Registration approved Residential/Group Housing project

Sobha Dream Acres - Tropical Greens Phase 19 Wings 19 and 20

By Sobha Limited

RG-KA-80298 · RERA PRM/KA/RERA/1251/446/PR/180612/001897

Source: official RERA Karnataka filing

Red flags

  • 3 complaints at RERA Karnataka
  • Completion date moved by 9 months
  • 1 extension taken

Clear

  • Separate project account declared
Sep 2023Possession promisedmoved 9 months from the original
3Complaints at RERA Karnatakaon this registration
Jump to the 67 documents Report an error

Sobha Dream Acres - Tropical Greens Phase 19 Wings 19 and 20 is a Residential/Group Housing project by Sobha Limited in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/180612/001897 on 12 Jun 2018. Possession is promised by 30 Sep 2023. The completion date has moved by 9 months from the original filing. 3 complaints are on record with the regulator.

At a glance

Project

  • NameSobha Dream Acres - Tropical Greens Phase 19 Wings 19 and 20
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/446/PR/180612/001897
  • ReraGenie IDRG-KA-80298

Builder

  • NameSobha Limited
  • Entity typeCompany
  • CINL45201KA1995PLC018475
  • Authorized SignatoryLt. Gen Mathew Mammen (Retd), PVSM, AVSM,VSM (Bar)
  • Other registrations119 more →
  • No longer live8 withdrawn or revoked
  • Declared earlier projects196 →

Key dates

this monthRegisteredJun 2018First promiseDec 2022Revised toSep 2023

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on12 Jun 2018
  • Promised completion30 Sep 2023
  • Revised completionRevised to 30 Sep 2023 (originally 31 Dec 2022)
  • Buildings2 building records
  • Documents filed67 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Wing 19---1090109
Wing 20---1120112

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level BeamNot applicable
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etcNot applicable
Plastering inside , outside & CeilingNot applicable
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network-
Weather Proof work(tile,concrete)-
Painting-
Elevation workNot applicable
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsYes-
Sewage and Drainage SystemYes-
Parks & Tree plantingYes-
Street LightingYes-
Provision for community buildings and for treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes-
Water conservationNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes-
Education/Health/Other public amenitiesNoNot applicable
Electricity supply transformer and substationYes-
Emergency Evacuation servicesNoNot applicable
Storm water drainsYes-
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseYes-
Community HallYes-
Outdoor Sports facilityYes-
Indoor Sports facilityYes-
Swimming PoolYes-
GymYes-
ParksYes-
Power BackupYes-
GasNoNot applicable
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesNoNot applicable
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallNoNot applicable
Open parking areas and common storage spacesYes-
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area7,219 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 98.19 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectArun Kumar
EngineerAnil kumar S Hokrani

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionDec 2022 → Sep 2023

No reason recorded in the filing

Complaints filed with RERA Karnataka3

Case no.ComplainantRespondentFiled
CMP/190424/0002750-Sobha Limited24/04/2019
CMP/190718/0003635-Sobha Limited18/07/2019
CMP/200520/0005914-Sobha Limited20/05/2020

Documents filed67

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/180612/001897 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CertificateFile: Registration Certificate.pdf-
BBMP Plan Sanction Letter - Sobha Dream Acres-
Sanctioned Plan - Sobha Dream Acres-
Approved Layout Plan - Non Applicability-
Proforma Sale deed 19 and 20-
Tropical Greens - Ph 19 Wing 19 and 20-
Sale Deed Wing 19 and 20-
Section and Elevation 19 & 20-
Wing 19 & 20-
Intimation Letter - Wing 19 & 20-
Sobha Dream Acres Wing 19, 20-
NOC's Note-
Specifications - Wing 19 and 20-
EC Dream Acres 19 & 20-min-
Khatha - Balagere-
Sale Deed, RTC, Khata W 19 & 20-
Conversion Order W 19 & 20-
Relinquishment Deed-
Fire NOC-
AAI & HAL NOC-
BESCOM NOC-
BWSSB NOC-
KSPCB NOC-
SEIAA-
Telecom NOC-
Unnamed document-
Not Appl - Inspector of Factories-
Engineer Cert - Wing 19 & 20-
Floor Plans, Section and Elevation-
Approved Layout Plan - Non Applicability-
Section, Elevtion & Specs-
Balance Sheet 2016 - 2017File: Balance Sheet - Mar 2015.pdf-
Balance Sheet 2015 - 2016File: Balance Sheet - Mar 2016.pdf-
Balance Sheet 2014 - 2015File: Balance Sheet - Mar 2017.pdf-
Audited Profit and Loss Statement 2016 - 2017File: Profit Loss Statement - Mar 2015.pdf-
Audited Profit and Loss Statement 2015 - 2016File: Profit Loss Statement - Mar 2016.pdf-
Audited Profit and Loss Statement 2014 - 2015File: Profit Loss Statement - Mar 2017.pdf-
Director's Report 2016 - 2017File: DR_2014-15.pdf-
Director's Report 2015 - 2016File: DR_2015-16.pdf-
Director's Report 2014 - 2015File: DR_2016-17.pdf-
Cash Flow Statement 2016 - 2017File: Cash Flow - Mar 2015.pdf-
Cash Flow Statement 2015 - 2016File: Cash Flow - Mar 2016.pdf-
Auditor's Report 2016 - 2017File: Auditors Report - Mar 2015.pdf-
Auditor's Report 2015 - 2016File: Auditors Report - Mar 2016.pdf-
Auditor's Report 2014 - 2015File: Auditors Report - Mar 2017.pdf-
Income Tax Return Acknowledgement 2016 - 2017File: ITR 2014-15.pdf-
Income Tax Return Acknowledgement 2015 - 2016File: ITR 2015-16.pdf-
Income Tax Return Acknowledgement 2014 - 2015File: ITR 2016-17.pdf-
Dream acres_Tropical Greens Ph 19 Wing 19 & 20-
Prospectus/BrochureFile: Sobha Dream Acres Wing 19, 20.pdf-
Advertisement Copy 1File: NA - Advertisements.pdf-
Tower Excel SheetFile: PRM_KA_RERA_1251_446_PR_180612_001897.xlsx-
Loan raised documentFile: SDA PH19 NOC.pdf-
Stability CertificateFile: SSC SDA18 19 20 39 40.pdf-
Road cutting permission letter issued by the planning Authority for laying Water supply line, sanitary line, UFile: SDA Road cutting NA.pdf-
NOC issued by the Fire Force department after completion of workFile: FFC w 18 19 20 39 40.pdf-
Occupancy CertificateFile: SDA BBMP OC Wing 19 20.pdf-
Consent for operation issued by KSPCBFile: KSPCB CFO Wings 18 19 20 27 28 35 to 40.pdf-
Certificate of operation for lifts issued by the Chief of Department of Electrical inspectorate Government of File: WING 18 to 20 27 and 28 LIFT LICENSE SDA.pdf-
Sanctioned Letter issued by concerned ESCOM of Power sanction and details of transformer installed and whetherFile: BESCOM Power Sanction Letter Dream Acres.pdf-
Sanctioned letter issued by concerned water supply and sanitary board for the projectFile: BWSSB all wings.pdf-
Details of external infrastructure work such as drive way, play area, park, STP and water treatment plant, WheFile: Architect certificate SDA P 19.pdf-
Common Area and other amenities facilities are completed or not and details of handling over of the same to asFile: SDA Tropical greens DOD compressed.pdf-
Details of undivided share of land handed over to the association of allotteesFile: SDA UDS W19 and 20.pdf-
Architect certificate for having completed the work(in format no 5)File: Architect certificate SDA P 19.pdf-
Chartered Accountant certificate for having completed the work(in format no 4)File: SDA PH19.pdf-
Affidavit cum declaration from promoter for having completed the project as per specification and as per adverFile: Affidavit Tropical Greens P19 W19 20.pdf-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one moved by 9 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Sobha Dream Acres - Tropical Greens Phase 19 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmSobha Dream Acres - TropOther 94Dot size: filed unitsN

Filed coordinates, straight-line distance. 94 registered projects within 2 km.

Builder: Sobha Limited

SOBHA LIMITED has 120 registrations on RERA Karnataka, including Sobha Oakshire Phase 1 Wing 1,2,7 and 8 and Sobha Oakshire Phase 2 Wing 3,4,9 and 10. Its filings declare 196 earlier projects, 85 of them declared completed. Litigation is declared on 33 of its registrations. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Sobha Dream Acres - Tropical Greens Phase 19 Wings 19 and 20 is delayed beyond 30 Sep 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Sobha Dream Acres - Tropical Greens Phase 19 Wings 19 and 20?

The registered promoter entity is Sobha Limited, a company as per the filing. Its CIN L45201KA1995PLC018475 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Sobha Dream Acres - Tropical Greens Phase 19 Wings 19 and 20?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Sobha Dream Acres - Tropical Greens Phase 19 Wings 19 and 20?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at Sobha Dream Acres - Tropical Greens Phase 19 Wings 19 and 20?

The professionals named in the filing: Architect: Arun Kumar; Engineer: Anil kumar S Hokrani. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Sobha Dream Acres - Tropical Greens Phase 19 Wings 19 and 20?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Sobha Dream Acres - Tropical Greens Phase 19 Wings 19 and 20. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Sobha Dream Acres - Tropical Greens Phase 19 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.