ReraGenieLog inGet a buyer report

Home / Browse projects / Bengaluru Urban, Karnataka / Century Mirai Ph1

Registration approved No litigation declared Residential/Group Housing project

Century Mirai Ph1

By Century Silicon City Private Limited

RG-KA-97491 · RERA PRM/KA/RERA/1251/446/PR/181025/008182 · Last updated on RERA Karnataka portal: 14 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Oct 2030Possession promisedno revision filed
2 of 18Construction stages donefurthest along: Upto Plinth Level, 23%
260 of 475Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 165 documents Report an error

Century Mirai Ph1 is a Residential/Group Housing project by Century Silicon City Private Limited in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/181025/008182 on 18 Oct 2025. Possession is promised by 30 Oct 2030. 215 of the 475 units on this registration are recorded sold or booked, and 2 of 18 construction stages are filed complete.

At a glance

Project

  • NameCentury Mirai Ph1
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
    • 560037
  • Pincode560037
  • RERA no.PRM/KA/RERA/1251/446/PR/181025/008182
  • ReraGenie IDRG-KA-97491

Builder

  • NameCentury Silicon City Private Limited
  • Entity typeCompany
  • CINU68100KA2023PTC173682
  • GSTIN29AALCC0361L1ZE
  • Authorized SignatoryMahesh Prabhu
  • DirectorsP Ravindra Pai, P Ravindra Pai, P Ashwin Pai
  • Project HeadNeelkanth Patil

Key dates

this monthRegisteredOct 2025PromisedOct 2030

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on18 Oct 2025
  • Promised completion30 Oct 2030
  • Revised completionNone
  • Buildings5 building records
  • Documents filed165 files

Current status

45%215 of 475 units booked
21.0%Of the estimated cost spent so far

Figures as on 14 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower 01---89089
Tower 02---1020102
Tower 03---1020102
Tower 04---91091
5---91091

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 14 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

2 of 18 construction stages are filed complete. The stage furthest along is Upto Plinth Level, at 23%.

Building: 12% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level23%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)0%
Retaining wall (All types)0%
RCC or MS Framed structure0%
Masonry Construction0%
Plastering inside , outside & Ceiling0%
Joinery: Doors, Windows, Ventilators etc0%
Basic work of Water supply, Sanitary and Electrification0%
Dadoing, Skirting, Flooring, Tiles work (All types)0%
Railing and Grill fixing0%
Electrification, Water supply and Sanitary Finishing0%
Painting0%
Fire prevention and fire fighting fitting and fixture with network0%
Weather Proof work(tile,concrete)0%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work0%
Internal and External work including landscapes as per sanctioned drawings0%

Progress on shared amenities40

As on 14 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes0%
Sewage and Drainage SystemYes0%
Water conservation/rain water harvesting/recharge of ground waterYes0%
Energy managementYes0%
Fire protection and fire safety requirementsYes0%
Solid waste management and disposalYes0%
Emergency Evacuation servicesYes0%
Internal Roads & FootpathsYes0%
Electricity supply transformer and substationYes0%
Storm water drainsYes0%
Use of renewable energyYes0%
Sewage Treatment Plant (STP)Yes0%
Parks & Tree plantingYes0%
Street LightingYes0%
ElectricityYes0%
Smart Home AutomationYes0%
CCTV SurveillanceYes0%
Club HouseYes0%
Community HallYes0%
Outdoor Sports facilityYes0%
Indoor Sports facilityYes0%
Swimming PoolYes0%
GymYes0%
ParksYes0%
Power BackupYes0%
Piped GasNoNot applicable
Water and SanitationYes0%
Air ConditioningNoNot applicable
StaircasesYes0%
LiftsYes0%
Corridor/LobbiesYes0%
Fire escapesYes0%
Common entrance and exit for the building/common portico/foyer/verandahYes0%
BasementYes0%
TerraceYes0%
Outer WallYes0%
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes0%
Common storage spacesNoNot applicable

Land and ownership9

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area38,033 sq m
Named landowners9
LandownerVillageDistrict
Century Silicon City Pvt Ltd--
Century Silicon City Pvt Ltd--
Century Silicon City Pvt Ltd--
Century Silicon City Pvt Ltd--
Century Silicon City Pvt Ltd--
Century Silicon City Pvt Ltd--
Century Silicon City Pvt Ltd--
Century Silicon City Pvt Ltd--
Century Silicon City Pvt Ltd--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 526.08 cr
Cost incurredRs 110.38 cr
Spent of the estimate20.98%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 279.35 crRs 53.57 cr
On-site expenditure-Salaries of workersRs 139.67 cr-
On-site expenditure-Cost Of Services(Water, Electricity, Sewage)Rs 52.61 cr-
On-site expenditure-Site OverheadRs 46.56 cr-
On-site expenditure-Consultants FeesRs 7.89 cr-
Principal sum and interest payable to financial institutions-Non Banking financial institution (NBFC)-Rs 56.81 cr

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectChandrashekar R
EngineerSwaroop Devaiah KL
Chartered AccountantSugnana Kumar H

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed165

As listed on the registration, under the names the promoter filed them with; the newest 80 of 165 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/181025/008182 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Mirai Ph1 Form - 4CA (Q2 2026-27) (1).pdf14 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Mirai1 Form 5 - Architect (Q2 2026-27).pdf14 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Mirai1 Form 6 - Engineer (Q2 2026-27).pdf14 Oct 2026
Q2 2026-27 Water supply and sewage board14 Oct 2026
Q2 2026-27 KSPCB- MOEF (Above 50 Acres)14 Oct 2026
Q2 2026-27 KPTCL- BESCOM14 Oct 2026
Q2 2026-27 Fire and Safety14 Oct 2026
Q2 2026-27 Airport Authority of India14 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Mirai Ph1 Form - 4CA (Q1 2026-27).pdf14 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Mirai1 Form 5 - Architect (Q1 2026-27).pdf14 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Mirai1 Form 6 - Engineer (Q1 2026-27).pdf14 Jul 2026
Q1 2026-27 Water supply and sewage board14 Jul 2026
Q1 2026-27 KSPCB- MOEF (Above 50 Acres)14 Jul 2026
Q1 2026-27 KPTCL- BESCOM14 Jul 2026
Q1 2026-27 Fire and Safety14 Jul 2026
Q1 2026-27 Airport Authority of India14 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Mirai Ph1 Form - 4CA (Q42026) Final.pdf5 May 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Mirai1 Form 5 - Architect (Q42026).pdf5 May 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Mirai1 Form 6 - Engineer (Q42026).pdf5 May 2026
Q4 2025-26 Water supply and sewage board5 May 2026
Q4 2025-26 KSPCB- MOEF (Above 50 Acres)5 May 2026
Q4 2025-26 KPTCL- BESCOM5 May 2026
Q4 2025-26 Fire and Safety5 May 2026
Q4 2025-26 Airport Authority of India5 May 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Mirai Ph1 Form - 4 CA (Q32025).pdf20 Feb 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Mirai1 Form 5 - Architect (Q32026).pdf20 Feb 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Mirai1 Form 6 - Engineer (Q32026).pdf20 Feb 2026
Q3 2025-26 Water supply and sewage board20 Feb 2026
Q3 2025-26 KSPCB- MOEF (Above 50 Acres)20 Feb 2026
Q3 2025-26 KPTCL- BESCOM20 Feb 2026
Q3 2025-26 Fire and Safety20 Feb 2026
Q3 2025-26 Airport Authority of India20 Feb 2026
Reply to the queriesFile: RERA Reply 30092025.pdf30 Sep 2025
Clarification of sources of fundsFile: Annexure R1 Clarification on Sources of Funds.pdf30 Sep 2025
Authenticated copy of current year RTCFile: Annexure R2 RTC for all survey Nos.pdf30 Sep 2025
Connected MR showing flow of titles in favour of landownerFile: Annexure R3 MR.pdf30 Sep 2025
Clarification on title of the PromoterFile: Annexure R4 Clarification on title.pdf30 Sep 2025
Clarification on title of the PromoterFile: Annexure R5 Clarification on title.pdf30 Sep 2025
Encumbrance certificatesFile: Annexure R6 EC.pdf30 Sep 2025
Updated Form B affidavitFile: Annexure R7 Form B Affidavit.pdf30 Sep 2025
Clarification on area detailsFile: Annexure R8 Area details.pdf30 Sep 2025
Updated structural stabilityFile: Annexure R9 structural stability.pdf30 Sep 2025
Clarification to agreement to sellFile: Annexure R10 Clarification and Proforma of ATS.pdf30 Sep 2025
Updated allotment letterFile: Annexure R11 Allotment Letter.pdf30 Sep 2025
Clarification for SEIAA NOCFile: Annexure R12 Clarification on SEIAA NOC.pdf30 Sep 2025
Clarification to Land CostFile: Annexure R13 - Clarification on Land Cost.pdf30 Sep 2025
STP DrawingFile: Annexure R14 STP Drawings.pdf30 Sep 2025
RTC, survey 42P (Old No. 42/4)-
Mutation, survey 42P (Old No. 42/4)-
Encumbrance Certificate, survey 42P (Old No. 42/4)-
Conversion/Alienation Order, survey 42P (Old No. 42/4)-
Sale/Title/Gift Deed, survey 42P (Old No. 42/4)-
Khatha, survey 42P (Old No. 42/4)-
RTC, survey 43 (Old No. 43/3)-
Mutation, survey 43 (Old No. 43/3)-
Encumbrance Certificate, survey 43 (Old No. 43/3)-
Conversion/Alienation Order, survey 43 (Old No. 43/3)-
Sale/Title/Gift Deed, survey 43 (Old No. 43/3)-
Khatha, survey 43 (Old No. 43/3)-
RTC, survey 44 (Part 1)-
Mutation, survey 44 (Part 1)-
Encumbrance Certificate, survey 44 (Part 1)-
Conversion/Alienation Order, survey 44 (Part 1)-
Sale/Title/Gift Deed, survey 44 (Part 1)-
Khatha, survey 44 (Part 1)-
RTC, survey 44 (Part 2)-
Mutation, survey 44 (Part 2)-
Encumbrance Certificate, survey 44 (Part 2)-
Conversion/Alienation Order, survey 44 (Part 2)-
Sale/Title/Gift Deed, survey 44 (Part 2)-
Khatha, survey 44 (Part 2)-
RTC, survey 45-
Mutation, survey 45-
Encumbrance Certificate, survey 45-
Conversion/Alienation Order, survey 45-
Sale/Title/Gift Deed, survey 45-
Khatha, survey 45-
RTC, survey 127P-
Mutation, survey 127P-
Encumbrance Certificate, survey 127P-

How this compares with Bengaluru Urban

45%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Century Mirai Ph1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: Century Silicon City Private Limited

Century Silicon City Private Limited has 1 registration on RERA Karnataka, including Century Mirai Ph1. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Century Mirai Ph1 is delayed beyond 30 Oct 2030?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Century Mirai Ph1?

The registered promoter entity is Century Silicon City Private Limited, a company as per the filing. Its CIN U68100KA2023PTC173682 and GSTIN 29AALCC0361L1ZE can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Century Mirai Ph1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Century Mirai Ph1?

The professionals named in the filing: Architect: Chandrashekar R; Engineer: Swaroop Devaiah KL; Chartered Accountant: Sugnana Kumar H. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Century Mirai Ph1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Century Mirai Ph1. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Century Mirai Ph1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.