ReraGenieLog inGet a buyer report

Home / Browse projects / Bengaluru Urban, Karnataka / Sobha Silicon Oasis Phase 1 Wing 1, 2, 3, 4, 5 & 6

Registration approved Residential/Group Housing project

Sobha Silicon Oasis Phase 1 Wing 1, 2, 3, 4, 5 & 6

By SOBHA LIMITED

RG-KA-68310 · RERA PRM/KA/RERA/1251/310/PR/170824/000032

Source: official RERA Karnataka filing

Red flags

  • 1 complaint at RERA Karnataka

Clear

  • Completion date never moved
  • Separate project account declared
Apr 2019Possession promisedno revision filed
1Complaints at RERA Karnatakaon this registration
Jump to the 39 documents Report an error

Sobha Silicon Oasis Phase 1 Wing 1, 2, 3, 4, 5 & 6 is a Residential/Group Housing project by SOBHA LIMITED in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/170824/000032 on 24 Aug 2017. Possession is promised by 1 Apr 2019. 1 complaint is on record with the regulator.

At a glance

Project

  • NameSobha Silicon Oasis Phase 1 Wing 1, 2, 3, 4, 5 & 6
  • TypeResidential/Group Housing
  • Location
    • Bengaluru South
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/310/PR/170824/000032
  • ReraGenie IDRG-KA-68310

Builder

  • NameSOBHA LIMITED
  • Entity typeCompany
  • CINL45201KA1995PLC018475
  • Authorized SignatoryLt. Gen Mathew Mammen (Retd), PVSM, AVSM,VSM (Bar)
  • Other registrations119 more →
  • No longer live8 withdrawn or revoked
  • Declared earlier projects196 →

Key dates

this monthRegisteredAug 2017PromisedApr 2019

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on24 Aug 2017
  • Promised completion1 Apr 2019
  • Revised completionNone
  • Buildings6 building records
  • Documents filed39 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Wing 1---83083
Wing 2---83083
Wing 3---82082
Wing 4---81081
Wing 5---80080
Wing 6---82082

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network-
Weather Proof work(tile,concrete)-
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsYes-
Sewage and Drainage SystemYes-
Parks & Tree plantingYes-
Street LightingYes-
Provision for community buildings and for treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes-
Water conservationNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes-
Education/Health/Other public amenitiesNoNot applicable
Electricity supply transformer and substationNoNot applicable
Emergency Evacuation servicesNoNot applicable
Storm water drainsYes-
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseYes-
Community HallNoNot applicable
Outdoor Sports facilityYes-
Indoor Sports facilityYes-
Swimming PoolYes-
GymYes-
ParksYes-
Power BackupYes-
GasNoNot applicable
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesNoNot applicable
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallNoNot applicable
Open parking areas and common storage spacesYes-
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area24,358 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 311.35 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectGEETHA K. NAIR
EngineerAnilkumar S. Hokrani

Complaints filed with RERA Karnataka1

Case no.ComplainantRespondentFiled
CMP/210406/0007866-SOBHA LIMITED06/04/2021

Documents filed39

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/170824/000032 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CertificateFile: Sobha reg certificate.jpg-
Commencement Certificate - SO P1-
BBMP Plan Sanction Drawings - SO P1-
Approved Layout Plan - Non Applicability-
Proforma for Sale Deed - SO P1-
Agreement to Sell - SO P1-
Land Documents & Location - SO P1 compressed-
Approved Section of Building, Infra Plan of Plotting - SO P1-
Area Development Plan - SO P1-
Allotment letter-
Brochure-
NOC's - SO P1 Compressed-
Specifications - SO P1-
Encumbrance Certificate - SO P1-
Balance Sheet 2015 - 2016File: Balance Sheet - Mar 2017.pdf-
Balance Sheet 2014 - 2015File: Balance Sheet - Mar 2016.pdf-
Balance Sheet 2013 - 2014File: Balance Sheet - Mar 2015.pdf-
Audited Profit and Loss Statement 2015 - 2016File: Profit Loss Statement - Mar 2017.pdf-
Audited Profit and Loss Statement 2014 - 2015File: Profit Loss Statement - Mar 2016.pdf-
Audited Profit and Loss Statement 2013 - 2014File: Profit Loss Statement - Mar 2015.pdf-
Director's Report 2015 - 2016File: DR_2016-17.pdf-
Director's Report 2014 - 2015File: DR_2015-16.pdf-
Director's Report 2013 - 2014File: DR_2014-15.pdf-
Cash Flow Statement 2015 - 2016File: Cash Flow - Mar 2017.pdf-
Cash Flow Statement 2014 - 2015File: Cash Flow - Mar 2016.pdf-
Auditor's Report 2015 - 2016File: Auditors Report - Mar 2017.pdf-
Auditor's Report 2014 - 2015File: Auditors Report - Mar 2016.pdf-
Auditor's Report 2013 - 2014File: Auditors Report - Mar 2015.pdf-
Income Tax Return Acknowledgement 2015 - 2016File: ITR 2016-17.pdf-
Income Tax Return Acknowledgement 2014 - 2015File: ITR 2015-16.pdf-
Income Tax Return Acknowledgement 2013 - 2014File: ITR 2014-15.pdf-
Form B Compressed-
Prospectus/BrochureFile: Brochure.pdf-
Advertisement Copy 1File: NA - Advertisements.pdf-
Tower Excel SheetFile: PRM_KA_RERA_1251_310_PR_170824_000032.xlsx-
Occupancy CertificateFile: BBMP OC_Blk-1 (Wing-1 to 6), Blk-2 & Blk-3_Silicon oasis.pdf-
Completion certificateFile: BBMP OC_Blk-1 (Wing-1 to 6), Blk-2 & Blk-3_Silicon oasis.pdf-
Registered Agreement of SaleFile: SO B2-1172 ATS 1.pdf-
Registered conveyance deed for an individual unitFile: SO B2-1172 SD 1.pdf-

Promoter's earlier projects40

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

38 not delivered by the promised date2 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
Sobha Winchester-OngoingJul 2017Not delivered
Sobha West Hill - Part C-OngoingJul 2017Not delivered
Sobha Valley View-OngoingJul 2017Not delivered
Sobha Silicon Oasis Wing 9-OngoingJul 2017Not delivered
Sobha Silicon Oasis Wing 8-OngoingJul 2017Not delivered
Sobha Silicon Oasis Wing 10 & 11-OngoingJul 2017Not delivered
Sobha Silicon Oasis Phase 1 Wing 7-OngoingJul 2017Not delivered
Sobha Silicon Oasis Block 2 and 3 (Row house No. 9, 10)-OngoingJul 2017Not delivered
Sobha Silicon Oasis Block 2 and 3 (Row house No. 1 to 8 & 11 to 17)-OngoingJul 2017Not delivered
Sobha Serene-CompletedJul 2017No date filed
Sobha Palm Court-OngoingJul 2017Not delivered
Sobha Orion-OngoingJul 2017Not delivered
Sobha Morzaria Grandeur-CompletedJul 2017No date filed
Sobha Indraprastha (Residential)-OngoingJul 2017Not delivered
Sobha Elan-OngoingJul 2017Not delivered
Sobha Dream Acres-Tropical Greens Wing 46-OngoingJul 2017Not delivered
Sobha Dream Acres-Tropical Greens Wing 45-OngoingJul 2017Not delivered
Sobha Dream Acres-Tropical Greens Wing 43 and 44-OngoingJul 2017Not delivered
Sobha Dream Acres-Tropical Greens Wing 42-OngoingJul 2017Not delivered
Sobha Dream Acres-Tropical Greens Wing 41-OngoingJul 2017Not delivered
Sobha Dream Acres-Rain Forest-Wing 5 and 6-OngoingJul 2017Not delivered
Sobha Dream Acres-Rain Forest-Wing 3 and 4-OngoingJul 2017Not delivered
Sobha Dream Acres-Rain Forest-Wing 16-OngoingJul 2017Not delivered
Sobha Dream Acres-Rain Forest-Wing 12-OngoingJul 2017Not delivered
Sobha Dream Acres-Rain Forest-Wing 11-OngoingJul 2017Not delivered
Sobha Dream Acres-Rain Forest-Wing 1,2 and 17-OngoingJul 2017Not delivered
Sobha Dream Acres-Palm Springs Wing 53-OngoingJul 2017Not delivered
Sobha Dream Acres-Palm Springs Wing 52-OngoingJul 2017Not delivered
Sobha Dream Acres-Palm Springs Wing 48 and 49-OngoingJul 2017Not delivered
Sobha Dream Acres-Palm Springs Wing 47-OngoingJul 2017Not delivered
Sobha Clovelly-OngoingJul 2017Not delivered
Sobha City Paradiso - Wing 4-OngoingJul 2017Not delivered
Sobha City - Tower C2-OngoingJul 2017Not delivered
Sobha City - Tower C1-OngoingJul 2017Not delivered
Sobha City - Tower A2, B2-OngoingJul 2017Not delivered
Sobha City - Tower A1, B1-OngoingJul 2017Not delivered
Sobha Avenue-OngoingJul 2017Not delivered
Sobha Arena - The Plaza-OngoingJul 2017Not delivered
Sobha Arena - The Park-OngoingJul 2017Not delivered
Sobha 25 Richmond-OngoingJul 2017Not delivered

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Sobha Silicon Oasis Phase 1 Wing 1, 2, 3, 4, on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: SOBHA LIMITED

SOBHA LIMITED has 120 registrations on RERA Karnataka, including Sobha Oakshire Phase 1 Wing 1,2,7 and 8 and Sobha Oakshire Phase 2 Wing 3,4,9 and 10. Its filings declare 196 earlier projects, 85 of them declared completed. Litigation is declared on 33 of its registrations. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Sobha Silicon Oasis Phase 1 Wing 1, 2, 3, 4, 5 & 6 is delayed beyond 1 Apr 2019?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Sobha Silicon Oasis Phase 1 Wing 1, 2, 3, 4, 5 & 6?

The registered promoter entity is SOBHA LIMITED, a company as per the filing. Its CIN L45201KA1995PLC018475 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Sobha Silicon Oasis Phase 1 Wing 1, 2, 3, 4, 5 & 6?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Sobha Silicon Oasis Phase 1 Wing 1, 2, 3, 4, 5 & 6?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at Sobha Silicon Oasis Phase 1 Wing 1, 2, 3, 4, 5 & 6?

The professionals named in the filing: Architect: GEETHA K. NAIR; Engineer: Anilkumar S. Hokrani. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Sobha Silicon Oasis Phase 1 Wing 1, 2, 3, 4, 5 & 6?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Sobha Silicon Oasis Phase 1 Wing 1, 2, 3, 4, 5 & 6. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Sobha Silicon Oasis Phase 1 Wing 1, 2, 3, 4, to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.