ReraGenieLog inGet a buyer report

Home / Browse projects / Nashik, Maharashtra / SOHAN CITY PHASE 1

Completed No litigation declared Residential / Group Housing project

SOHAN CITY PHASE 1

By SIDDHARTH SOHANLAL BHANDARI

RG-MH-14312 · RERA P51600032430 · Last updated on MahaRERA portal: 14 Apr 2023

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 2 other registrations.

See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.
Dec 2025Possession promisedregistration recorded completed
126 of 154Construction stages doneacross 14 buildings; furthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 49 documents Report an error

SOHAN CITY PHASE 1 is a Residential / Group Housing project by SIDDHARTH SOHANLAL BHANDARI in Nashik, Maharashtra, registered with MahaRERA as P51600032430 on 4 Jan 2022. The registration is recorded completed; possession was promised by 31 Dec 2025.

At a glance

Project

  • NameSOHAN CITY PHASE 1
  • TypeResidential / Group Housing
  • Location
    • OPP JOPUL ROAD
    • PIMPALGAON
    • Pimpalgaon Baswant
    • Niphad
    • Nashik
    • 422209
  • Pincode422209
  • RERA no.P51600032430
  • ReraGenie IDRG-MH-14312

Builder

  • NameSIDDHARTH SOHANLAL BHANDARI
  • Entity typeIndividual
  • GSTIN27BRRPB7051F1ZQ
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • Other registrations2 more →
  • Completed1 of 3
  • Declared earlier projects1 →

Key dates

this monthRegisteredJan 2022PromisedDec 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on4 Jan 2022
  • Promised completion31 Dec 2025
  • Revised completionNone
  • Buildings14 building records
  • Documents filed49 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BNA20000
LNA20000
HNA20000
MNA20000
NNA20000
DNA20000
INA20000
KNA20000
ANA20000
ENA20000
FNA20000
JNA20000
GNA20000
CNA20000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building14

As on 14 Apr 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

126 of 154 construction stages are filed complete across 14 buildings. The stage furthest along is Podiums (if any), at 0%.

B82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
L82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
H82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
M82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
N82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
D82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
I82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
K82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
A82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
E82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
F82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
J82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
G82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
C82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 14 Apr 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area17,963 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI11248.0
Proposed, not sanctioned11,248 sq m
Buildings approved14
Buildings sanctioned14

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHRIMAN SANKUL SHOP NO 1 TO 4 440/2 NEAR S T STAND MUMBAI AGRA ROAD PIMPALGAON NASHIK

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRaveena Nikhil Dhadiwal
EngineerMitesh Mutha
EngineerMilind Rathi
Chartered AccountantCA LALIT PAWAR
Chartered AccountantNirav Shah
Chartered AccountantSaril Shah
PartnerRole in project
SIDDHARTH SOHANLAL BHANDARI-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 15 Dec 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 23 Nov 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 15 Dec 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 10 Nov 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 11 Apr 2023

Documents filed49

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Status of Formation of Legal Entity (Society/Co Op etc.)File: Declaration of Apartment.pdf14 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf12 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf12 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 - 2022-23.pdf12 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf11 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 - 2021-22.pdf11 Apr 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Completion Certificate 1.pdf11 Apr 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Completion Certificate 2.pdf11 Apr 2023
Architect’s Certificate on Completion of Project (Form 4)File: From 4.pdf11 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf21 Nov 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf21 Nov 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf21 Nov 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf18 Oct 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf18 Oct 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf18 Oct 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf18 Oct 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A.pdf18 Oct 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf18 Oct 2022
CERSAI detailsFile: CERSAI_Search_Report_200226362981_For_Asset_Based_Search_22_12_2021_11_18_25_010.pdf22 Dec 2021
Building plan approvalFile: N A ORDER.pdf15 Dec 2021
Copy of the legal title reportFile: LGL Title Report 1_compressed.pdf15 Dec 2021
Copy of the legal title reportFile: LGL Title Report 2_compressed.pdf15 Dec 2021
Building Plan Approval / NA Order for plotted developmentFile: N A ORDER.pdf15 Dec 2021
Copy of the legal title reportFile: LEGAL TITLE REPORT 1_compressed.pdf7 Dec 2021
Copy of the legal title reportFile: LEGAL TITLE REPORT 2_compressed.pdf7 Dec 2021
CERSAI detailsFile: CERSAI_Search_Report_200225837796_For_Debtor_Based_Search_14_12_2021_11_49_32_170.pdf7 Dec 2021
Layout approvalFile: SOHAN CITY 1 02 Siddharth Bhandari1 555 556 4 Part 2_compressed.pdf23 Nov 2021
Layout approvalFile: SOHAN CITY 1 Siddharth Bhandari1 555 556 3 Part 1 Black_.pdf23 Nov 2021
Copy of Layout Approval (in case of layout)File: SOHAN CITY 1 02 Siddharth Bhandari1 555 556 4 Part 2_compressed.pdf23 Nov 2021
Copy of Layout Approval (in case of layout)File: SOHAN CITY 1 Siddharth Bhandari1 555 556 3 Part 1 Black_.pdf23 Nov 2021
Layout approvalFile: SIDHARTH SOHAM CITY 1 1-2 MAP.pdf10 Nov 2021
Layout approvalFile: SIDHARTH SOHAM CITY 1 2-2 MAP.pdf10 Nov 2021
Building plan approvalFile: SIDHARTH SOHAM CITY 1 1-2 MAP.pdf10 Nov 2021
Building plan approvalFile: SIDHARTH SOHAM CITY 1 2-2 MAP.pdf10 Nov 2021
PAN CardFile: PAN CARD.pdf10 Nov 2021
Details of encumbrancesFile: Siddharth - Non - Encumbramce.pdf10 Nov 2021
Copy of Layout Approval (in case of layout)File: SIDHARTH SOHAM CITY 1 1-2 MAP.pdf10 Nov 2021
Copy of Layout Approval (in case of layout)File: SIDHARTH SOHAM CITY 1 2-2 MAP.pdf10 Nov 2021
Building Plan Approval / NA Order for plotted developmentFile: SIDHARTH SOHAM CITY 1 1-2 MAP.pdf10 Nov 2021
Building Plan Approval / NA Order for plotted developmentFile: SIDHARTH SOHAM CITY 1 2-2 MAP.pdf10 Nov 2021
Commencement Certificates / NA Order for plotted developmentFile: COMMENSMENT CERTIFICATE.pdf10 Nov 2021
Declaration about Commencement CertificateFile: Siddharth Commencemnt Cert.pdf10 Nov 2021
Declaration in FORM BFile: Siddharth Affidavit.pdf10 Nov 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCITECT'S CERTIFICATE.pdf10 Nov 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGEENERS CERTIFICATE SIDDHARTH.pdf10 Nov 2021
Disclosure of sold/ booked inventoryFile: Siddharth Sold Book Inventory.pdf10 Nov 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 SIDHARTH BHANDARI.pdf10 Nov 2021
Proforma of Allotment letterFile: Siddharth Allotment Letter.pdf10 Nov 2021
Proforma of Allotment letterFile: SALE DEED FORMAT_compressed.pdf10 Nov 2021

How this compares with Nashik

10%of Nashik projects moved their completion datethis one has not
19%of Nashik registrations have lapsed or been cancelledthis one is completed

Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.

Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SOHAN CITY PHASE 1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near PIMPALGAON4,100+ in Nashik

Builder: SIDDHARTH SOHANLAL BHANDARI

SIDDHARTH SOHANLAL BHANDARI has 3 registrations on MahaRERA, including SOHAN CITY PHASE 1 and Sohan City Phase 1 Lasalgaon. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Nashik district page.

Frequently asked questions

What are my rights if SOHAN CITY PHASE 1 is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SOHAN CITY PHASE 1?

The registered promoter entity is SIDDHARTH SOHANLAL BHANDARI, an individual as per the filing. Its GSTIN 27BRRPB7051F1ZQ can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SOHAN CITY PHASE 1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SOHAN CITY PHASE 1?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SOHAN CITY PHASE 1?

The professionals named in the filing: Architect: Raveena Nikhil Dhadiwal; Engineer: Mitesh Mutha; Engineer: Milind Rathi; Chartered Accountant: CA LALIT PAWAR; Chartered Accountant: Nirav Shah; Chartered Accountant: Saril Shah. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SOHAN CITY PHASE 1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SOHAN CITY PHASE 1. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SOHAN CITY PHASE 1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.