Home / Browse projects / Nashik, Maharashtra / SOHAN CITY PHASE 2

Registration lapsed No litigation declared Residential / Group Housing project

SOHAN CITY PHASE 2

By SAGAR SOHANLAL BHANDARI

RG-MH-14313 · RERA P51600031995 · Last updated on MahaRERA portal: 12 Apr 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
99 of 132Construction stages doneacross 12 buildings; furthest along: Excavation, 85%
0Complaints at MahaRERAon this registration
Jump to the 57 documents Report an error

SOHAN CITY PHASE 2 is a Residential / Group Housing project by SAGAR SOHANLAL BHANDARI in Nashik, Maharashtra, registered with MahaRERA as P51600031995 on 3 Dec 2021. Possession was promised by 31 Dec 2025 and is now 10 months past that date.

At a glance

Project

  • NameSOHAN CITY PHASE 2
  • TypeResidential / Group Housing
  • Location
    • OFF S T STAND
    • PIMPALGAON B
    • Pimpalgaon Baswant
    • Niphad
    • Nashik
    • 422209
  • Pincode422209
  • RERA no.P51600031995
  • ReraGenie IDRG-MH-14313

Builder

  • NameSAGAR SOHANLAL BHANDARI
  • Entity typeIndividual
  • Other registrations1 more →
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

10 months past promisethis monthRegisteredDec 2021PromisedDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on3 Dec 2021
  • Promised completion31 Dec 2025
  • Revised completionNone
  • Buildings12 building records
  • Documents filed57 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
QNA20000
MNA20000
XNA20000
NNA20000
UNA20000
PNA20000
SNA20000
TNA20000
0NA20000
RNA20000
VNA20000
WNA20000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building12

As on 12 Apr 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

99 of 132 construction stages are filed complete across 12 buildings. The stage furthest along is Excavation, at 85%.

Q82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
M82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
X82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
N82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
U82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
P82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
S82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
T82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
082%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
R70%
ActivityProgress
Excavation85%
Basement (if any)85%
Podiums (if any)0%
Plinth85%
Stilt Floor0%
Slabs of Super Structure85%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises85%
Sanitary Fittings within the flats / premises85%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks85%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.85%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.85%
V82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
W82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 12 Apr 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes94%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes94%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes100%

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area18,187 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI10816.52
Proposed, not sanctioned10,817 sq m
Buildings approved12
Buildings sanctioned12

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHRIMAN SANKULS SHOP NO 1 TO 4 NEAR S T STAND PIMPALAGAON NASHIK

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRaveena Nikhil Dhadiwal
EngineerMitesh Mutha
Chartered AccountantCA LALIT PAWAR
Chartered AccountantNirav Shah
PartnerRole in project
SAGAR SOHANLAL BHANDARI-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 24 Nov 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 10 Nov 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 10 Nov 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 10 Nov 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed57

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 24-25 Q4.pdf12 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 SD 24-25 Q4.pdf12 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 24-25 Q4.pdf12 Apr 2025
Disclosure of sold/ booked inventoryFile: Inventory 31-03-2025.pdf12 Apr 2025
Disclosure of sold/ booked inventoryFile: Inventory 31-12-2024.pdf6 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 23-24 Q4.pdf5 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 24-25 Q1.pdf5 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 24-25 Q2.pdf5 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 24-25 Q3.pdf5 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 SC 23-24 Q4.pdf5 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 SC 24-25 Q1.pdf5 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 SC 24-25 Q2.pdf5 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 SC 24-25 Q3.pdf5 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 23-24 Q4.pdf5 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 24-25 Q1.pdf5 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 24-25 Q2.pdf5 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 24-25 Q3.pdf5 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A - 2024.pdf5 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 - 2023-24.pdf5 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf7 Aug 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf7 Aug 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A - 2023.pdf7 Aug 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf7 Aug 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 - 2022-23.pdf7 Aug 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf17 May 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf17 May 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf17 May 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 - 2021-22.pdf11 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf18 Oct 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf18 Oct 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf18 Oct 2022
Declaration in FORM BFile: SAGAR S BHANDARI STAMP.pdf26 Nov 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 SOHAN CITY 2 26-11-2021.pdf26 Nov 2021
CERSAI detailsFile: Sagar - Non Encumbramce.pdf26 Nov 2021
OtherFile: Untitled.pdf26 Nov 2021
Copy of the legal title reportFile: LEGAL TITLE REPORT 1_compressed.pdf24 Nov 2021
Copy of the legal title reportFile: LEGAL TITLE REPORT 2_compressed.pdf24 Nov 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 24-11-2021 SAGAR - SOHAN CITY 2.pdf24 Nov 2021
Layout approvalFile: sagar soham city 2 1-3_compressed.pdf10 Nov 2021
Layout approvalFile: sagar soham city 2 2-3.pdf10 Nov 2021
Layout approvalFile: sagar soham city 2 3-3.pdf10 Nov 2021
Building plan approvalFile: sagar soham city 2 1-3_compressed.pdf10 Nov 2021
Building plan approvalFile: sagar soham city 2 2-3.pdf10 Nov 2021
Building plan approvalFile: sagar soham city 2 3-3.pdf10 Nov 2021
PAN CardFile: PAN CARD.pdf10 Nov 2021
Details of encumbrancesFile: Sagar - Non Encumbramce.pdf10 Nov 2021
Copy of Layout Approval (in case of layout)File: sagar soham city 2 1-3_compressed.pdf10 Nov 2021
Copy of Layout Approval (in case of layout)File: sagar soham city 2 2-3.pdf10 Nov 2021
Copy of Layout Approval (in case of layout)File: sagar soham city 2 3-3.pdf10 Nov 2021
Building Plan Approval / NA Order for plotted developmentFile: sagar soham city 2 1-3_compressed.pdf10 Nov 2021
Building Plan Approval / NA Order for plotted developmentFile: sagar soham city 2 2-3.pdf10 Nov 2021
Building Plan Approval / NA Order for plotted developmentFile: sagar soham city 2 3-3.pdf10 Nov 2021
Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT LETTER.pdf10 Nov 2021
Declaration about Commencement CertificateFile: Sagar - Commencemnt Cert.pdf10 Nov 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGEENERS CERTIFICATE SAGAR.pdf10 Nov 2021
Proforma of Allotment letterFile: Sagar - Allotment Letter.pdf10 Nov 2021
Proforma of Allotment letterFile: SALE DEED FORMAT_compressed.pdf10 Nov 2021

How this compares with Nashik

10%of Nashik projects moved their completion datethis one has not
19%of Nashik registrations have lapsed or been cancelledthis one is among them

Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.

Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SOHAN CITY PHASE 2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near PIMPALGAON B4,100+ in Nashik

Builder: SAGAR SOHANLAL BHANDARI

SAGAR SOHANLAL BHANDARI has 2 registrations on MahaRERA, including SOHAN CITY PHASE 2 and Sohan City Phase 2 Lasalgaon. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Nashik district page.

Frequently asked questions

What does it mean that SOHAN CITY PHASE 2 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if SOHAN CITY PHASE 2 is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SOHAN CITY PHASE 2?

The registered promoter entity is SAGAR SOHANLAL BHANDARI, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SOHAN CITY PHASE 2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SOHAN CITY PHASE 2?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SOHAN CITY PHASE 2?

The professionals named in the filing: Architect: Raveena Nikhil Dhadiwal; Engineer: Mitesh Mutha; Chartered Accountant: CA LALIT PAWAR; Chartered Accountant: Nirav Shah. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SOHAN CITY PHASE 2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SOHAN CITY PHASE 2. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SOHAN CITY PHASE 2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.