Home / Browse projects / Bengaluru Urban, Karnataka / South Park Phase 1

Registration approved No litigation declared Residential/Group Housing project

South Park Phase 1

By ESTEEM SOUTH PARKS PRIVATE LIMITED

RG-KA-74588 · RERA PRM/KA/RERA/1251/310/PR/090523/005916 · Last updated on RERA Karnataka portal: 14 Aug 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Aug 2026Possession promisedno revision filed
17 of 17Construction stages doneevery applicable stage filed complete
54 of 191Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 130 documents Report an error

South Park Phase 1 is a Residential/Group Housing project by ESTEEM SOUTH PARKS PRIVATE LIMITED in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/090523/005916 on 9 May 2023. Possession is promised by 15 Aug 2026. 137 of the 191 units on this registration are recorded sold or booked, and 17 of 17 construction stages are filed complete.

At a glance

Project

  • NameSouth Park Phase 1
  • TypeResidential/Group Housing
  • Location
    • Bengaluru South
    • Bengaluru Urban
    • 560097
  • Pincode560097
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/310/PR/090523/005916
  • ReraGenie IDRG-KA-74588

Builder

  • NameESTEEM SOUTH PARKS PRIVATE LIMITED
  • Entity typeCompany
  • CINU70109KA2019PTC123620
  • GSTIN29AAFCE4593C1ZJ
  • Authorized SignatoryABHISHEK AHUJA
  • DirectorABHISHEK AHUJA
  • DirectorsNARAINDAS BODARAM, ABHISHEK AHUJA, GAURAV AHUJA
  • Project HeadABHISHEK AHUJA
  • Other registrations1 more →

Key dates

this monthRegisteredMay 2023PromisedAug 2026

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on9 May 2023
  • Promised completion15 Aug 2026
  • Revised completionNone
  • Buildings2 building records
  • Documents filed130 files

Current status

72%137 of 191 units booked
3.3%Of the estimated cost spent so far

Figures as on 14 Aug 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
D---87087
E---1040104

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 14 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

17 of 17 construction stages are filed complete.

Building: 100% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)100%
RCC or MS Framed structure100%
Masonry Construction100%
Plastering inside , outside & Ceiling100%
Joinery: Doors, Windows, Ventilators etc100%
Basic work of Water supply, Sanitary and Electrification100%
Dadoing, Skirting, Flooring, Tiles work (All types)100%
Railing and Grill fixing100%
Electrification, Water supply and Sanitary Finishing100%
Painting100%
Fire prevention and fire fighting fitting and fixture with network100%
Weather Proof work(tile,concrete)100%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation workNot applicable
Internal and External work including landscapes as per sanctioned drawings100%

Progress on shared amenities40

As on 14 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes99%
Sewage and Drainage SystemYes100%
Water conservation/rain water harvesting/recharge of ground waterYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes100%
Solid waste management and disposalYes100%
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsNoNot applicable
Electricity supply transformer and substationNoNot applicable
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes100%
Parks & Tree plantingYes100%
Street LightingNoNot applicable
ElectricityYes100%
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseYes100%
Community HallYes100%
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityYes100%
Swimming PoolNoNot applicable
GymYes100%
ParksYes100%
Power BackupNoNot applicable
Piped GasNoNot applicable
Water and SanitationNoNot applicable
Air ConditioningNoNot applicable
StaircasesYes100%
LiftsYes100%
Corridor/LobbiesYes100%
Fire escapesYes100%
Common entrance and exit for the building/common portico/foyer/verandahNoNot applicable
BasementNoNot applicable
TerraceNoNot applicable
Outer WallYes100%
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area7,953 sq m
Named landowners1
LandownerVillageDistrict
esteem south park private limited--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 55.00 cr
Cost incurredRs 1.81 cr
Spent of the estimate3.28%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 55.00 crRs 89.21 lakh
On-site expenditure-Salaries of workers-Rs 49.17 lakh
On-site expenditure-Consultants Fees-Rs 13.76 lakh
On-site expenditure-Site Overhead-Rs 5.89 lakh
Payment of taxes-Rs 21.99 lakh
Principal sum and interest payable to financial institutions-Scheduled Banks-Rs 60,490

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectArchitects Inc
EngineerNadig Consultants
Chartered AccountantSagar and Dhananjaya

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed130

As listed on the registration, under the names the promoter filed them with; the newest 80 of 130 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/090523/005916 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: ESP 1 - Form 4 CA - Q1 2627 - Final_compressed.pdf14 Aug 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: ESP 1 Form 5 Arch q1 2627.pdf14 Aug 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: ESP 1 DE Form 6 - Q 1 26 27.pdf14 Aug 2026
Q1 2026-27 Water supply and sewage board14 Aug 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)14 Aug 2026
Q1 2026-27 KPTCL- BESCOM14 Aug 2026
Q1 2026-27 Fire and Safety14 Aug 2026
Q1 2026-27 Airport Authority of India14 Aug 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: ESP 1 - Form 4 CA - Q4 2526 - Final_compressed.pdf1 Jun 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: ESP 1 from 5 q4 25 26 arch cert.pdf1 Jun 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: ESP 1 DE Form-6 EC - Q4 25 26.pdf1 Jun 2026
Q4 2025-26 Water supply and sewage board1 Jun 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)1 Jun 2026
Q4 2025-26 KSPCB- MOEF (Above 50 Acres)1 Jun 2026
Q4 2025-26 KPTCL- BESCOM1 Jun 2026
Q4 2025-26 Fire and Safety1 Jun 2026
Q4 2025-26 Airport Authority of India1 Jun 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: ESP 1 - Form 4 CA - Q3 2526 3-4-26 (1)_compressed.pdf1 May 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Q3 25-26 15JAN26.pdf1 May 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: ESP 1 Form-6 EC - Q3 25 26 - January 2025.pdf1 May 2026
Q3 2025-26 Water supply and sewage board1 May 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)1 May 2026
Q3 2025-26 KSPCB- MOEF (Above 50 Acres)1 May 2026
Q3 2025-26 KPTCL- BESCOM1 May 2026
Q3 2025-26 Fire and Safety1 May 2026
Q3 2025-26 Airport Authority of India1 May 2026
FORM DFile: Certificate - Esteem South Parks - form - D.pdf13 Apr 2023
FORM C - SHIVA EnterprisesFile: Shiva Enterprises Partnership Deed.pdf13 Apr 2023
Oder of amalgamationFile: Amalgamation Order or Endorsement - Shiva Enterprises.pdf13 Apr 2023
AFSFile: Phase 1 Agreement for Sale draft for RERA.pdf13 Apr 2023
Allotment LetterFile: ESPALLOTMENT LETTER DRAFT.pdf13 Apr 2023
Bank Certificate for RERA designated accountFile: Bank Certificate - Phase 1.pdf7 Apr 2023
Agreement for Sale as per RERA formatFile: Agreement for Sale draft - Phase 1.pdf7 Apr 2023
Allotment Letter - as per RERA formatFile: ESP_ALLOTMENT LETTER DRAFT.pdf7 Apr 2023
Title Document 1 - Deed of AmalgamationFile: Shiva Enterprises Amalgation Deed 3564 of 2015-16.pdf7 Apr 2023
Title Document 2 - Partnership DeedFile: Shiva Enterprises Partnership Deed.pdf7 Apr 2023
CA expenditure detailsFile: CA Cert Phase 1.pdf7 Apr 2023
Bank in principle approvalFile: In Principle Sanction Letter - PNB.pdf7 Apr 2023
Bank account details letterFile: Bank Certificate Phase 1.pdf7 Apr 2023
Sale Deed Sy.No.19/6File: Sale Deed 19-6.pdf6 Mar 2023
Sale Deed Sy.No.19/7File: Sale Deed 19-7.pdf6 Mar 2023
Sale Deed Sy.No.19/2File: SALEDEED 18-2.pdf6 Mar 2023
Sale Deed Sy.No.19/3A and 3BFile: Sale Deed 19-3A - 3B.pdf6 Mar 2023
Sale Deed Sy.No.5/2File: Sale Deed Sy No 5 - 2.pdf6 Mar 2023
Sale Deed Sy.No.19/4File: Sale Deed Sy No 19 - 4.pdf6 Mar 2023
kathaFile: katha.pdf6 Mar 2023
DraftSale AgreementFile: Phase 1 Agreement for Sale draft.pdf6 Mar 2023
Directors report 22File: Director Report 2021-22.pdf13 Feb 2023
Directors report 21File: Directors report 2020-21.pdf13 Feb 2023
Directors report 20File: Directors Report_19-20.pdf13 Feb 2023
auditors report 22File: Audit report 2021-22.pdf13 Feb 2023
auditors report 21File: Audit report 2020-21.pdf13 Feb 2023
auditors report 20File: Audit report 2019-20.pdf13 Feb 2023
Balance sheet 22File: Balance Sheet 2021-22.pdf13 Feb 2023
Balance sheet 21File: Balance Sheet 2020-21.pdf13 Feb 2023
Balance sheet 20File: Balance sheet 2019-20.pdf13 Feb 2023
P and L 22File: P &L 2021-22.pdf13 Feb 2023
P and L 21File: P & L 2020-21.pdf13 Feb 2023
P and L 20File: P & L 2019-20.pdf13 Feb 2023
auditor registrationFile: CA Sagar COP-min.pdf13 Feb 2023
proforma allotment letterFile: ESP allotment Draft - RERA.pdf13 Feb 2023
engineer registration certificateFile: Nadig REgn BBMP Certificate - AN.pdf13 Feb 2023
engineer structural stability certificateFile: Form 6B - Esteem South Park - Phase 1.pdf13 Feb 2023
CDPFile: BDA - CDP- GOTTIGERE1.pdf13 Feb 2023
village mapFile: Village Map - Gottigere.pdf13 Feb 2023
bescom ddFile: BESCOM - NOC -DD-COPY.pdf13 Feb 2023
bwssb receiptFile: BWSSB Fee Paid Receipt.pdf13 Feb 2023
self attested panFile: South parks PAN Sign copy.pdf13 Feb 2023
STP drawingFile: STP DRAWING.pdf13 Feb 2023
phase wise drawingsFile: PHASE 01 DRAWINGS.pdf13 Feb 2023
KSPCB CFEFile: KSPCB NOC- Gottigere.pdf13 Feb 2023
khataFile: Katha Extract, Certificate Sy No 18-2.pdf13 Feb 2023
khataFile: Khatha Certificate & Extract - Sy No 5-2 - Gottigere.pdf13 Feb 2023
khataFile: Khatha Certificate & Khatha Extract - 19-4.pdf13 Feb 2023
khataFile: Khatha Certificate & Khatha Extract - 19-7 - 23G.pdf13 Feb 2023
khataFile: Khatha Certificate & Khatha Extract 19-3A & B.pdf13 Feb 2023
khataFile: Khatha Certificate & Khatha Extract - 19-6.pdf13 Feb 2023
architect certificateFile: COA CERTIFICATE.pdf13 Feb 2023
CA certificateFile: CA Sagar COP-min.pdf13 Feb 2023
civil cost summaryFile: Form 6B - Esteem South Park - Phase 1.pdf13 Feb 2023

How this compares with Bengaluru Urban

72%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep South Park Phase 1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmSouth Park Phase 1Other 34Dot size: filed unitsN

Filed coordinates, straight-line distance. 34 registered projects within 2 km.

Builder: ESTEEM SOUTH PARKS PRIVATE LIMITED

ESTEEM SOUTH PARKS PRIVATE LIMITED has 2 registrations on RERA Karnataka, including South Park phase 2 and South Park Phase 1. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if South Park Phase 1 is delayed beyond 15 Aug 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of South Park Phase 1?

The registered promoter entity is ESTEEM SOUTH PARKS PRIVATE LIMITED, a company as per the filing. Its CIN U70109KA2019PTC123620 and GSTIN 29AAFCE4593C1ZJ can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in South Park Phase 1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at South Park Phase 1?

The professionals named in the filing: Architect: Architects Inc; Engineer: Nadig Consultants; Chartered Accountant: Sagar and Dhananjaya. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in South Park Phase 1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About South Park Phase 1. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save South Park Phase 1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.