Sobha Insignia

By SOBHA LIMITED

RG-KA-81406 · RERA PRM/KA/RERA/1251/446/PR/030922/005212 · Last updated on RERA Karnataka portal: 10 Apr 2026

Source: official RERA Karnataka filing

Red flags

  • Litigation declared, 1 case
  • 1 complaint at RERA Karnataka

Clear

  • Completion date never moved
  • Separate project account declared
Mar 2026Possession promisedno revision filed
16 of 17Construction stages donefurthest along: Internal and External work including..., 57%
19 of 33Units unsoldnot recorded sold or booked
1Complaints at RERA Karnatakaon this registration
Jump to the 105 documents Report an error

Sobha Insignia is a Residential/Group Housing project by SOBHA LIMITED in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/030922/005212 on 3 Sep 2022. Possession is promised by 31 Mar 2026. 14 of the 33 units on this registration are recorded sold or booked, and 16 of 17 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameSobha Insignia
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
    • 560037
  • Pincode560037
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/446/PR/030922/005212
  • ReraGenie IDRG-KA-81406

Builder

  • NameSOBHA LIMITED
  • Entity typeCompany
  • CINL45201KA1995PLC018475
  • GSTIN29AABCS7723E1ZB
  • Authorized SignatoryMr. Suresh Ganiga
  • Managing DirectorMr Jagadish Nangineni
  • DirectorsRavi P N C Menon, Mr Jagadish Nangineni
  • Project HeadMr JAYAKUMAR G
  • Other registrations119 more →
  • No longer live8 withdrawn or revoked
  • Declared earlier projects196 →

Key dates

this monthRegisteredSep 2022PromisedMar 2026

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on3 Sep 2022
  • Promised completion31 Mar 2026
  • Revised completionNone
  • Buildings1 building record
  • Documents filed105 files

Current status

42%14 of 33 units booked
102.5%Of the estimated cost spent so far

Figures as on 10 Apr 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Wing 1---33033

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 10 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

16 of 17 construction stages are filed complete. The stage furthest along is Internal and External work including landscapes as per..., at 57%.

Building: 97% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)100%
RCC or MS Framed structure100%
Masonry Construction100%
Plastering inside , outside & Ceiling100%
Joinery: Doors, Windows, Ventilators etc100%
Basic work of Water supply, Sanitary and Electrification100%
Dadoing, Skirting, Flooring, Tiles work (All types)100%
Railing and Grill fixing100%
Electrification, Water supply and Sanitary Finishing100%
Painting100%
Fire prevention and fire fighting fitting and fixture with network100%
Weather Proof work(tile,concrete)100%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation workNot applicable
Internal and External work including landscapes as per sanctioned drawings57%

Progress on shared amenities40

As on 10 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes100%
Sewage and Drainage SystemYes100%
Water conservation/rain water harvesting/recharge of ground waterNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes100%
Solid waste management and disposalYes40%
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsYes90%
Electricity supply transformer and substationYes0%
Storm water drainsYes0%
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes0%
Parks & Tree plantingYes0%
Street LightingYes0%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseYes95%
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolYes0%
GymNoNot applicable
ParksNoNot applicable
Power BackupYes0%
Piped GasNoNot applicable
Water and SanitationYes0%
Air ConditioningNoNot applicable
StaircasesYes100%
LiftsYes100%
Corridor/LobbiesYes100%
Fire escapesYes100%
Common entrance and exit for the building/common portico/foyer/verandahYes100%
BasementYes60%
TerraceYes98%
Outer WallYes100%
Open parking areasYes0%
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,946 sq m
Named landowners1
LandownerVillageDistrict
M/s. Sobha Limited--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 61.37 cr
Cost incurredRs 62.88 cr
Spent of the estimate102.45%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 47.10 crRs 48.61 cr
Payment of taxesRs 5.97 crRs 5.97 cr
Principal sum and interest payable to financial institutions-Scheduled BanksRs 5.00 crRs 5.00 cr
On-site expenditure-Site OverheadRs 3.30 crRs 3.30 cr

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectGeetha K Nair
EngineerArjun M V
Chartered AccountantBalaji D

Litigation declared1

CaseCourtStatus
352/2017/2017O S No 352/2017 filed by Smt Bharathi & Others against Sri Ramaiah & Others before the City Civil Court Bengaluru for partition of suit schedule properties and other reliefs-

Complaints filed with RERA Karnataka1

Case no.ComplainantRespondentFiled
01192/2023-SOBHA LIMITED26/07/2023

Documents filed105

As listed on the registration, under the names the promoter filed them with; the newest 80 of 105 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/030922/005212 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Insignia.pdf10 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Insignia.pdf10 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Insignia.pdf10 Apr 2026
Q4 2025-26 Water supply and sewage board10 Apr 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)10 Apr 2026
Q4 2025-26 KPTCL- BESCOM10 Apr 2026
Q4 2025-26 Fire and Safety10 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Insignia C.pdf12 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Insignia.pdf12 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Insignia.pdf12 Jan 2026
Q3 2025-26 KPTCL- BESCOM12 Jan 2026
Affidavit for pendency of BWSSB NOC and BWSSB application acknowledgementFile: Affidavit for pendency of BWSSB NOC and application ack.pdf30 Aug 2022
Furnished Khata Certificate obtained in the name of Sobha LimitedFile: MR.pdf18 Aug 2022
No litigation with land owners signatureFile: 2 Affidavit for No Litigation format for Insignia.pdf18 Aug 2022
Legal OpinionFile: Legal Opinion Bhoganahalli.pdf18 Aug 2022
Single plot layoutFile: Single plot layout remarks and Approved drawings.pdf18 Aug 2022
Single plot layout orderFile: Building lincense and remarks.pdf18 Aug 2022
Commencement certificateFile: CC remarks and Building lincense.pdf18 Aug 2022
Village map showing proposed siteFile: BHOGANAHALLI SITE LOCATION Village map 17082022.pdf18 Aug 2022
Updated the total built up area of 11256.18 sqm as per the approved drawing in page 4File: TBUA updation in page 4 screenshot.pdf18 Aug 2022
Project schedule dates updated till the proposed completion date in page 6File: Project schedule of Insignia.pdf18 Aug 2022
Brief copy of estimated cost of construction certified by the EngineerFile: Form 3 Engineer certificate.pdf18 Aug 2022
Mentioned the project name and project address in section 3(1) notarized affidavitFile: Notarized Affidavit for 3(1) Voliation Insignia.pdf18 Aug 2022
Renewed BWSSB NOC along with the copy of fee paid receipt towards NOCFile: BWSSB NOC ack with remarks.pdf18 Aug 2022
Proforma of Agreement for sale comprising with project bank detailsFile: Proforma of ATS Sobha Insignia.pdf18 Aug 2022
BSNL NOC and MSL KSRSACFile: BSNL NOC remarks and MSL KSRSAC.pdf18 Aug 2022
RTC, survey 128/7-
Mutation, survey 128/7-
Encumbrance Certificate, survey 128/7-
Conversion/Alienation Order, survey 128/7-
Sale/Title/Gift Deed, survey 128/7-
Khatha, survey 128/7-
Registration CertificateFile: Registration Certificate of SL.pdf-
Organization StructureFile: Organisation Structure.pdf-
Certificate issued by CA Form 1File: Form 1 Sobha Insignia CA c.pdf-
Certificate issued by Architect Form 2File: Form 2 Architect Certificate.pdf-
Certificate issued by Engineer Form 3File: Form 3 Engineer certificate.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: Affidavit for No Litigation format for Insignia R1.pdf-
Certificate from Chartered AccountFile: Form 1 Sobha Insignia CA c.pdf-
Balance Sheet 2020 - 2021File: Balance sheet Mar 2022.pdf-
Balance Sheet 2019 - 2020File: Balance sheet Mar 2021.pdf-
Balance Sheet 2018 - 2019File: Balance Sheet Mar 2020.pdf-
Audited Profit and Loss Statement 2020 - 2021File: Profit Loss Statement Mar 2022.pdf-
Audited Profit and Loss Statement 2019 - 2020File: Profit Loss Statement Mar 2021.pdf-
Audited Profit and Loss Statement 2018 - 2019File: Profit Loss Statement Mar 2020.pdf-
Director's Report 2020 - 2021File: DR 2021 22.pdf-
Director's Report 2019 - 2020File: DR 2020 21.pdf-
Director's Report 2018 - 2019File: DR 2019 20.pdf-
Cash Flow Statement 2020 - 2021File: Cash Flow Mar 2022.pdf-
Cash Flow Statement 2019 - 2020File: Cash Flow Mar 2021.pdf-
Auditor's Report 2020 - 2021File: Auditors Report Mar 2022.pdf-
Auditor's Report 2019 - 2020File: Auditors Report Mar 2021.pdf-
Auditor's Report 2018 - 2019File: Auditors Report Mar 2020.pdf-
Income Tax Return Acknowledgement 2020 - 2021File: ITR AY 2021 22.pdf-
Income Tax Return Acknowledgement 2019 - 2020File: ITR AY 2020 21.pdf-
Income Tax Return Acknowledgement 2018 - 2019File: ITR AY 2019 20.pdf-
BUILDING LICENCE Insignia-
BESCOM NOC 21052020-
BWSSB NOC-
Approved drawings Insignia-
Approved drawings Insignia-
Approved drawings Insignia-
Approved drawings and specification-
Approved drawings Insignia-
Insignia Specifications-
Approved drawings Insignia-
NA Area Development Plan Of Project Area-
SSC Insignia 21062022-
NA Not a JDA-
Change of land use No 96 2020 21 1957 of 2021 2022 c-
District Magistrate-
Official Memorandum No 78 of 2007 08-
Sale deed docs combined-
Proforma of ATS Sobha Insignia Highlighted Final-
Intimation Letter-
Insigni RERA BOOKLET final Aug 6 2022-
Form B Sobha Insignia c-

Promoter's earlier projects40

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

28 not delivered by the promised date12 under way, not due yet41 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
Sobha Manhattan Towers-Town Park Phase 2 W 1 & 2 LitigationPhase 1 at Sy.No.48/1A and 48/2, in the composite project Sobha Manhattan Towers - Town Park situated at Sy.Nos.48/1A, 48/2, 50/2 and 50/3, presently bearing Khata No.1877/48/1A-1881/50/2-1886/48/2-1913/50/3, situated at Yadavanahalli Village, Attibele Hobli, Anekal TalukOngoingSep 2028Not due yet
Sobha Brooklyn Towers - Town Park Phase 5, W3 LitigationSy nos - 51/1(P), 51/2(P), 52/1(P), 52/2(P)&53 at Yadavanahalli village, Attibele hobli, Anekal taluk, Bangalore, KarnatakaOngoingJun 2028Not due yet
Sobha Windsor Phase 4 Wing 9, 10 and 11 LitigationSy No. 107(P), 115/2, 115/3, 115/4, 115/5, 116/3 situated at Nagondanahalli village and Sy No. 30/1, 30/6, Situated at Hagadur Village, K.R.Puram HobliOngoingMar 2028Not due yet
Sobha Victoria park phase 2 LitigationPROPOSED RESIDENTIAL DEVELOPMENT PROJECT AT SY.NO.47/1B,47/2B, KYALASANAHALLI VILLAGE , WARD NO.25, MAHADEVAPURA ZONE, K.R. PURAM HOBLI, BANGALOREOngoingDec 2027Not due yet
Sobha Victoria park phase 1 LitigationPROPOSED RESIDENTIAL DEVELOPMENT PROJECT AT SY.NO.47/1B,47/2B, KYALASANAHALLI VILLAGE , WARD NO.25, MAHADEVAPURA ZONE, K.R. PURAM HOBLI, BANGALOREOngoingDec 2027Not due yet
Sobha Sentosa Phase 4 Wing 1 and 2 LitigationPROPOSED RESIDENTIAL DEVELOPMENT PLAN AT SY NOS. 49/4 , 49/7, 50/2 (P) , 50/3 (P) , 50/4 (P) , 51/1 (P) , 51/2 B1(P) & 51/2B2 (P) AT BALAGERE, VARTHUR HOBLI, BANGALORE EAST, KARNATAKAOngoingDec 2027Not due yet
Sobha Brooklyn Towers - Town Park Phase 2, W2 LitigationSy nos - 51/1(P), 51/2(P), 52/1(P), 52/2(P)&53 at Yadavanahalli village, Attibele hobli, Anekal taluk, Bangalore, KarnatakaOngoingDec 2027Not due yet
Sobha Windsor Phase 3 Wing 6, 7 and 8 LitigationSy No. 107(P), 115/2, 115/3, 115/4, 115/5, 116/3 situated at Nagondanahalli village and Sy No. 30/1, 30/6, Situated at Hagadur Village, K.R.Puram HobliOngoingSep 2027Not due yet
Sobha City AthenaProperty No 2091/40/7/1, 9/1, 9/2, 62/2, 62/3/1, Chokkanahalli Village, Ward No. 5, Jakkuru, Yelahanka Zone, BengaluruOngoingSep 2027Not due yet
Sobha Sentosa Phase 3 Wing 3 and 4 LitigationPROPOSED RESIDENTIAL DEVELOPMENT PLAN AT SY NOS. 49/4 , 49/7, 50/2 (P) , 50/3 (P) , 50/4 (P) , 51/1 (P) , 51/2 B1(P) & 51/2B2 (P) AT BALAGERE, VARTHUR HOBLI, BANGALORE EAST, KARNATAKAOngoingJun 2027Not due yet
Sobha Sentosa Phase 2 Wing 5 and 6 LitigationPROPOSED RESIDENTIAL DEVELOPMENT PLAN AT SY NOS. 49/4 , 49/7, 50/2 (P) , 50/3 (P) , 50/4 (P) , 51/1 (P) , 51/2 B1(P) & 51/2B2 (P) AT BALAGERE, VARTHUR HOBLI, BANGALORE EAST, KARNATAKAOngoingDec 2026Not due yet
Sobha Manhattan Towers-Town Park Phase 1 W 4 & 5 LitigationPhase 1 at Sy.No.48/1A and 48/2, in the composite project Sobha Manhattan Towers - Town Park situated at Sy.Nos.48/1A, 48/2, 50/2 and 50/3, presently bearing Khata No.1877/48/1A-1881/50/2-1886/48/2-1913/50/3, situated at Yadavanahalli Village, Attibele Hobli, Anekal TalukOngoingDec 2026Not due yet
Sobha Dream Acres - Oasis Phase 27 Wing 55, 56, 57 and 58 LitigationBalagere, BangaloreOngoingSep 2026Not delivered
Sobha Sentosa Phase 1 Wing 7 LitigationPROPOSED RESIDENTIAL DEVELOPMENT PLAN AT SY NOS. 49/4 , 49/7, 50/2 (P) , 50/3 (P) , 50/4 (P) , 51/1 (P) , 51/2 B1(P) & 51/2B2 (P) AT BALAGERE, VARTHUR HOBLI, BANGALORE EAST, KARNATAKAOngoingJun 2026Not delivered
Sobha Royal Pavilion Phase 7 - Wing 12, 13 and 14 LitigationSy No. 54/3, 55/1, 55/2, 58/1, 58/2, 58/3, 59/2, 59/3, 59/4, 59/5, 60/2, 61, 63/1 Hadosiddapura Village, and Sy. No 31/1 Chikkannelli VillageOngoingJun 2026Not delivered
Sobha Royal Pavilion Phase 6 - Wing 10 and 11 LitigationSy No. 54/3, 55/1, 55/2, 58/1, 58/2, 58/3, 59/2, 59/3, 59/4, 59/5, 60/2, 61, 63/1 Hadosiddapura Village, and Sy. No 31/1 Chikkannelli VillageOngoingJun 2026Not delivered
Sobha Royal Pavilion Phase 5 - Wing 8 and 9 LitigationSy No. 54/3, 55/1, 55/2, 58/1, 58/2, 58/3, 59/2, 59/3, 59/4, 59/5, 60/2, 61, 63/1 Hadosiddapura Village, and Sy. No 31/1 Chikkannelli VillageOngoingJun 2026Not delivered
Sobha Royal Pavilion Phase 8 - Wing 15 LitigationSy No. 54/3, 55/1, 55/2, 58/1, 58/2, 58/3, 59/2, 59/3, 59/4, 59/5, 60/2, 61, 63/1 Hadosiddapura Village, and Sy. No 31/1 Chikkannelli VillageOngoingApr 2026Not delivered
Sobha Windsor Phase 2 Wing 3, 4 and 5 LitigationSy No. 107(P), 115/2, 115/3, 115/4, 115/5, 116/3 situated at Nagondanahalli village and Sy No. 30/1, 30/6, Situated at Hagadur Village, K.R.Puram HobliOngoingNov 2025Not delivered
Sobha Windsor Phase 1 Wing 1 and 2 LitigationSy No. 107(P), 115/2, 115/3, 115/4, 115/5, 116/3 situated at Nagondanahalli village and Sy No. 30/1, 30/6, Situated at Hagadur Village, K.R.Puram HobliOngoingNov 2025Not delivered
Sobha RajvilasSy. No 19/3, Minerva Mill Quarters, Gopalapura, Mysore Deviation roadOngoingMar 2025Not delivered
Sobha Dream Acres - Tropical Greens Phase 24 Wing 29 and 30Balagere, BangaloreOngoingMar 2025Not delivered
Sobha Lake Gardens Phase 1Bharathi Nagar, Krishnarajapura, Seegehalli Village, K.R. Puram HobliOngoingNov 2024Not delivered
Sobha Dream Gardens Phase 2 - Wing 5, 6 and 7Survey No. 50, 51 & 54, Belahalli Village, Yelahanka HobliOngoingNov 2024Not delivered
Sobha Dream Gardens Phase 1 - Wing 8 and 9 LitigationSurvey No. 50, 51 & 54, Belahalli Village, Yelahanka HobliOngoingNov 2024Not delivered
Sobha Dream Acres - Tropical Greens Phase 26 Wing 35, 36, 37 and 38 LitigationBalagere, BangaloreOngoingSep 2024Not delivered
Sobha Dream Acres - Tropical Greens Phase 23 Wing 25, 26, 27 and 28Balagere, BangaloreOngoingSep 2024Not delivered
Sobha Royal Pavilion Phase 4 - Wing 1, 2 and 3 LitigationSy No. 54/3, 55/1, 55/2, 58/1, 58/2, 58/3, 59/2, 59/3, 59/4, 59/5, 60/2, 61, 63/1 Hadosiddapura Village, and Sy. No 31/1 Chikkannelli VillageOngoingJun 2024Not delivered
Sobha Royal Pavilion Phase 3 - Wing 16 LitigationSy No. 54/3, 55/1, 55/2, 58/1, 58/2, 58/3, 59/2, 59/3, 59/4, 59/5, 60/2, 61, 63/1 Hadosiddapura Village, and Sy. No 31/1 Chikkannelli VillageOngoingJun 2024Not delivered
Sobha Royal Pavilion Phase 2 - Wing 4 and 5Sy No. 54/3, 55/1, 55/2, 58/1, 58/2, 58/3, 59/2, 59/3, 59/4, 59/5, 60/2, 61, 63/1 Hadosiddapura Village, and Sy. No 31/1 Chikkannelli VillageOngoingJun 2024Not delivered
Sobha Royal Pavilion Phase 1 - Wing 6 and 7Sy No. 54/3, 55/1, 55/2, 58/1, 58/2, 58/3, 59/2, 59/3, 59/4, 59/5, 60/2, 61, 63/1 Hadosiddapura Village, and Sy. No 31/1 Chikkannelli VillageOngoingJun 2024Not delivered
Sobha Forest Edge02/20/1/21/2 Hosahalli, Kengeri Sub Division, Ward No.198, BengaluruOngoingJun 2023Not delivered
Sobha HRC Pristine Phase 4 Block 4 and 5 LitigationSurvey No. 87/2, 87/3, 80 and 111, Jakkur Village, Yelahanka Hobli, BengaluruOngoingApr 2023Not delivered
Sobha HRC Pristine Phase 3 Block 3 LitigationSurvey No. 87/2, 87/3, 80 and 111, Jakkur Village, Yelahanka Hobli, BengaluruOngoingApr 2023Not delivered
Sobha HRC Pristine Phase 2 Block 2 LitigationSurvey No. 87/2, 87/3, 80 and 111, Jakkur Village, Yelahanka Hobli, BengaluruOngoingApr 2023Not delivered
Sobha HRC Pristine Phase 1 Block 1 LitigationSurvey No. 87/2, 87/3, 80 and 111, Jakkur Village, Yelahanka Hobli, BengaluruOngoingApr 2023Not delivered
Sobha Dream Acres - Palm Springs Phase 16 Wing 50 LitigationBalagere, BangaloreOngoingMar 2023Not delivered
Sobha Arena - Pebble Court (Block 1) LitigationKanakapura Road, BangaloreOngoingJan 2023Not delivered
Sobha Palm Court LitigationYelahanka, BangaloreOngoingFeb 2022Not delivered
Sobha Morzaria Grandeur 2 (W1)Dairy circle, BangaloreOngoingFeb 2022Not delivered

How this compares with Bengaluru Urban

42%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Sobha Insignia on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmSobha InsigniaOther 20Dot size: filed unitsN

Filed coordinates, straight-line distance. 20 registered projects within 2 km.

Builder: SOBHA LIMITED

SOBHA LIMITED has 120 registrations on RERA Karnataka, including Sobha Oakshire Phase 1 Wing 1,2,7 and 8 and Sobha Oakshire Phase 2 Wing 3,4,9 and 10. Its filings declare 196 earlier projects, 85 of them declared completed. Litigation is declared on 33 of its registrations. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Sobha Insignia is delayed beyond 31 Mar 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Sobha Insignia?

The registered promoter entity is SOBHA LIMITED, a company as per the filing. Its CIN L45201KA1995PLC018475 and GSTIN 29AABCS7723E1ZB can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Sobha Insignia?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Sobha Insignia?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at Sobha Insignia?

The professionals named in the filing: Architect: Geetha K Nair; Engineer: Arjun M V; Chartered Accountant: Balaji D. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Sobha Insignia?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Sobha Insignia. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Sobha Insignia to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.