Home / Browse projects / Thane, Maharashtra / Silver Spring
Silver Spring
By Anudan Properties Private Limited
RG-MH-50104 · RERA P51700008397 · Last updated on MahaRERA portal: 30 Jan 2020
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 46 months past the filed date
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Silver Spring is a Others project by Anudan Properties Private Limited in Thane, Maharashtra, registered with MahaRERA as P51700008397 on 18 Aug 2017. Possession was promised by 30 Dec 2022 and is now 46 months past that date.
At a glance
Project
- NameSilver Spring
- TypeOthers
- Location
- ESIC Road
- Nitin Company Junction
- Thane (M Corp.)
- Thane
- 400604
- Pincode400604
- RERA no.P51700008397
- ReraGenie IDRG-MH-50104
Builder
- NameAnudan Properties Private Limited
- Entity typeCompany
- DirectorsAjay Amarchand Munot, Madhusudana Kalagarla Rao
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on18 Aug 2017
- Promised completion30 Dec 2022
- Revised completionNone
- Buildings5 building records
- Documents filed39 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| BLDG S1 | NA | 27 | 0 | 0 | 0 | 0 |
| BLDG S2 | NA | 27 | 0 | 0 | 0 | 0 |
| BLDG S3 | NA | 24 | 0 | 0 | 0 | 0 |
| REHAB - 1 | NA | 25 | 0 | 0 | 0 | 0 |
| REHAB -2 | NA | 23 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building5
As on 30 Jan 2020, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
19 of 55 construction stages are filed complete across 5 buildings. The stage furthest along is Basement (if any), at 80%.
BLDG S116%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 40% |
| Podiums (if any) | 1% |
| Plinth | 40% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BLDG S229%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 80% |
| Podiums (if any) | 1% |
| Plinth | 80% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 53% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 7% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BLDG S327%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 1% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
REHAB - 145%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 1% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 54% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 7% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 30% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
REHAB -291%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 1% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities16
As on 30 Jan 2020, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 20% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 70% |
| Storm Water Drains | Yes | 40% |
| Landscaping & Tree Planting | Yes | 10% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 25% |
| Solid Waste Management And Disposal | Yes | 10% |
| Water conservation /Rain water harvesting | Yes | 25% |
| Energy managemcnt | Yes | 10% |
| Fire protection and fire safety requirements | Yes | 20% |
| Electrical meter room, sub-station, receiving station | Yes | 37% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
| CLUB HOUSE OF 2 FLOORS FITNESS CENTRES SWIMMING POOL | Yes | 5% |
Parking filed376
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| BLDG S1 | 90 | 90 |
| BLDG S2 | 175 | 175 |
| BLDG S3 | 91 | 91 |
| REHAB - 1 | 8 | 8 |
| REHAB -2 | 12 | 12 |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | YOGESH N KELKAR & ASSOCIATES |
| Engineer | Shravani Consultants |
| Chartered Accountant | SANKET R SHAH & ASSOCIATES |
| Chartered Accountant | JAYAWANT DESAI & CO |
| Partner | Role in project |
|---|---|
| Anudan Properties Private Limited | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 30 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 10 Jun 2019 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 30 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 30 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 30 Jan 2020
Documents filed39
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certifate (2nd for Sep-17).pdf | 30 Jan 2020 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Engineer Certificate as on 31st March-18.pdf | 30 Jan 2020 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate -Mar 19.pdf | 30 Jan 2020 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate June-19.pdf | 30 Jan 2020 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certaficate Dec-2019.pdf | 30 Jan 2020 |
| Certificates of CA (Form 3)File: CA Certificate Dec 19.pdf | 30 Jan 2020 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: R-2 Bldg Full Occupation Certificate.pdf | 30 Jan 2020 |
| Certificates of CA (Form 5)File: CA Form 5.pdf | 30 Sep 2019 |
| Certificates of CA (Form 5)File: CA Form 5.pdf | 30 Sep 2019 |
| Layout approvalFile: layout Plan.pdf | 10 Jun 2019 |
| Layout approvalFile: layout Plan.pdf | 10 Jun 2019 |
| Copy of Layout Approval (in case of layout)File: layout Plan.pdf | 10 Jun 2019 |
| Copy of Layout Approval (in case of layout)File: layout Plan.pdf | 10 Jun 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architech Certificate- Dec-18.pdf | 10 Jun 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architech Certificate- Dec-18.pdf | 10 Jun 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Dec-18.pdf | 10 Jun 2019 |
| Certificates of CA (Form 3)File: CA Certificate-dec-18.pdf | 10 Jun 2019 |
| Certificates of CA (Form 3)File: CA Certificate FORM-III3.pdf | 23 Oct 2018 |
| Certificates of CA (Form 5)File: Form-5.pdf | 15 Oct 2018 |
| Layout approvalFile: 4) Layout Plan.pdf | 30 Jul 2017 |
| Layout approvalFile: Lay out op 2-Model.pdf | 30 Jul 2017 |
| Building plan approvalFile: 9) Sanction of Development (CC)040510.pdf | 30 Jul 2017 |
| Building plan approvalFile: CC2.pdf | 30 Jul 2017 |
| PAN CardFile: 1) Anudan Properties Pancard PDF.pdf | 30 Jul 2017 |
| Copy of the legal title reportFile: 2) Title Certificate.pdf | 30 Jul 2017 |
| Details of encumbrancesFile: 3)Encumbrance Certificate.pdf | 30 Jul 2017 |
| Details of encumbrancesFile: Mortgage Deed LICHFL (Index-2).pdf | 30 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: 4) Layout Plan.pdf | 30 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: Lay out op 2-Model.pdf | 30 Jul 2017 |
| Building Plan Approval (IOD)File: 9) Sanction of Development (CC)040510.pdf | 30 Jul 2017 |
| Building Plan Approval (IOD)File: CC2.pdf | 30 Jul 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: CC1.pdf | 30 Jul 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: CC2.pdf | 30 Jul 2017 |
| Declaration in FORM BFile: 6)From 'B' (Affidavit cum Declaration).pdf | 30 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 7)Architect Certificate.pdf | 30 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate 1.pdf | 30 Jul 2017 |
| Certificates of CA (Form 3)File: 8) CA Certificate - Silver Spring.pdf | 30 Jul 2017 |
| Proforma of Allotment letterFile: 5) Allotment letter.pdf | 30 Jul 2017 |
| Proforma of Allotment letterFile: 5) Agreement For sale.pdf | 30 Jul 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- All 39 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep Silver Spring on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Nitin Company Junction7,600+ in Thane
Dosti 604
Dosti Corporation Business Park
ONE ARTHASYA
TOP FLOOR REALTY LLP
ASHAR MERAC PHASE I
AJAY PRATAP ASHAR
EMPERIA I PARK
MANOMETER (INDIA) LLP
Ace Signature IT Park
Yojit Builder
O22 Business Park
MIDAS TOUCH
See every Thane project, with the district possession charts
Builder: Anudan Properties Private Limited
Anudan Properties Private Limited has 1 registration on MahaRERA, including Silver Spring. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What does it mean that Silver Spring shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Silver Spring is delayed beyond 30 Dec 2022?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Silver Spring?
The registered promoter entity is Anudan Properties Private Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Silver Spring?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Silver Spring?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Silver Spring?
The professionals named in the filing: Architect: YOGESH N KELKAR & ASSOCIATES; Engineer: Shravani Consultants; Chartered Accountant: SANKET R SHAH & ASSOCIATES; Chartered Accountant: JAYAWANT DESAI & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Silver Spring?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback