SOLSTICE PHASE- I
By NEELAM FINANCE (BOMBAY ) PVT LTD
RG-MH-10668 · RERA P51900002750 · Last updated on MahaRERA portal: 14 May 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- 7 complaints at MahaRERA
- Completion date moved by 48 months
- 4 extensions taken
Clear
- No litigation declared
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SOLSTICE PHASE- I is a Residential / Group Housing project by NEELAM FINANCE (BOMBAY ) PVT LTD in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51900002750 on 4 Aug 2017. Possession is promised by 31 Dec 2026. The completion date has moved by 48 months from the original filing. 297 of the 332 units on this registration are recorded sold or booked, and 0 of 11 construction stages are filed complete. 7 complaints are on record with the regulator.
At a glance
Project
- NameSOLSTICE PHASE- I
- TypeResidential / Group Housing
- Location
- Eastern Express Highway
- Kamraj Nagar
- Kurla
- Mumbai Suburban
- 400077
- Pincode400077
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51900002750
- ReraGenie IDRG-MH-10668
Builder
- NameNEELAM FINANCE (BOMBAY ) PVT LTD
- Entity typeCompany
- ChairpersonCHAMPALAL KISHORECHANDRA VARDHAN
- Declared earlier projects2 →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on4 Aug 2017
- Promised completion31 Dec 2026
- Revised completionRevised to 31 Dec 2026 (originally 30 Dec 2022)
- Buildings1 building record
- Documents filed103 files
Current status
Figures as on 14 May 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SETARIA AND SAVERIA | NA | 31 | 26 | 332 | 0 | 332 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 14 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
0 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 90%.
SETARIA AND SAVERIA: 89% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 90% |
| Basement (if any) | 90% |
| Podiums (if any) | 90% |
| Plinth | 90% |
| Stilt Floor | 90% |
| Slabs of Super Structure | 90% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 90% |
| Sanitary Fittings within the flats / premises | 90% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 85% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 80% |
Progress on shared amenities15
As on 14 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 90% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 90% |
| Landscaping & Tree Planting | Yes | 90% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 40% |
| Energy managemcnt | Yes | 50% |
| Fire protection and fire safety requirements | Yes | 90% |
| Electrical meter room, sub-station, receiving station | Yes | 50% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Parking filed258
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership1
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| OM SAI GANESH CHS LTD. | Kurla | Mumbai Suburban |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| SETARIA AND SAVERIA | NA | Rs 176.45 cr | Rs 153.63 cr |
| - | NA | Rs 5.22 cr | Rs 5.00 cr |
Certifying professionals and partners8
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | VASTUVIKALP |
| Architect | SAURABH SANJEEV MAYEKAR |
| Architect | ARCHITECT HAFEEZ CONTRACTOR |
| Architect | S G DALVI & ASSOCIATES |
| Engineer | GHANSHYAM SUTAR |
| Engineer | J W CONSULTANTS |
| Chartered Accountant | SANKET R SHAH & ASSOCIATES |
| Chartered Accountant | A D SHETH & ASSOCIATES |
| Partner | Role in project |
|---|---|
| NEELAM FINANCE (BOMBAY ) PVT LTD | - |
Extensions applied for4
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDue to Covid Pandemic situation project stuck and increase of estimation cost of project.
Reason as filed by the promoterDUE TO COVID 19 WE ARE NOT ABLE TO COMPLETE OUR PROJECT DUE SHORTAGE OF MATERIAL PLEASE GRANT US EXTENSION TILL 31/12/2024
Reason as filed by the promoter1. A part of the proposed extension of the DP Eastern Freeway (from Ghatkopar to Vikhrolij passes through the said property. 2. On or about 04.12.2023, Prerna CHS & Adarsh CHS filed Writ Petition (L) No.11493 of 2023 praying inter alia for removal of the Developer u/s 13(2). SRA was also made a party to the said Writ Petition. The Hon'ble High Court had dismissed the Writ Petition vide an order dated 04.12.2023 and had referred to the SRA letter dt 11.08.2022 and observed that on account of the eligibility issue not having been decided, the Developer could not proceed with the Slum Scheme. 3.
Reason as filed by the promoterTHE REASONS FOR DELAY 1 Plot bearing CTS No 195 (Part) corresponding to S No 249 (Part) of Village Ghatkopar, Taluka Kurla admeasuring 196,905 sq mtrs popularly known as Ramabaı Ambedkar Nagar (the property). 2 A part of the proposed extension of the DP Eastern Freeway [from Ghatkopar to Vikhroli] passes through the said property 3 On or about 04 12 2023, Prerna CHS & Adarsh CHS filed Writ Petition (L) No.11493 of 2023 praying inter alia for removal of the Developer u/s 13(2). SRA was also made a party to the said Writ Petition. The Hon'ble High Court had dismissed the Writ Petition vide an or
Litigation declared4
| Case | Court | Status |
|---|---|---|
| SUIT/670/1987/1987 | HIGH COURT | PENDING |
| PS/254/15/2015 | VIKHROLI COURT | PENDING |
| 224/17/2017 | CHIEF METROPOLITAN MAGISTRATE COURT | PENDING |
| 1567/2015/2015 | VIKHROLI COURT | PENDING |
Complaints filed with MahaRERA7
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000429382 | pooja tripathi | M/S. NEELAM FINANCE (BOMBAY) PVT. LTD | 22/02/2024 |
| CC006000000500632 | Neelam Finance (Bombay) Private Limited | Reena Amit Patel and Amit Hasmukhbhai Patel | 30/05/2024 |
| CC12400079 | Dilip Keshavlal Shah | NEELAM FINANCE (BOMBAY ) PVT LTD | 11/09/2024 |
| CC12502126 | NEELAM FINANCE (BOMBAY ) PVT LTD | MR AKSHAY LAXMAN KANDARKAR | 28/06/2025 |
| CC12503110 | Ritesh Vinaychandra Shah | NEELAM FINANCE (BOMBAY ) PVT LTD | 04/09/2025 |
| CC12600769 | Biharilal Harishchandra Kumbhare | NEELAM FINANCE (BOMBAY ) PVT LTD | 10/02/2026 |
| CC12604722 | Punit Pravin Boda | NEELAM FINANCE (BOMBAY ) PVT LTD | 27/07/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 29 Aug 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 22 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 26 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 17 Sep 2018Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 7 Apr 2022
Documents filed103
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 103 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1 - NFBPL (1).pdf | 14 May 2026 |
| Withdrawal Update Form 1File: Form 1 - NFBPL (1).pdf | 14 May 2026 |
| Withdrawal Update Form 2File: 2.pdf | 14 May 2026 |
| Withdrawal Update Form 2File: 2.pdf | 14 May 2026 |
| Withdrawal Update Form 3File: Form III (Mar 26) - SANKET SHAH.pdf | 14 May 2026 |
| Withdrawal Update Form 3File: Form III (Mar 26) - SANKET SHAH.pdf | 14 May 2026 |
| Withdrawal Update Form 1File: Form 1 Jun 25 - NFBPL (1).pdf | 5 Mar 2026 |
| Withdrawal Update Form 2File: form 2 (1)-DSC.pdf | 5 Mar 2026 |
| Withdrawal Update Form 3File: NFBPL FORM 3 CA CERTIFICATE 2026_11zon.pdf | 5 Mar 2026 |
| Form 2A (FY 2024-2025)File: 2A-DSC.pdf | 14 Jan 2026 |
| Withdrawal Update Form 1File: Form 1 Jun 25 - NFBPL.pdf | 4 Dec 2025 |
| Withdrawal Update Form 2File: form 2.pdf | 4 Dec 2025 |
| Withdrawal Update Form 3File: Form III Neelam Finance.pdf | 4 Dec 2025 |
| Withdrawal Update Form 1File: form 1.pdf | 23 Aug 2025 |
| Withdrawal Update Form 2File: form 2.pdf | 23 Aug 2025 |
| Withdrawal Update Form 3File: form 3 (1).pdf | 23 Aug 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Mar 25 - NFBPL.pdf | 1 Jul 2025 |
| Certificates of CA (Form 3)File: Form III (Mar 25) - NFBPL_compressed (1).pdf | 1 Jul 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Mar 25 - NFBPL.pdf | 1 Jul 2025 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold (Mar 25) - NFBPL_compressed.pdf | 1 Jul 2025 |
| Declaration about Commencement CertificateFile: CC Bldg No 04 nfbpl.pdf | 1 Jul 2025 |
| Form 3File: Form III (Mar 25) - NFBPL_compressed.pdf | 30 May 2025 |
| Certificates of CA (Form 3)File: ca form 3.pdf | 20 Jan 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 SEP 24.pdf | 3 Jan 2025 |
| Certificates of CA (Form 3)File: FORM 3 SEP 24.pdf | 3 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 SEP 24.pdf | 3 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: INVENTORY SEP 24.pdf | 3 Jan 2025 |
| CERSAI detailsFile: CERSAI.pdf | 3 Jan 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A 23-24.pdf | 3 Jan 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 Neelam Finance pvt ltd.pdf | 2 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: rera scan 2.pdf | 14 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: rera scan 2.pdf | 14 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: rera scan1.pdf | 14 Dec 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 (Sep 23) - NFBPL Architect.pdf | 13 Dec 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 (Sep 23) - NFBPL Engineer.pdf | 13 Dec 2023 |
| Declaration in FORM BFile: Affidavit cum declaration.pdf | 11 Dec 2023 |
| CERSAI detailsFile: cersai report.pdf | 11 Dec 2023 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold unsold.pdf | 11 Dec 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architech Certificate - NFBPL.pdf | 13 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate - NFBPL.pdf | 13 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A Supervisor Certificate - NFBPL.pdf | 13 Oct 2023 |
| Certificates of CA (Form 3)File: Form III (30 Sep 23) - NFBPL.pdf | 13 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: NF - FORM 5.pdf | 13 Oct 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A - NFBPL.pdf | 20 Apr 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form_V_Mar_22_NFBPL.pdf | 4 Jan 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate for RERA.pdf | 19 Dec 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate.pdf | 19 Dec 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A-Quality assurance.pdf | 19 Dec 2022 |
| Certificates of CA (Form 3)File: FORM III SEP 22 SOLSTICE.pdf | 12 Dec 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf | 13 Oct 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER'S CERTIFICATE 02 .pdf | 13 Oct 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER'S CERTIFICATE 02.pdf | 13 Oct 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: QUALITY Certificate 02.pdf | 13 Oct 2022 |
| Certificates of CA (Form 3)File: FORM III Jun 22 NFBPL.pdf | 24 Aug 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form V (Mar - 20) - Neelam.pdf | 27 Jun 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form V (Mar - 21) - Neelam.pdf | 27 Jun 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT FORM 1.pdf | 19 Apr 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER FORM 2.pdf | 19 Apr 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: ENGINEER FORM 2A.pdf | 19 Apr 2022 |
| PAN CardFile: COMPANY PAN CARD.pdf | 18 Apr 2022 |
| Declaration about Commencement CertificateFile: Declaration About CC.pdf | 18 Apr 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A 19-20_compressed.pdf | 18 Apr 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A 20-21_compressed.pdf | 18 Apr 2022 |
| Disclosure of sold/ booked inventoryFile: SETARIA - A WING RERA CARPET STATEMENT.pdf | 18 Apr 2022 |
| Disclosure of sold/ booked inventoryFile: SAVERIA - B WING RERA CARPET STATEMENT.pdf | 18 Apr 2022 |
| Certificates of CA (Form 3)File: Form III (Mar 22) - Solstice.pdf | 18 Apr 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form V (Mar 19) - Solstice.pdf | 18 Apr 2022 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: PART OC.pdf | 7 Apr 2022 |
| Certificates of CA (Form 5)File: CAForm 518122018.pdf | 19 Dec 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: Ghatkopar full cc.pdf | 17 Sep 2018 |
| Details of encumbrancesFile: DHFL RERA.pdf | 19 Mar 2018 |
| Copy of the legal title reportFile: Title Certificate editted.pdf | 29 Aug 2017 |
| Declaration in FORM BFile: Form B Solstics Promoter.pdf | 31 Jul 2017 |
| Declaration in FORM BFile: Agreement with co-promoter 1.pdf | 31 Jul 2017 |
| Declaration in FORM BFile: Agreement with co-promoter 2.pdf | 31 Jul 2017 |
| Declaration in FORM BFile: Agreement with co-promoter 3.pdf | 31 Jul 2017 |
| Declaration in FORM BFile: Agreement with co-promoter 4.pdf | 31 Jul 2017 |
| Declaration in FORM BFile: Agreement with co-promoter 5.pdf | 31 Jul 2017 |
| Declaration in FORM BFile: Agreement with co-promoter 6.pdf | 31 Jul 2017 |
| Declaration in FORM BFile: Agreement with co-promoter 7.pdf | 31 Jul 2017 |
Promoter's earlier projects2
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| SPIRO TOWER | MULUND EAST | 17 | Completed | Dec 2014 | Late, Apr 2016 |
| SENROOFS - SANCTURA AND SERENA | SENROOFS MILE OFF GOREGAON MULUND LINK ROAD NAHUR EAST MUMBAI 81 | 344 | Completed | Mar 2014 | Late, Jan 2016 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 103 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep SOLSTICE PHASE- I on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Kamraj Nagar6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 380 registered projects within 2 km.
Mahindra Rainforest Phase 1
Anthurium Developers Limited
Mahindra Rainforest Phase 2
Anthurium Developers Limited
CRYSTAL PRIME MERIDIAN
ARYAMAAN DEVELOPERS PRIVATE LIMITED
AARADHYA ONEPARK
MICL CREATORS LLP
CENTRONA ZEN-A
ELEVATED AVENUE REALTY LLP
CENTRONA ZEN-B
ELEVATED AVENUE REALTY LLP
See every Mumbai Suburban project, with the district possession charts
Builder: NEELAM FINANCE (BOMBAY ) PVT LTD
NEELAM FINANCE (BOMBAY ) PVT LTD has 1 registration on MahaRERA, including SOLSTICE PHASE- I. Its filings disclose 2 earlier MahaRERA projects: declares 0 of 2 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What are my rights if SOLSTICE PHASE- I is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SOLSTICE PHASE- I?
The registered promoter entity is NEELAM FINANCE (BOMBAY ) PVT LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SOLSTICE PHASE- I?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against SOLSTICE PHASE- I?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for SOLSTICE PHASE- I?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SOLSTICE PHASE- I?
The professionals named in the filing: Architect: VASTUVIKALP; Architect: SAURABH SANJEEV MAYEKAR; Architect: ARCHITECT HAFEEZ CONTRACTOR; Architect: S G DALVI & ASSOCIATES; Engineer: GHANSHYAM SUTAR; Engineer: J W CONSULTANTS. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SOLSTICE PHASE- I?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback