Home / Browse projects / Bengaluru Urban, Karnataka / MAITHRI SPRINGWOODS
MAITHRI SPRINGWOODS
RG-KA-30623 · RERA PRM/KA/RERA/1251/446/PR/230726/008837 · Last updated on RERA Karnataka portal: 15 Oct 2026
Source: official RERA Karnataka filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
MAITHRI SPRINGWOODS is a Residential/Group Housing project by MAITHRI DEVELOPERS in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/230726/008837 on 23 Jul 2026. Possession is promised by 15 Jul 2031. 10 of the 630 units on this registration are recorded sold or booked, and 1 of 18 construction stages are filed complete.
At a glance
Project
- NameMAITHRI SPRINGWOODS
- TypeResidential/Group Housing
- Location
- Bengaluru East
- Bengaluru Urban
- 560037
- Pincode560037
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1251/446/PR/230726/008837
- ReraGenie IDRG-KA-30623
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on23 Jul 2026
- Promised completion15 Jul 2031
- Revised completionNone
- Buildings6 building records
- Documents filed184 files
Current status
Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| BUILDING-1-(TOWER-1) | - | - | - | 113 | 0 | 113 |
| BUILDING-1 -(TOWER-2) | - | - | - | 113 | 0 | 113 |
| BUILDING -1- (TOWER-3) | - | - | - | 113 | 0 | 113 |
| BUILDING - 2- (TOWER-5) | - | - | - | 113 | 0 | 113 |
| BUILDING - 2 - (TOWER-6) | - | - | - | 105 | 0 | 105 |
| BUILDING - 2 - (TOWER-7) | - | - | - | 73 | 0 | 73 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
1 of 18 construction stages are filed complete. The stage furthest along is Foundation footing work, at 20%.
Building: 7% average across the applicable activities
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | 100% |
| Foundation footing work | 20% |
| Upto Plinth Level | 0% |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | 0% |
| Retaining wall (All types) | 0% |
| RCC or MS Framed structure | 0% |
| Masonry Construction | 0% |
| Plastering inside , outside & Ceiling | 0% |
| Joinery: Doors, Windows, Ventilators etc | 0% |
| Basic work of Water supply, Sanitary and Electrification | 0% |
| Dadoing, Skirting, Flooring, Tiles work (All types) | 0% |
| Railing and Grill fixing | 0% |
| Electrification, Water supply and Sanitary Finishing | 0% |
| Painting | 0% |
| Fire prevention and fire fighting fitting and fixture with network | 0% |
| Weather Proof work(tile,concrete) | 0% |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Elevation work | 0% |
| Internal and External work including landscapes as per sanctioned drawings | 0% |
Progress on shared amenities40
As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | 0% |
| Sewage and Drainage System | Yes | 0% |
| Water conservation/rain water harvesting/recharge of ground water | Yes | 0% |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Solid waste management and disposal | Yes | 0% |
| Emergency Evacuation services | Yes | 0% |
| Internal Roads & Footpaths | Yes | 0% |
| Electricity supply transformer and substation | Yes | 0% |
| Storm water drains | No | Not applicable |
| Use of renewable energy | No | Not applicable |
| Sewage Treatment Plant (STP) | Yes | 0% |
| Parks & Tree planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Electricity | Yes | 0% |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | 0% |
| Club House | Yes | 0% |
| Community Hall | Yes | 0% |
| Outdoor Sports facility | Yes | 0% |
| Indoor Sports facility | Yes | 0% |
| Swimming Pool | Yes | 0% |
| Gym | Yes | 0% |
| Parks | Yes | 0% |
| Power Backup | Yes | 0% |
| Piped Gas | No | Not applicable |
| Water and Sanitation | Yes | 0% |
| Air Conditioning | No | Not applicable |
| Staircases | Yes | 0% |
| Lifts | Yes | 0% |
| Corridor/Lobbies | Yes | 0% |
| Fire escapes | Yes | 0% |
| Common entrance and exit for the building/common portico/foyer/verandah | Yes | 0% |
| Basement | Yes | 0% |
| Terrace | Yes | 0% |
| Outer Wall | Yes | 0% |
| Open parking areas | Yes | 0% |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | No | Not applicable |
| Common storage spaces | No | Not applicable |
Land and ownership16
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| K LAKSHMISUTHAA & OTHERS | - | - |
| K LAKSHMISUTHAA & OTHERS | - | - |
| KANDERI BABU @ OTHERS | - | - |
| BVS REDDY | - | - |
| PARVATHAMMA w/o Ramaiaha reddy | - | - |
| V PADMA & OTHERS | - | - |
| BVS REDDY | - | - |
| BVS REDDY | - | - |
| PARVATHAMMA w/o Ramaiaha reddy | - | - |
| BVS REDDY | - | - |
| BVS REDDY | - | - |
| V PADMA & OTHERS | - | - |
| JAYALAKSHMI B | - | - |
| Jayalakshmi S | - | - |
| PARVATHAMMA & OTHERS | - | - |
| BIDDAPPA PREMALATHA | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 321.68 cr | Rs 2.63 cr |
| On-site expenditure-Salaries of workers | Rs 16.08 cr | - |
| On-site expenditure-Consultants Fees | Rs 6.43 cr | Rs 3.00 cr |
| On-site expenditure-Site Overhead | Rs 3.22 cr | - |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | ALEKHYA REDDY |
| Engineer | R Ravindra |
| Chartered Accountant | V S Krishna Murthy |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed184
As listed on the registration, under the names the promoter filed them with; the newest 80 of 184 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/230726/008837 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form-4 CA Certificate.pdf | 15 Oct 2026 |
| Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form-5 Architect Certificate sept-26.pdf | 15 Oct 2026 |
| Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form-6 MAITHRI SPRINGWOODS.pdf | 15 Oct 2026 |
| Q2 2026-27 Water supply and sewage board | 15 Oct 2026 |
| Q2 2026-27 BSNL/Telecommunication Department | 15 Oct 2026 |
| proforma agreement for saleFile: afs maithri NEW.pdf | 18 Jul 2026 |
| Titile deed Lakshmisutha Sy no 321/2 33.5 GuntaFile: lakshmi sutha 11064-2005-06.pdf | 17 Jul 2026 |
| Titile deed Lakshmisutha Sy no 321/3 16.5 GuntaFile: lakshmi sutha 11067-2005-06.pdf | 17 Jul 2026 |
| Title deed Padma Sy no 324/2,325/2 (17 G & 31 G)File: Padma sale deed 485-14-15 dated 06-05-2014.pdf | 17 Jul 2026 |
| Title deed Ramaiah reddy Sy no 324/1 & 325/1 (1A 1G & 15 G)File: sale deed 14-12-1939 Doc no 1978 Ramaiah Reddy.pdf | 17 Jul 2026 |
| Title deed Sy No 476, 3A 13 G (Jayalakshmi S, Jayalakshmi B, Premalatha & Parvathamma)File: WILL 54 BAR 2001-2002 476.pdf | 17 Jul 2026 |
| Title deed Kanderbabu Sy no 321/4 17GFile: kanderubabu 11068-2005-06.pdf | 17 Jul 2026 |
| Full Land MRFile: Thubarahalli all MR.pdf | 17 Jul 2026 |
| Jayalakshmi B JDA Sy no 476File: Jayalakshmi B JDA 22-07-2022_compressed_high (1) (1).pdf | 17 Jul 2026 |
| Jayalakshmi S JDA Sy no 476File: Jayalakshmi S JDA.pdf | 17 Jul 2026 |
| Parvathamma JDA Sy no 476File: Parvathamma JDA.pdf | 17 Jul 2026 |
| Premalatha JDA Sy no 476File: Premalatha JDA.pdf | 17 Jul 2026 |
| S Jayalakshmi ECFile: s jayalakshmi ec 2004 to june 2026.pdf | 17 Jul 2026 |
| B Jayalakshmi ECFile: b jayalakshmi ec 2004-april 2026.pdf | 17 Jul 2026 |
| Parvathamma ECFile: parvathamma EC 2004- april 2026.pdf | 17 Jul 2026 |
| Premalatha ECFile: premalatha ec 2004 to june 2026.pdf | 17 Jul 2026 |
| Lakshmisutha & Kanderbabu ECFile: lakshmisutha and kanderi babu EC 2004 to till date.pdf | 17 Jul 2026 |
| BVS Reddy 323/1 ECFile: BVS REDDY 323 bar 1 ec 2004 to 06-07-2026.pdf | 17 Jul 2026 |
| Padma 324/2 & 325/2 ECFile: padma 324 bar 2 and 325 bar 2 ec 2004 to 06-07-2026.pdf | 17 Jul 2026 |
| BVS Reddy 324/3 & 325/3File: BVS REDDY 324 bar 3 and 325 bar 3 ec 2004 to 25-04-2026.pdf | 17 Jul 2026 |
| BVS Reddy 324/4 & 325/4File: BVS REDDY 324 bar4 and 325 bar4 ec 2004- 25-04-2025.pdf | 17 Jul 2026 |
| Ramaiah Reddy 324/1 & 325/1File: ramayaih reddy 324 bar 1 and 325 bar 1 ec from 2004 - 25-04-2026.pdf | 17 Jul 2026 |
| Single Plot layout/Development plan ApprovedFile: scan0001.pdf | 17 Jul 2026 |
| ADLR Certified survey sketchFile: 0027_001 (1) (1).pdf | 17 Jul 2026 |
| Area/ No of units of KSPCB noc is not matching with sanction planFile: maithri kspcb.pdf | 17 Jul 2026 |
| Single Plot layout/Development plan orderFile: BDA Plan Work Order.pdf | 17 Jul 2026 |
| Phase wise Development phase demarcation drawingsFile: scan0001.pdf | 17 Jul 2026 |
| Village mapFile: Village map (4).pdf | 17 Jul 2026 |
| KTCP ActFile: ktcp act.pdf | 17 Jul 2026 |
| fire fighting facilitiesFile: Maithri Fire NOC.pdf | 17 Jul 2026 |
| Brochure of the projectFile: broucher maitri.pdf | 17 Jul 2026 |
| master planFile: CDP Plan (1).pdf | 17 Jul 2026 |
| STRUCTURAL Engineer licenceFile: Self attested BEP.PDF | 17 Jul 2026 |
| Engineer licenseFile: Engineer license (2).pdf | 17 Jul 2026 |
| project specificationFile: project specification (4).pdf | 17 Jul 2026 |
| ESCOM NOCFile: Bescom Noc thubarahalli .pdf | 17 Jul 2026 |
| SEIAA NOCFile: Environmental.pdf | 17 Jul 2026 |
| STP drawingFile: Maithri RERA STP.pdf | 17 Jul 2026 |
| Phase wise DevelopmentFile: phase wise detailes.pdf | 17 Jul 2026 |
| allotment letterFile: Allotment letter (49).pdf | 17 Jul 2026 |
| Proforma of agreementFile: afs maithri.pdf | 17 Jul 2026 |
| RTC, survey 321/2 | - |
| Mutation, survey 321/2 | - |
| Encumbrance Certificate, survey 321/2 | - |
| Conversion/Alienation Order, survey 321/2 | - |
| JDA, survey 321/2 | - |
| Khatha, survey 321/2 | - |
| RTC, survey 321/3 | - |
| Mutation, survey 321/3 | - |
| Encumbrance Certificate, survey 321/3 | - |
| Conversion/Alienation Order, survey 321/3 | - |
| JDA, survey 321/3 | - |
| Khatha, survey 321/3 | - |
| RTC, survey 321/4 | - |
| Mutation, survey 321/4 | - |
| Encumbrance Certificate, survey 321/4 | - |
| Conversion/Alienation Order, survey 321/4 | - |
| JDA, survey 321/4 | - |
| Khatha, survey 321/4 | - |
| RTC, survey 323/1 | - |
| Mutation, survey 323/1 | - |
| Encumbrance Certificate, survey 323/1 | - |
| Conversion/Alienation Order, survey 323/1 | - |
| Sale/Title/Gift Deed, survey 323/1 | - |
| Khatha, survey 323/1 | - |
| RTC, survey 324/1 | - |
| Mutation, survey 324/1 | - |
| Encumbrance Certificate, survey 324/1 | - |
| Conversion/Alienation Order, survey 324/1 | - |
| JDA, survey 324/1 | - |
| Khatha, survey 324/1 | - |
| RTC, survey 324/2 | - |
| Mutation, survey 324/2 | - |
| Encumbrance Certificate, survey 324/2 | - |
| Conversion/Alienation Order, survey 324/2 | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep MAITHRI SPRINGWOODS on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Filed coordinates, straight-line distance. 74 registered projects within 2 km.
Century Mirai Ph1
Century Silicon City Private Limited
MYHNA ORCHID
MYHNA ESTATE PROJECTS
INNOVATIVE PALACIA
SHUBANKARA DEVELOPERS
Saideep Hiranya
Shri Saideep Srinidhi Buildcon LLP
77° LIFE
DivyaSree Infrastructure Projects Private
Concorde Econex
Concorde Housing Corporation Pvt Ltd
See every Bengaluru Urban project, with the district possession charts
Builder: MAITHRI DEVELOPERS
Maithri Developers has 3 registrations on RERA Karnataka, including Shilpitha Royal Oak and Shilpitha Tech Park. Its filings declare 1 earlier project, none of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if MAITHRI SPRINGWOODS is delayed beyond 15 Jul 2031?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of MAITHRI SPRINGWOODS?
The registered promoter entity is MAITHRI DEVELOPERS, a proprietorship as per the filing. Its GSTIN 29AIMPB2102N1ZB can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in MAITHRI SPRINGWOODS?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at MAITHRI SPRINGWOODS?
The professionals named in the filing: Architect: ALEKHYA REDDY; Engineer: R Ravindra; Chartered Accountant: V S Krishna Murthy. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in MAITHRI SPRINGWOODS?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.