RG-KA-03809 · RERA PRM/KA/RERA/1251/308/PR/200604/003449 · Last updated on RERA Karnataka portal: 2 Jun 2020

Source: official RERA Karnataka filing

Red flags

  • 2 complaints at RERA Karnataka
  • Completion date moved by 9 months
  • 1 extension taken

Clear

  • Separate project account declared
May 2023Possession promisedmoved 9 months from the original
2Complaints at RERA Karnatakaon this registration
Jump to the 73 documents Report an error

SIGNATURE CREST is a Residential/Group Housing project by Signature Dwellings Private Limited in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/308/PR/200604/003449 on 4 Jun 2020. Possession is promised by 25 May 2023. The completion date has moved by 9 months from the original filing. 2 complaints are on record with the regulator.

At a glance

Project

  • NameSIGNATURE CREST
  • TypeResidential/Group Housing
  • Location
    • Anekal
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/308/PR/200604/003449
  • ReraGenie IDRG-KA-03809

Builder

  • NameSignature Dwellings Private Limited
  • Entity typeCompany
  • CINU70200KL2012PTC030293
  • Authorized SignatoryPrasanth Narayanan
  • DirectorPrasanth Narayanan
  • Other registrations9 more →
  • Declared earlier projects6 →

Key dates

this monthRegisteredJun 2020First promiseAug 2022Revised toMay 2023

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on4 Jun 2020
  • Promised completion25 May 2023
  • Revised completionRevised to 25 May 2023 (originally 25 Aug 2022)
  • Buildings1 building record
  • Documents filed73 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Signature Crest---1200120

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 2 Jun 2020, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)Not applicable
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)Not applicable
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities42

As on 2 Jun 2020, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsYes-
Sewage and Drainage SystemYes-
Parks & Tree plantingYes-
Street LightingYes-
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes-
Solid waste management and disposalYes-
Water conservationNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesYes-
Electricity supply transformer and substationYes-
Emergency Evacuation servicesNoNot applicable
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationYes-
CCTV SurveillanceYes-
Club HouseYes-
Community HallYes-
Outdoor Sports facilityYes-
Indoor Sports facilityYes-
Swimming PoolYes-
GymYes-
ParksYes-
Power BackupYes-
GasNoNot applicable
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesNoNot applicable
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementNoNot applicable
TerraceNoNot applicable
Outer WallYes-
Open parking areas and common storage spacesNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes-
Stilt FloorYes-

Land and ownership2

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,008 sq m
Named landowners2
LandownerVillageDistrict
K.Narayana--
Babu Reddy--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 17.20 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRamesha DB, Landmark Architects and Engineers
EngineerG.Praveen Kumar, ECO Consultants

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionAug 2022 → May 2023

No reason recorded in the filing

Complaints filed with RERA Karnataka2

Case no.ComplainantRespondentFiled
CMP/220408/0009335-Signature Dwellings Private Limited08/04/2022
01380/2023-Signature Dwellings Private Limited09/09/2023

Documents filed73

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/308/PR/200604/003449 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
17-18 Cash Flow and Director StatementFile: 17-18 Cash Flow and Director Statement.pdf2 Jun 2020
Auditors Report FY 19-20File: Auditors Report FY 19-20.pdf2 Jun 2020
Balance sheet Cash Flow Director report and Financial Statement FY 19-20File: Balance sheet Cash Flow Director report and Financial Statement FY 19-20.pdf2 Jun 2020
Cash Flow and Balance sheet FY 18-19File: Cash Flow and Balance sheet FY 18-19.pdf2 Jun 2020
Director and Audit Report FY 18-19File: Director and Audit Report FY 18-19.pdf2 Jun 2020
CertificateFile: Certificate of Incorporation.pdf-
Commencement Certificate-
GF plan-
Site plan-
GPA-
Sale Deeds in the name of Narayan and Gift Deed in the name of Babu Redddy-
First Second and Third Floor Plan-
First Second and Third Floor Plan-
Project Specifications-
Encumbrance Certificate - Till date-
Affidavit-
Joint Affidavit Land Owners and Builder-
RTC MR and Khatha-
JDA-
RELINQUISHMENT DEED SIGNATURE CREST-
Conversion Order-
Unnamed document-
Water NOC-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
BESCOM - NOC-
Unnamed document-
Karnataka State Pollution Control Board-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Signature Crest- sharing agreement-
First Second and Third Floor Plan-
Unnamed document-
Balance Sheet 2018 - 2019File: Signature Dwellings _AY2019-20_ITR V.pdf-
Balance Sheet 2017 - 2018File: Balance Sheet.pdf-
Balance Sheet 2016 - 2017File: Balance Sheet.pdf-
Audited Profit and Loss Statement 2018 - 2019File: Signature Dwellings _AY2019-20_ITR V.pdf-
Audited Profit and Loss Statement 2017 - 2018File: P and L.pdf-
Audited Profit and Loss Statement 2016 - 2017File: Profit and Loss.pdf-
Director's Report 2018 - 2019File: Signature Dwellings _AY2019-20_ITR V.pdf-
Director's Report 2017 - 2018File: Audit Report.pdf-
Director's Report 2016 - 2017File: Auditor Report.pdf-
Cash Flow Statement 2018 - 2019File: Signature Dwellings _AY2019-20_ITR V.pdf-
Cash Flow Statement 2017 - 2018File: Financial Statement.pdf-
Auditor's Report 2018 - 2019File: Signature Dwellings _AY2019-20_ITR V.pdf-
Auditor's Report 2017 - 2018File: Audit report.pdf-
Auditor's Report 2016 - 2017File: Auditor Report.pdf-
Income Tax Return Acknowledgement 2018 - 2019File: Signature Dwellings _AY2019-20_ITR V.pdf-
Income Tax Return Acknowledgement 2017 - 2018File: Signature Dwellings ITR-V AY 2018-19.pdf-
Income Tax Return Acknowledgement 2016 - 2017File: IT Ack.pdf-
Form - B-
Prospectus/BrochureFile: Brouchure.pdf-
Advertisement Copy 1File: 99acres.png-
Tower Excel SheetFile: PRM_KA_RERA_1251_308_PR_200604_003449.xlsx-
Occupancy CertificateFile: Signature Crest OC.pdf-
Certificate of operation for lifts issued by the Chief of Department of Electrical inspectorate Government of File: BESCOM NOC.pdf-
Sanctioned Letter issued by concerned ESCOM of Power sanction and details of transformer installed and whetherFile: BESCOM NOC.pdf-
Sanctioned letter issued by concerned water supply and sanitary board for the projectFile: Water NOC.pdf-
Architect certificate for having completed the work(in format no 5)File: Form-5__Architect_-_Completion.pdf-
Chartered Accountant certificate for having completed the work(in format no 4)File: form4_c_c_Completion-2.pdf-
Affidavit cum declaration from promoter for having completed the project as per specification and as per adverFile: Crest Completion for Affidavit.pdf-

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
Signature Classic-Completed-No date filed

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one moved by 9 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep SIGNATURE CREST on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: Signature Dwellings Private Limited

SIGNATURE DWELLINGS PRIVATE LIMITED has 10 registrations on RERA Karnataka, including SIGNATURE REGAL and SIGNATURE PREMIER. Its filings declare 6 earlier projects, 3 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if SIGNATURE CREST is delayed beyond 25 May 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of SIGNATURE CREST?

The registered promoter entity is Signature Dwellings Private Limited, a company as per the filing. Its CIN U70200KL2012PTC030293 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in SIGNATURE CREST?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against SIGNATURE CREST?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at SIGNATURE CREST?

The professionals named in the filing: Architect: Ramesha DB, Landmark Architects and Engineers; Engineer: G.Praveen Kumar, ECO Consultants. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SIGNATURE CREST?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SIGNATURE CREST. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SIGNATURE CREST to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.