Home / Browse projects / Bengaluru Urban, Karnataka / Century Mirai Ph1
Century Mirai Ph1
By Century Silicon City Private Limited
RG-KA-97491 · RERA PRM/KA/RERA/1251/446/PR/181025/008182 · Last updated on RERA Karnataka portal: 14 Oct 2026
Source: official RERA Karnataka filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
Century Mirai Ph1 is a Residential/Group Housing project by Century Silicon City Private Limited in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/181025/008182 on 18 Oct 2025. Possession is promised by 30 Oct 2030. 215 of the 475 units on this registration are recorded sold or booked, and 2 of 18 construction stages are filed complete.
At a glance
Project
- NameCentury Mirai Ph1
- TypeResidential/Group Housing
- Location
- Bengaluru East
- Bengaluru Urban
- 560037
- Pincode560037
- RERA no.PRM/KA/RERA/1251/446/PR/181025/008182
- ReraGenie IDRG-KA-97491
Builder
- NameCentury Silicon City Private Limited
- Entity typeCompany
- CINU68100KA2023PTC173682
- GSTIN29AALCC0361L1ZE
- Authorized SignatoryMahesh Prabhu
- DirectorsP Ravindra Pai, P Ravindra Pai, P Ashwin Pai
- Project HeadNeelkanth Patil
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on18 Oct 2025
- Promised completion30 Oct 2030
- Revised completionNone
- Buildings5 building records
- Documents filed165 files
Current status
Figures as on 14 Oct 2026, this project's latest RERA Karnataka filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Tower 01 | - | - | - | 89 | 0 | 89 |
| Tower 02 | - | - | - | 102 | 0 | 102 |
| Tower 03 | - | - | - | 102 | 0 | 102 |
| Tower 04 | - | - | - | 91 | 0 | 91 |
| 5 | - | - | - | 91 | 0 | 91 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 14 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
2 of 18 construction stages are filed complete. The stage furthest along is Upto Plinth Level, at 23%.
Building: 12% average across the applicable activities
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | 100% |
| Foundation footing work | 100% |
| Upto Plinth Level | 23% |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | 0% |
| Retaining wall (All types) | 0% |
| RCC or MS Framed structure | 0% |
| Masonry Construction | 0% |
| Plastering inside , outside & Ceiling | 0% |
| Joinery: Doors, Windows, Ventilators etc | 0% |
| Basic work of Water supply, Sanitary and Electrification | 0% |
| Dadoing, Skirting, Flooring, Tiles work (All types) | 0% |
| Railing and Grill fixing | 0% |
| Electrification, Water supply and Sanitary Finishing | 0% |
| Painting | 0% |
| Fire prevention and fire fighting fitting and fixture with network | 0% |
| Weather Proof work(tile,concrete) | 0% |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Elevation work | 0% |
| Internal and External work including landscapes as per sanctioned drawings | 0% |
Progress on shared amenities40
As on 14 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | 0% |
| Sewage and Drainage System | Yes | 0% |
| Water conservation/rain water harvesting/recharge of ground water | Yes | 0% |
| Energy management | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Solid waste management and disposal | Yes | 0% |
| Emergency Evacuation services | Yes | 0% |
| Internal Roads & Footpaths | Yes | 0% |
| Electricity supply transformer and substation | Yes | 0% |
| Storm water drains | Yes | 0% |
| Use of renewable energy | Yes | 0% |
| Sewage Treatment Plant (STP) | Yes | 0% |
| Parks & Tree planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Electricity | Yes | 0% |
| Smart Home Automation | Yes | 0% |
| CCTV Surveillance | Yes | 0% |
| Club House | Yes | 0% |
| Community Hall | Yes | 0% |
| Outdoor Sports facility | Yes | 0% |
| Indoor Sports facility | Yes | 0% |
| Swimming Pool | Yes | 0% |
| Gym | Yes | 0% |
| Parks | Yes | 0% |
| Power Backup | Yes | 0% |
| Piped Gas | No | Not applicable |
| Water and Sanitation | Yes | 0% |
| Air Conditioning | No | Not applicable |
| Staircases | Yes | 0% |
| Lifts | Yes | 0% |
| Corridor/Lobbies | Yes | 0% |
| Fire escapes | Yes | 0% |
| Common entrance and exit for the building/common portico/foyer/verandah | Yes | 0% |
| Basement | Yes | 0% |
| Terrace | Yes | 0% |
| Outer Wall | Yes | 0% |
| Open parking areas | No | Not applicable |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | Yes | 0% |
| Common storage spaces | No | Not applicable |
Land and ownership9
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Century Silicon City Pvt Ltd | - | - |
| Century Silicon City Pvt Ltd | - | - |
| Century Silicon City Pvt Ltd | - | - |
| Century Silicon City Pvt Ltd | - | - |
| Century Silicon City Pvt Ltd | - | - |
| Century Silicon City Pvt Ltd | - | - |
| Century Silicon City Pvt Ltd | - | - |
| Century Silicon City Pvt Ltd | - | - |
| Century Silicon City Pvt Ltd | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 279.35 cr | Rs 53.57 cr |
| On-site expenditure-Salaries of workers | Rs 139.67 cr | - |
| On-site expenditure-Cost Of Services(Water, Electricity, Sewage) | Rs 52.61 cr | - |
| On-site expenditure-Site Overhead | Rs 46.56 cr | - |
| On-site expenditure-Consultants Fees | Rs 7.89 cr | - |
| Principal sum and interest payable to financial institutions-Non Banking financial institution (NBFC) | - | Rs 56.81 cr |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Chandrashekar R |
| Engineer | Swaroop Devaiah KL |
| Chartered Accountant | Sugnana Kumar H |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed165
As listed on the registration, under the names the promoter filed them with; the newest 80 of 165 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/181025/008182 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Mirai Ph1 Form - 4CA (Q2 2026-27) (1).pdf | 14 Oct 2026 |
| Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Mirai1 Form 5 - Architect (Q2 2026-27).pdf | 14 Oct 2026 |
| Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Mirai1 Form 6 - Engineer (Q2 2026-27).pdf | 14 Oct 2026 |
| Q2 2026-27 Water supply and sewage board | 14 Oct 2026 |
| Q2 2026-27 KSPCB- MOEF (Above 50 Acres) | 14 Oct 2026 |
| Q2 2026-27 KPTCL- BESCOM | 14 Oct 2026 |
| Q2 2026-27 Fire and Safety | 14 Oct 2026 |
| Q2 2026-27 Airport Authority of India | 14 Oct 2026 |
| Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Mirai Ph1 Form - 4CA (Q1 2026-27).pdf | 14 Jul 2026 |
| Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Mirai1 Form 5 - Architect (Q1 2026-27).pdf | 14 Jul 2026 |
| Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Mirai1 Form 6 - Engineer (Q1 2026-27).pdf | 14 Jul 2026 |
| Q1 2026-27 Water supply and sewage board | 14 Jul 2026 |
| Q1 2026-27 KSPCB- MOEF (Above 50 Acres) | 14 Jul 2026 |
| Q1 2026-27 KPTCL- BESCOM | 14 Jul 2026 |
| Q1 2026-27 Fire and Safety | 14 Jul 2026 |
| Q1 2026-27 Airport Authority of India | 14 Jul 2026 |
| Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Mirai Ph1 Form - 4CA (Q42026) Final.pdf | 5 May 2026 |
| Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Mirai1 Form 5 - Architect (Q42026).pdf | 5 May 2026 |
| Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Mirai1 Form 6 - Engineer (Q42026).pdf | 5 May 2026 |
| Q4 2025-26 Water supply and sewage board | 5 May 2026 |
| Q4 2025-26 KSPCB- MOEF (Above 50 Acres) | 5 May 2026 |
| Q4 2025-26 KPTCL- BESCOM | 5 May 2026 |
| Q4 2025-26 Fire and Safety | 5 May 2026 |
| Q4 2025-26 Airport Authority of India | 5 May 2026 |
| Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Mirai Ph1 Form - 4 CA (Q32025).pdf | 20 Feb 2026 |
| Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Mirai1 Form 5 - Architect (Q32026).pdf | 20 Feb 2026 |
| Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Mirai1 Form 6 - Engineer (Q32026).pdf | 20 Feb 2026 |
| Q3 2025-26 Water supply and sewage board | 20 Feb 2026 |
| Q3 2025-26 KSPCB- MOEF (Above 50 Acres) | 20 Feb 2026 |
| Q3 2025-26 KPTCL- BESCOM | 20 Feb 2026 |
| Q3 2025-26 Fire and Safety | 20 Feb 2026 |
| Q3 2025-26 Airport Authority of India | 20 Feb 2026 |
| Reply to the queriesFile: RERA Reply 30092025.pdf | 30 Sep 2025 |
| Clarification of sources of fundsFile: Annexure R1 Clarification on Sources of Funds.pdf | 30 Sep 2025 |
| Authenticated copy of current year RTCFile: Annexure R2 RTC for all survey Nos.pdf | 30 Sep 2025 |
| Connected MR showing flow of titles in favour of landownerFile: Annexure R3 MR.pdf | 30 Sep 2025 |
| Clarification on title of the PromoterFile: Annexure R4 Clarification on title.pdf | 30 Sep 2025 |
| Clarification on title of the PromoterFile: Annexure R5 Clarification on title.pdf | 30 Sep 2025 |
| Encumbrance certificatesFile: Annexure R6 EC.pdf | 30 Sep 2025 |
| Updated Form B affidavitFile: Annexure R7 Form B Affidavit.pdf | 30 Sep 2025 |
| Clarification on area detailsFile: Annexure R8 Area details.pdf | 30 Sep 2025 |
| Updated structural stabilityFile: Annexure R9 structural stability.pdf | 30 Sep 2025 |
| Clarification to agreement to sellFile: Annexure R10 Clarification and Proforma of ATS.pdf | 30 Sep 2025 |
| Updated allotment letterFile: Annexure R11 Allotment Letter.pdf | 30 Sep 2025 |
| Clarification for SEIAA NOCFile: Annexure R12 Clarification on SEIAA NOC.pdf | 30 Sep 2025 |
| Clarification to Land CostFile: Annexure R13 - Clarification on Land Cost.pdf | 30 Sep 2025 |
| STP DrawingFile: Annexure R14 STP Drawings.pdf | 30 Sep 2025 |
| RTC, survey 42P (Old No. 42/4) | - |
| Mutation, survey 42P (Old No. 42/4) | - |
| Encumbrance Certificate, survey 42P (Old No. 42/4) | - |
| Conversion/Alienation Order, survey 42P (Old No. 42/4) | - |
| Sale/Title/Gift Deed, survey 42P (Old No. 42/4) | - |
| Khatha, survey 42P (Old No. 42/4) | - |
| RTC, survey 43 (Old No. 43/3) | - |
| Mutation, survey 43 (Old No. 43/3) | - |
| Encumbrance Certificate, survey 43 (Old No. 43/3) | - |
| Conversion/Alienation Order, survey 43 (Old No. 43/3) | - |
| Sale/Title/Gift Deed, survey 43 (Old No. 43/3) | - |
| Khatha, survey 43 (Old No. 43/3) | - |
| RTC, survey 44 (Part 1) | - |
| Mutation, survey 44 (Part 1) | - |
| Encumbrance Certificate, survey 44 (Part 1) | - |
| Conversion/Alienation Order, survey 44 (Part 1) | - |
| Sale/Title/Gift Deed, survey 44 (Part 1) | - |
| Khatha, survey 44 (Part 1) | - |
| RTC, survey 44 (Part 2) | - |
| Mutation, survey 44 (Part 2) | - |
| Encumbrance Certificate, survey 44 (Part 2) | - |
| Conversion/Alienation Order, survey 44 (Part 2) | - |
| Sale/Title/Gift Deed, survey 44 (Part 2) | - |
| Khatha, survey 44 (Part 2) | - |
| RTC, survey 45 | - |
| Mutation, survey 45 | - |
| Encumbrance Certificate, survey 45 | - |
| Conversion/Alienation Order, survey 45 | - |
| Sale/Title/Gift Deed, survey 45 | - |
| Khatha, survey 45 | - |
| RTC, survey 127P | - |
| Mutation, survey 127P | - |
| Encumbrance Certificate, survey 127P | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep Century Mirai Ph1 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
MAITHRI SPRINGWOODS
MAITHRI DEVELOPERS
MYHNA ORCHID
MYHNA ESTATE PROJECTS
INNOVATIVE PALACIA
SHUBANKARA DEVELOPERS
Saideep Hiranya
Shri Saideep Srinidhi Buildcon LLP
77° LIFE
DivyaSree Infrastructure Projects Private
Concorde Econex
Concorde Housing Corporation Pvt Ltd
See every Bengaluru Urban project, with the district possession charts
Builder: Century Silicon City Private Limited
Century Silicon City Private Limited has 1 registration on RERA Karnataka, including Century Mirai Ph1. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if Century Mirai Ph1 is delayed beyond 30 Oct 2030?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of Century Mirai Ph1?
The registered promoter entity is Century Silicon City Private Limited, a company as per the filing. Its CIN U68100KA2023PTC173682 and GSTIN 29AALCC0361L1ZE can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in Century Mirai Ph1?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at Century Mirai Ph1?
The professionals named in the filing: Architect: Chandrashekar R; Engineer: Swaroop Devaiah KL; Chartered Accountant: Sugnana Kumar H. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Century Mirai Ph1?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback