SOUNDARYA KAMAKSHI
RG-KA-48147 · RERA PRM/KA/RERA/1251/446/PR/180222/002210 · Last updated on RERA Karnataka portal: 2 Feb 2022
Source: official RERA Karnataka filing
Red flags
- Completion date moved by 12 months
- 1 extension taken
Clear
- No complaints on record
- Separate project account declared
Saved.
SOUNDARYA KAMAKSHI is a Residential/Group Housing project by SOUNDARYA CONSTRUCTIONS in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/180222/002210 on 22 Feb 2018. Possession is promised by 31 Mar 2020. The completion date has moved by 12 months from the original filing.
At a glance
Project
- NameSOUNDARYA KAMAKSHI
- TypeResidential/Group Housing
- Location
- Bengaluru East
- Bengaluru Urban
- PincodeNot stated
- RERA no.PRM/KA/RERA/1251/446/PR/180222/002210
- ReraGenie IDRG-KA-48147
Builder
- NameSOUNDARYA CONSTRUCTIONS
- Entity typePartnership Firm
- Authorized SignatoryS.P.HOMBANNA
- OthersV.S.SURESH, R.JAGADEESH
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on22 Feb 2018
- Promised completion31 Mar 2020
- Revised completionRevised to 31 Mar 2020 (originally 31 Mar 2019)
- Buildings3 building records
- Documents filed62 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| WING A | - | - | - | 25 | 0 | 25 |
| WING B | - | - | - | 36 | 0 | 36 |
| WING C | - | - | - | 50 | 0 | 50 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 2 Feb 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building:
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Retaining wall (All types) | - |
| Plinth level Beam | - |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | - |
| RCC or MS Framed structure | - |
| Masonry construction: Bricks, Concrete blocks etc | - |
| Plastering inside , outside & Ceiling | - |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Fire prevention and fire fighting fitting and fixture with network | - |
| Weather Proof work(tile,concrete) | - |
| Painting | - |
| Elevation work | - |
| Internal and External work including landscapes as per santioned drawings | - |
Progress on shared amenities41
As on 2 Feb 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Internal Roads & Footpaths | No | Not applicable |
| Sewage and Drainage System | Yes | - |
| Parks & Tree planting | No | Not applicable |
| Street Lighting | Yes | - |
| Provision for community buildings and for treatment and disposal of sewage and sullage water | Yes | - |
| Solid waste management and disposal | Yes | - |
| Water conservation | Yes | - |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | Yes | - |
| Education/Health/Other public amenities | No | Not applicable |
| Electricity supply transformer and substation | Yes | - |
| Emergency Evacuation services | No | Not applicable |
| Storm water drains | No | Not applicable |
| Use of renewable energy | No | Not applicable |
| Water conservation/rain water harvesting/recharge of ground water | No | Not applicable |
| Electricity | Yes | - |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | - |
| Club House | Yes | - |
| Community Hall | Yes | - |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | No | Not applicable |
| Gym | Yes | - |
| Parks | No | Not applicable |
| Power Backup | Yes | - |
| Gas | No | Not applicable |
| Water and Sanitation | Yes | - |
| Air Conditioning And incerntion | No | Not applicable |
| Staircases | Yes | - |
| Lifts | Yes | - |
| Staircases and Lift lobbies, corridor,lobbies, corridor | Yes | - |
| Fire escapes | Yes | - |
| Common entrance and exit for the building / common portico/foyer/verandah | Yes | - |
| Basement | Yes | - |
| Terrace | Yes | - |
| Outer Wall | Yes | - |
| Open parking areas and common storage spaces | Yes | - |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | Yes | - |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterFinancial crunch; Shortage of Labour
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed62
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/180222/002210 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| BANK ACCOUNT CHANGE REQUESTFile: QUERY - REPLY.pdf | 2 Feb 2022 |
| CLARIFICATION FOR PREVIOUS AND NEW END DATEFile: QUERY - REPLY.pdf | 2 Feb 2022 |
| CLARIFICATION LETTERFile: 1 CLARIFICTION LETTER.pdf | 1 Mar 2021 |
| LOAN CLOSURE LETTERFile: 2 Tata Capital - CLOSURE LETTER.pdf | 1 Mar 2021 |
| ESCROW ACCOUNT BANK STATEMENTFile: ICICI BANK Escrow acc.pdf | 1 Mar 2021 |
| SEC 18 AFFIDAVITFile: Affidavit-Soundarya Kamakshi.pdf | 1 Mar 2021 |
| CURRENT ACCOUNT BANK STATEMENTFile: CURRENT ACCOUNT BANK STATEMENT.pdf | 1 Mar 2021 |
| CertificateFile: 1_Firm Registration Certificate.pdf | - |
| Architect Certificate for Work Completion Schedule till DateFile: ARC Work Completion.pdf | - |
| Engineer Certificate for Work Completion Schedule till DateFile: ENG Work Completion.pdf | - |
| CA Certificate for Funds UtilizationFile: CA Fund Utilization.pdf | - |
| Architect Certificate for Pending Work Completion Schedule.File: ARC WOrk Pending.pdf | - |
| Engineer Certificate for Pending Work Completion Schedule.File: ENG Work Pending.pdf | - |
| CA Certificate for Funds required for Project CompletionFile: CA Fund Required.pdf | - |
| AffidavitFile: SECTION18 AFFIDAVIT.pdf | - |
| Latest Encumbrance CertificateFile: FORM-B_ NEW.pdf | - |
| Details Of Sold/ Un-sold UnitsFile: Kamakshi - SoldUnsoldDetails.xlsx | - |
| Document 1File: Soundarya Kamakshi EC.pdf | - |
| Document 2File: Bank statement.pdf | - |
| Document 3File: Commencement Certificate.pdf | - |
| Document 4File: Elevation Section Site Plan.pdf | - |
| 6_Commencement Certificate | - |
| Floor Plan | - |
| Elevation Section Site Plan | - |
| 17_Proforma for Sale Deed | - |
| 9_Proforma for Sale Agreement Kamakshi | - |
| RTC | - |
| Elevation Section Site Plan | - |
| Floor Plan | - |
| 13_ALLOTEMENT LETTER - SOUNDARYA | - |
| 14_Kamakshi Brochure | - |
| 16_Project Specifications | - |
| EC | - |
| Katha | - |
| 19_JDA | - |
| 18_Title Deed with Area Sketch | - |
| 10_Conversion Certificate | - |
| 15_NOC BWSSB | - |
| Floor Plan | - |
| Project Specifications | - |
| 19_Supplemental Agreement | - |
| Balance Sheet 2016 - 2017File: Soundarya ITR Acts 2015-16.pdf | - |
| Balance Sheet 2015 - 2016File: Soundarya ITR Acts 2014-15.pdf | - |
| Balance Sheet 2014 - 2015File: Soundarya ITR Acts 2013-14.pdf | - |
| Audited Profit and Loss Statement 2016 - 2017File: Soundarya ITR Acts 2015-16.pdf | - |
| Audited Profit and Loss Statement 2015 - 2016File: Soundarya ITR Acts 2014-15.pdf | - |
| Audited Profit and Loss Statement 2014 - 2015File: Soundarya ITR Acts 2013-14.pdf | - |
| Director's Report 2016 - 2017File: Soundarya ITR Acts 2015-16.pdf | - |
| Director's Report 2015 - 2016File: Soundarya ITR Acts 2014-15.pdf | - |
| Director's Report 2014 - 2015File: Soundarya ITR Acts 2013-14.pdf | - |
| Cash Flow Statement 2016 - 2017File: Soundarya ITR Acts 2015-16.pdf | - |
| Cash Flow Statement 2015 - 2016File: Soundarya ITR Acts 2014-15.pdf | - |
| Auditor's Report 2016 - 2017File: Soundarya ITR Acts 2015-16.pdf | - |
| Auditor's Report 2015 - 2016File: Soundarya ITR Acts 2014-15.pdf | - |
| Auditor's Report 2014 - 2015File: Soundarya ITR Acts 2013-14.pdf | - |
| Income Tax Return Acknowledgement 2016 - 2017File: Soundarya ITR Acts 2015-16.pdf | - |
| Income Tax Return Acknowledgement 2015 - 2016File: Soundarya ITR Acts 2014-15.pdf | - |
| Income Tax Return Acknowledgement 2014 - 2015File: Soundarya ITR Acts 2013-14.pdf | - |
| Form B | - |
| Prospectus/BrochureFile: Will upload later.pdf | - |
| Advertisement Copy 1File: Will upload later.pdf | - |
| Tower Excel SheetFile: PRM_KA_RERA_1251_446_PR_180222_002210_WING A.xlsx | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep SOUNDARYA KAMAKSHI on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Prestige Park Grove
PRESTIGE PROJECTS PRIVATE LIMITED
Prestige Lakeside Habitat
Prestige Habitat Ventures
LivingTree by Kalyani Developers
Kalyani Tech Park Private Limited
PRESTIGE FALCON CITY
PRESTIGE NOTTINGHILL INVESTMENTS
SATTVA CITY
SATTVA CITY PRIVATE LIMITED
GM AMBITIOUS ENCLAVE
M/s. Allam Infinite India Private Limited
See every Bengaluru Urban project, with the district possession charts
Builder: SOUNDARYA CONSTRUCTIONS
SOUNDARYA CONSTRUCTIONS has 1 registration on RERA Karnataka, including SOUNDARYA KAMAKSHI. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if SOUNDARYA KAMAKSHI is delayed beyond 31 Mar 2020?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of SOUNDARYA KAMAKSHI?
The registered promoter entity is SOUNDARYA CONSTRUCTIONS, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in SOUNDARYA KAMAKSHI?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
What should I check before booking in SOUNDARYA KAMAKSHI?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.