19) | - |
| Registration CertificateFile: Certification Of Incorporation.pdf | - |
| GST CertificateFile: Soven Gst Certificate.pdf | - |
| Partnership DeedFile: LLP Agreement (1).pdf | - |
| Partner Details | - |
| Partner Details | - |
| Partner Details | - |
| Certificate issued by CA Form 1File: RERA Certificate - Reg 1.pdf | - |
| Certificate issued by Architect Form 2File: 03) Certificate - Areas.pdf | - |
| Certificate issued by Engineer Form 3File: 05) Engineer - Form 6_compressed.pdf | - |
| Project Chartered Accountant | - |
| Project Engineer | - |
| Project Architect | - |
| AffidavitFile: No litigation Scheddule Property.pdf | - |
| Balance Sheet 2023 - 2024File: Soven Balance Sheet 23-24.pdf | - |
| Audited Profit and Loss Statement 2023 - 2024File: Soven Statement of Profit & Loss 23-24.pdf | - |
| Income Tax Return Acknowledgement 2023 - 2024File: Soven ITR Acknowledgement 23-24.pdf | - |
| WILL SUBMIT LATER | - |
| SANCTION PLAN FULL | - |
| Plan Fifth & Terrace Floor (1) | - |
| 04) Engineer - Structural Design Compliances | - |
| 06) Engineer - Specifications | - |
| Soven Sachi Brochure 08-03-2025_compressed | - |
| Registered Relinquishment Deed | - |
| Sale Agreement 01 | - |
| Allotment Letter (1) | - |
| Rera Stamp Affidavit Form-B | - |
| Rera Stamp Affidavit - 03 | - |
| Advocate | - |
| BESCOM NOC (1) | - |
| BWSSB NOC (1) | - |
| KSPCB | - |
| FIRE NOC | - |
| AIRPORT NOC | - |
| Request for Cost Correction | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep SOVEN SACHI on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Prestige Park Grove
PRESTIGE PROJECTS PRIVATE LIMITED
Prestige Lakeside Habitat
Prestige Habitat Ventures
LivingTree by Kalyani Developers
Kalyani Tech Park Private Limited
PRESTIGE FALCON CITY
PRESTIGE NOTTINGHILL INVESTMENTS
SATTVA CITY
SATTVA CITY PRIVATE LIMITED
GM AMBITIOUS ENCLAVE
M/s. Allam Infinite India Private Limited
See every Bengaluru Urban project, with the district possession charts
Builder: Soven Buildtech LLP
Soven Buildtech LLP has 1 registration on RERA Karnataka, including SOVEN SACHI. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if SOVEN SACHI is delayed beyond 30 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of SOVEN SACHI?
The registered promoter entity is Soven Buildtech LLP, a partnership firm as per the filing. Its LLPIN ABB-9867 and GSTIN 29AETFS9820F1ZB can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in SOVEN SACHI?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at SOVEN SACHI?
The professionals named in the filing: Architect: Nitin S Kamath; Engineer: Chetan Megharaj Sidgiddi; Chartered Accountant: MADHUSUDHAN N HIREMATH. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SOVEN SACHI?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback