Home / Browse projects / Bengaluru Urban, Karnataka / SKAV SILVER CLOUD
SKAV SILVER CLOUD
RG-KA-07460 · RERA PRM/KA/RERA/1251/309/PR/190829/002830
Source: official RERA Karnataka filing
Red flags
- Completion date moved by 9 months
- 1 extension taken
Clear
- No complaints on record
- Separate project account declared
Saved.
SKAV SILVER CLOUD is a Commercial project by MOUDGALYA CONSTRUCTION in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/309/PR/190829/002830 on 29 Aug 2019. Possession is promised by 1 Nov 2024. The completion date has moved by 9 months from the original filing.
At a glance
Project
- NameSKAV SILVER CLOUD
- TypeCommercial
- Location
- Bengaluru North
- Bengaluru Urban
- PincodeNot stated
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1251/309/PR/190829/002830
- ReraGenie IDRG-KA-07460
Builder
- NameMOUDGALYA CONSTRUCTION
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on29 Aug 2019
- Promised completion1 Nov 2024
- Revised completionRevised to 1 Nov 2024 (originally 1 Feb 2024)
- Buildings1 building record
- Documents filed38 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SKAV SILVER CLOUD | - | - | - | 0 | 9 | 9 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building:
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Retaining wall (All types) | - |
| Plinth level Beam | - |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | - |
| RCC or MS Framed structure | - |
| Masonry construction: Bricks, Concrete blocks etc | - |
| Plastering inside , outside & Ceiling | - |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Fire prevention and fire fighting fitting and fixture with network | - |
| Weather Proof work(tile,concrete) | - |
| Painting | - |
| Elevation work | - |
| Internal and External work including landscapes as per santioned drawings | - |
Progress on shared amenities42
Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Internal Roads & Footpaths | No | Not applicable |
| Sewage and Drainage System | Yes | - |
| Parks & Tree planting | No | Not applicable |
| Street Lighting | Yes | - |
| Provision for community buildings and for treatment and disposal of sewage and sullage water | Yes | - |
| Solid waste management and disposal | Yes | - |
| Water conservation | Yes | - |
| Energy management | Yes | - |
| Fire protection and fire safety requirements | Yes | - |
| Education/Health/Other public amenities | No | Not applicable |
| Electricity supply transformer and substation | No | Not applicable |
| Emergency Evacuation services | No | Not applicable |
| Storm water drains | No | Not applicable |
| Use of renewable energy | No | Not applicable |
| Water conservation/rain water harvesting/recharge of ground water | No | Not applicable |
| Electricity | Yes | - |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | - |
| Club House | No | Not applicable |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | No | Not applicable |
| Gym | No | Not applicable |
| Parks | No | Not applicable |
| Power Backup | Yes | - |
| Gas | No | Not applicable |
| Water and Sanitation | Yes | - |
| Air Conditioning And incerntion | No | Not applicable |
| Air Conditioning Provision | Yes | - |
| Staircases | Yes | - |
| Lifts | Yes | - |
| Staircases and Lift lobbies, corridor,lobbies, corridor | Yes | - |
| Fire escapes | Yes | - |
| Common entrance and exit for the building / common portico/foyer/verandah | Yes | - |
| Basement | Yes | - |
| Terrace | Yes | - |
| Outer Wall | Yes | - |
| Open parking areas and common storage spaces | Yes | - |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | Yes | - |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | KABIR HIRA |
| Engineer | ARUN RAO |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
No reason recorded in the filing
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed38
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/309/PR/190829/002830 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Spectrapack building licence | - |
| BUILDING PLANS SACTION | - |
| Plan approved BBMP | - |
| Sale Deed Spec | - |
| MYSCAN_20180911_0003-min | - |
| p01 | - |
| p01 | - |
| ec | - |
| Affidavit | - |
| JD AFFIDAVIT CUM DECLARATION | - |
| khata | - |
| Spectra JDA | - |
| Sale Deed Spec | - |
| land conversion | - |
| Fire NOC | - |
| Airports Authority Of India | - |
| BESCOM NOC | - |
| BWSSB NOC | - |
| KSPCB | - |
| SPECTRAPACK -CITB LETTERS | - |
| p02 | - |
| p02 | - |
| p03 | - |
| Balance Sheet 2017 - 2018File: 17-18 B.jpg | - |
| Balance Sheet 2016 - 2017File: 17-18 B.jpg | - |
| Balance Sheet 2015 - 2016File: 16-17 B.jpg | - |
| Audited Profit and Loss Statement 2017 - 2018File: 17-18 C.jpg | - |
| Audited Profit and Loss Statement 2016 - 2017File: 17-18 C.jpg | - |
| Audited Profit and Loss Statement 2015 - 2016File: 16-17 C.jpg | - |
| Income Tax Return Acknowledgement 2017 - 2018File: 17-18 A.jpg | - |
| Income Tax Return Acknowledgement 2016 - 2017File: 17-18 A.jpg | - |
| Income Tax Return Acknowledgement 2015 - 2016File: 16-17 A.jpg | - |
| affidavit for moudgalya | - |
| Tower Excel SheetFile: PRM_KA_RERA_1251_309_PR_190829_002830.xlsx | - |
| Occupancy CertificateFile: Skav Silver Cloud OC 28-10-2024.pdf | - |
| Completion certificate issued by the competent authorityFile: Skav Silver Cloud OC 28-10-2024.pdf | - |
| Registered Agreement of SaleFile: Skav Silver Cloud OC 28-10-2024.pdf | - |
| Registered conveyance deed for an individual unitFile: Skav Silver Cloud OC 28-10-2024.pdf | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep SKAV SILVER CLOUD on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Filed coordinates, straight-line distance. 19 registered projects within 2 km.
Prestige Park Grove
PRESTIGE PROJECTS PRIVATE LIMITED
Prestige Lakeside Habitat
Prestige Habitat Ventures
LivingTree by Kalyani Developers
Kalyani Tech Park Private Limited
PRESTIGE FALCON CITY
PRESTIGE NOTTINGHILL INVESTMENTS
SATTVA CITY
SATTVA CITY PRIVATE LIMITED
GM AMBITIOUS ENCLAVE
M/s. Allam Infinite India Private Limited
See every Bengaluru Urban project, with the district possession charts
Builder: MOUDGALYA CONSTRUCTION
MOUDGALYA CONSTRUCTION has 1 registration on RERA Karnataka, including SKAV SILVER CLOUD. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if SKAV SILVER CLOUD is delayed beyond 1 Nov 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of SKAV SILVER CLOUD?
The registered promoter entity is MOUDGALYA CONSTRUCTION. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in SKAV SILVER CLOUD?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at SKAV SILVER CLOUD?
The professionals named in the filing: Architect: KABIR HIRA; Engineer: ARUN RAO. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SKAV SILVER CLOUD?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback