ReraGenieLog inGet a buyer report

Home / Browse projects / Bengaluru Urban, Karnataka / SNN ESTATES FELICITY

Registration approved No litigation declared Residential/Group Housing project

SNN ESTATES FELICITY

By SNN Builders Private Limited

RG-KA-70217 · RERA PRM/KA/RERA/1251/309/PR/220124/006568 · Last updated on RERA Karnataka portal: 14 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • 1 complaint at RERA Karnataka

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
Dec 2028Possession promisedno revision filed
1 of 17Construction stages donefurthest along: Foundation footing work, 98%
238 of 604Units unsoldnot recorded sold or booked
1Complaints at RERA Karnatakaon this registration
Jump to the 233 documents Report an error

SNN ESTATES FELICITY is a Residential/Group Housing project by SNN Builders Private Limited in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/309/PR/220124/006568 on 22 Jan 2024. Possession is promised by 31 Dec 2028. 366 of the 604 units on this registration are recorded sold or booked, and 1 of 17 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameSNN ESTATES FELICITY
  • TypeResidential/Group Housing
  • Location
    • Bengaluru North
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/309/PR/220124/006568
  • ReraGenie IDRG-KA-70217

Builder

  • NameSNN Builders Private Limited
  • Entity typeCompany
  • CINU45202KA2009PTC051411
  • GSTIN29AANCS6172K1ZL
  • Authorized SignatoryNitin Agarwal
  • DirectorsNikhil Agarwal, Nitin Agarwal, Nikhil Agarwal
  • Project HeadNikhil Agarwal
  • Other registrations1 more →
  • Declared earlier projects1 →

Key dates

this monthRegisteredJan 2024PromisedDec 2028

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on22 Jan 2024
  • Promised completion31 Dec 2028
  • Revised completionNone
  • Buildings9 building records
  • Documents filed233 files

Current status

61%366 of 604 units booked
48.6%Of the estimated cost spent so far

Figures as on 14 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower 1---67067
Tower 2---67067
Tower 3---67067
Tower 4---67067
Tower 5---84084
Tower 6---84084
Tower 7---56056
Tower 8---56056
Tower 9---56056

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 14 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

1 of 17 construction stages are filed complete. The stage furthest along is Foundation footing work, at 98%.

Building: 39% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work98%
Retaining wall (All types)96%
Plinth level Beam92%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)95%
RCC or MS Framed structure50%
Masonry construction: Bricks, Concrete blocks etc40%
Plastering inside , outside & Ceiling20%
Joinery: Doors, Windows, Ventilators etc5%
Basic work of Water supply, Sanitary and Electrification12%
Dadoing, Skirting, Flooring, Tiles work (All types)7%
Railing and Grill fixing2%
Electrification, Water supply and Sanitary Finishing16%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network5%
Weather Proof work(tile,concrete)12%
Painting10%
Elevation workNot applicable
Internal and External work including landscapes as per santioned drawings10%

Progress on shared amenities41

As on 14 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes20%
Internal Roads & FootpathsNoNot applicable
Sewage and Drainage SystemYes5%
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
Provision for community buildings and for treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes0%
Water conservationNoNot applicable
Energy managementYes0%
Fire protection and fire safety requirementsYes25%
Education/Health/Other public amenitiesYes0%
Electricity supply transformer and substationYes0%
Emergency Evacuation servicesNoNot applicable
Storm water drainsYes0%
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterYes0%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseYes9%
Community HallYes0%
Outdoor Sports facilityYes0%
Indoor Sports facilityYes0%
Swimming PoolYes15%
GymYes0%
ParksYes0%
Power BackupYes0%
GasNoNot applicable
Water and SanitationYes20%
Air Conditioning And incerntionNoNot applicable
StaircasesYes75%
LiftsYes0%
Staircases and Lift lobbies, corridor,lobbies, corridorYes65%
Fire escapesYes40%
Common entrance and exit for the building / common portico/foyer/verandahYes40%
BasementYes90%
TerraceYes25%
Outer WallYes55%
Open parking areas and common storage spacesNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable

Land and ownership5

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Named landowners5
LandownerVillageDistrict
SNN Builders Pvt Ltd--
SNN Builders Pvt Ltd--
N Subramani--
Usha J--
Usha J--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 332.49 cr
Cost incurredRs 161.47 cr
Spent of the estimate48.56%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 268.09 crRs 156.61 cr
Principal sum and interest payable to financial institutions-Non Banking financial institution (NBFC)*Rs 35.00 cr-
On-site expenditure-Salaries of workersRs 28.90 crRs 4.87 cr
Payment of taxesRs 50.00 lakh-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectGouri Mohan Upasani
EngineerHP Yogesh
Chartered AccountantRamakrishna Kamat

Complaints filed with RERA Karnataka1

Case no.ComplainantRespondentFiled
00861/2024-SNN Builders Private Limited10/09/2024

Documents filed233

As listed on the registration, under the names the promoter filed them with; the newest 80 of 233 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/309/PR/220124/006568 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Felicity Form 4 Final 26-27 Q2.pdf14 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Felicity-Architect Certificate 26-27 Q2.pdf14 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Felicity-Form-6 Engineer Certificate 26 27 Q2.pdf14 Oct 2026
Q2 2026-27 Water supply and sewage board14 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)14 Oct 2026
Q2 2026-27 KPTCL- BESCOM14 Oct 2026
Q2 2026-27 Fire and Safety14 Oct 2026
Q2 2026-27 Airport Authority of India14 Oct 2026
Q2 2026-27 BSNL/Telecommunication Department14 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Felicity Form 4 Q1 26-27.pdf13 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Felicity-Architect Certificate 26-27 Q1_.pdf13 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form-6 Engineer Certificate 26 27 Q1.pdf13 Jul 2026
Q1 2026-27 Water supply and sewage board13 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)13 Jul 2026
Q1 2026-27 KPTCL- BESCOM13 Jul 2026
Q1 2026-27 Fire and Safety13 Jul 2026
Q1 2026-27 Airport Authority of India13 Jul 2026
Q1 2026-27 BSNL/Telecommunication Department13 Jul 2026
Sold and unsold DetailsFile: 1 Sold and unsold Details.pdf21 May 2026
Engineer License Self-attestedFile: 2 Engineer License Self-attested.pdf21 May 2026
BESCOM NOC Delcaration AffidavitFile: 3 BESCOM NOC Delcaration Affidavit.pdf21 May 2026
NOC-FIRE AND EMERGENCY SERVICEFile: 5 NOC-FIRE AND EMERGENCY SERVICE.pdf21 May 2026
Response to th ClarificationFile: 1 Response to th Clarification.pdf19 Jan 2024
EC FROM 13-10-2022 TO 10-04-023File: 1 EC FROM 13-10-2022 TO 10-04-023.pdf19 Jan 2024
RTC Sy No 35File: 2 RTC Sy No 35.pdf19 Jan 2024
RTC Sy No 34-3File: 3 RTC Sy No 34-3.pdf19 Jan 2024
Common area &amenities details certified by EngineerFile: 4 Common area &amenities details certified by Engineer.pdf19 Jan 2024
Engineer License self AttestedFile: 5 Engineer License self Attested.pdf19 Jan 2024
KSPCB NOC with fee paid receiptFile: 6 KSPCB NOC with fee paid receipt.pdf19 Jan 2024
Guideline ValueFile: 7 Guideline Value.pdf19 Jan 2024
BESCOM NOC self-attestedFile: 8 BESCOM NOC self-attested.pdf19 Jan 2024
BWSSB NOC self-attestedFile: 9 BWSSB NOC self-attested.pdf19 Jan 2024
RTC, survey 34/3-
Mutation, survey 34/3-
Encumbrance Certificate, survey 34/3-
Conversion/Alienation Order, survey 34/3-
Sale/Title/Gift Deed, survey 34/3-
Khatha, survey 34/3-
RTC, survey 35-
Mutation, survey 35-
Encumbrance Certificate, survey 35-
Conversion/Alienation Order, survey 35-
Sale/Title/Gift Deed, survey 35-
Khatha, survey 35-
RTC, survey 35-
Mutation, survey 35-
Encumbrance Certificate, survey 35-
Conversion/Alienation Order, survey 35-
Sale/Title/Gift Deed, survey 35-
JDA, survey 35-
Khatha, survey 35-
RTC, survey 35-
Mutation, survey 35-
Encumbrance Certificate, survey 35-
Conversion/Alienation Order, survey 35-
Sale/Title/Gift Deed, survey 35-
JDA, survey 35-
Khatha, survey 35-
RTC, survey 35-
Mutation, survey 35-
Encumbrance Certificate, survey 35-
Conversion/Alienation Order, survey 35-
Sale/Title/Gift Deed, survey 35-
JDA, survey 35-
Khatha, survey 35-
Registration CertificateFile: INCORPORATION CERTIFICATE.pdf-
Organization StructureFile: Organisation Structure.pdf-
Certificate issued by CA Form 1File: Modification Form-4 CA.pdf-
Certificate issued by Architect Form 2File: Modification Form-5 Architect.pdf-
Certificate issued by Engineer Form 3File: Modification Form-6 Engineer.pdf-
TDR Purchase Deed / Sale DeedFile: tdr purchase deeds.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: Non Litigation Affidavit.pdf-
Certificate from Chartered AccountFile: Modification Form-4 CA.pdf-
Certificate from Chartered AccountFile: Modification Form-4 CA.pdf-
Balance Sheet 2022 - 2023File: Balance Sheet FY-22-23.pdf-
Balance Sheet 2021 - 2022File: Balance Sheet-2021-22.pdf-
Balance Sheet 2020 - 2021File: Audited Balance Sheet 2020-21.pdf-

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 under way, not due yet
ProjectLocationStatusPromisedDelivered
SNN Raj SerenitySy No, 40/1, 40/2, 40/3, 40/4. 40/5,40/6, 49/1, 49/2, 41/1, 41/2, 41/3,41/4, 41/7, 42/5 SNN RAJ SERENITY,YELENAHALLI VILLAGE , BEGUR HOBLI BENGALURU SOUTH TALUK,BENGALURU URBAN DISTRICT KARNATAKA 560068OngoingOct 2027Not due yet

How this compares with Bengaluru Urban

61%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep SNN ESTATES FELICITY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: SNN Builders Private Limited

SNN Builders Private Limited has 2 registrations on RERA Karnataka, including SNN ESTATES FELICITY and SNN RAJ SERENITY. Its filings declare 1 earlier project, none of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if SNN ESTATES FELICITY is delayed beyond 31 Dec 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of SNN ESTATES FELICITY?

The registered promoter entity is SNN Builders Private Limited, a company as per the filing. Its CIN U45202KA2009PTC051411 and GSTIN 29AANCS6172K1ZL can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in SNN ESTATES FELICITY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against SNN ESTATES FELICITY?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at SNN ESTATES FELICITY?

The professionals named in the filing: Architect: Gouri Mohan Upasani; Engineer: HP Yogesh; Chartered Accountant: Ramakrishna Kamat. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SNN ESTATES FELICITY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SNN ESTATES FELICITY. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SNN ESTATES FELICITY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.