Home / Browse projects / Bengaluru Urban, Karnataka / SHRIRAM SUVILAS GARDEN OF JOY
SHRIRAM SUVILAS GARDEN OF JOY
By SUVILAS PROPERTIES PRIVATE LIMITED
RG-KA-11727 · RERA PRM/KA/RERA/1251/309/PR/180227/001096 · Last updated on RERA Karnataka portal: 25 Jan 2021
Source: official RERA Karnataka filing
Red flags
- Registration transferred
- 12 complaints at RERA Karnataka
- Completion date moved by 18 months
- 2 extensions taken
Clear
- Separate project account declared
Saved.
SHRIRAM SUVILAS GARDEN OF JOY is a Residential/Group Housing project by SUVILAS PROPERTIES PRIVATE LIMITED in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/309/PR/180227/001096 on 27 Feb 2018. Possession is promised by 1 Jan 2022. The completion date has moved by 18 months from the original filing. 12 complaints are on record with the regulator.
At a glance
Project
- NameSHRIRAM SUVILAS GARDEN OF JOY
- TypeResidential/Group Housing
- Location
- Bengaluru North
- Bengaluru Urban
- PincodeNot stated
- RERA no.PRM/KA/RERA/1251/309/PR/180227/001096
- ReraGenie IDRG-KA-11727
Builder
- NameSUVILAS PROPERTIES PRIVATE LIMITED
- Entity typeCompany
- CINU70102KA2012PTC062139
- Authorized SignatorySUNIL CHOWDARY
- DirectorsSUNIL CHOWDARY, M N UMESH, C R SURESH
Key dates
Key facts
Registration and timeline
- StatusRegistration transferred
- Registered on27 Feb 2018
- Promised completion1 Jan 2022
- Revised completionRevised to 1 Jan 2022 (originally 1 Jul 2020)
- Buildings2 building records
- Documents filed69 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Block1 | - | - | - | 76 | 0 | 76 |
| Block2 | - | - | - | 76 | 0 | 76 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 25 Jan 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building:
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Retaining wall (All types) | - |
| Plinth level Beam | Not applicable |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | - |
| RCC or MS Framed structure | - |
| Masonry construction: Bricks, Concrete blocks etc | - |
| Plastering inside , outside & Ceiling | - |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Fire prevention and fire fighting fitting and fixture with network | Not applicable |
| Weather Proof work(tile,concrete) | - |
| Painting | - |
| Elevation work | - |
| Internal and External work including landscapes as per santioned drawings | - |
Progress on shared amenities41
As on 25 Jan 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Internal Roads & Footpaths | No | Not applicable |
| Sewage and Drainage System | Yes | - |
| Parks & Tree planting | Yes | - |
| Street Lighting | Yes | - |
| Provision for community buildings and for treatment and disposal of sewage and sullage water | Yes | - |
| Solid waste management and disposal | Yes | - |
| Water conservation | Yes | - |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Education/Health/Other public amenities | Yes | - |
| Electricity supply transformer and substation | Yes | - |
| Emergency Evacuation services | No | Not applicable |
| Storm water drains | Yes | - |
| Use of renewable energy | Yes | - |
| Water conservation/rain water harvesting/recharge of ground water | Yes | - |
| Electricity | Yes | - |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | No | Not applicable |
| Club House | Yes | - |
| Community Hall | Yes | - |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | Yes | - |
| Swimming Pool | Yes | - |
| Gym | Yes | - |
| Parks | Yes | - |
| Power Backup | Yes | - |
| Gas | No | Not applicable |
| Water and Sanitation | Yes | - |
| Air Conditioning And incerntion | No | Not applicable |
| Staircases | Yes | - |
| Lifts | Yes | - |
| Staircases and Lift lobbies, corridor,lobbies, corridor | Yes | - |
| Fire escapes | Yes | - |
| Common entrance and exit for the building / common portico/foyer/verandah | Yes | - |
| Basement | Yes | - |
| Terrace | Yes | - |
| Outer Wall | Yes | - |
| Open parking areas and common storage spaces | Yes | - |
| Provision for lodging of management staff and security staff | Yes | - |
| Water conservation and renewable energy | Yes | - |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | DESIGN DESK ( RAVI JOHN) |
| Engineer | MANOHAR CONSULTANTS ( N MANOHAR) |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
No reason recorded in the filing
Reason as filed by the promoterDelay in getting loan
Complaints filed with RERA Karnataka12
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CMP/220223/0009046 | - | SUVILAS PROPERTIES PRIVATE LIMITED | 23/02/2022 |
| CMP/220516/0009461 | - | SUVILAS PROPERTIES PRIVATE LIMITED | 16/05/2022 |
| CMP/220623/0009670 | - | SUVILAS PROPERTIES PRIVATE LIMITED | 23/06/2022 |
| CMP/220903/0009974 | - | SUVILAS PROPERTIES PRIVATE LIMITED | 03/09/2022 |
| CMP/221029/0010151 | - | SUVILAS PROPERTIES PRIVATE LIMITED | 29/10/2022 |
| CMP/221102/0010156 | - | SUVILAS PROPERTIES PRIVATE LIMITED | 02/11/2022 |
| CMP/221115/0010339 | - | SUVILAS PROPERTIES PRIVATE LIMITED | 15/11/2022 |
| CMP/221125/0010404 | - | SUVILAS PROPERTIES PRIVATE LIMITED | 25/11/2022 |
| 00050/2023 | - | SUVILAS PROPERTIES PRIVATE LIMITED | 10/01/2023 |
| 00101/2023 | - | SUVILAS PROPERTIES PRIVATE LIMITED | 19/01/2023 |
| 00148/2023 | - | SUVILAS PROPERTIES PRIVATE LIMITED | 01/02/2023 |
| 00153/2023 | - | SUVILAS PROPERTIES PRIVATE LIMITED | 02/02/2023 |
Documents filed69
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/309/PR/180227/001096 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Kotak Bank StatementFile: Kotak Bank Statement 01042019 To 31032020.pdf | 25 Jan 2021 |
| Kotak Bank StatementFile: Kotak Bank Statement 01042020 To 25012020.pdf | 25 Jan 2021 |
| CA letter for ExtensionFile: CA letter for Extension.pdf | 25 Jan 2021 |
| Form Ex 3File: Form Ex 3.pdf | 25 Jan 2021 |
| Form Ex 4File: Form Ex 4.pdf | 25 Jan 2021 |
| REPLY LETTERFile: reply letter for RERA extenstion queries.pdf | 28 Dec 2020 |
| CA CERTIFICATE FOR DESIGNATED BANK ACCOUNT AS PER PORTALFile: CA certificate.pdf | 28 Dec 2020 |
| CA CERTIFICATE FOR RECENT BANK ACCOUNT CHANGE REQUESTFile: CA Certificate.pdf | 28 Dec 2020 |
| COVID -19 EXTENSTION CERTIFICATEFile: Covid extenstion certificate upto 1-1-21.pdf | 28 Dec 2020 |
| NOTORISED AFFIDAVITFile: Form Ex-7 affidavit.pdf | 28 Dec 2020 |
| COMMENCEMENT CERTIFICATEFile: SRG - Commencement Certificate .pdf | 28 Dec 2020 |
| CONSENT LETTERSFile: Consent Letters-signed.pdf | 28 Dec 2020 |
| BANK STATEMENT AS PER RERA PORTALFile: kotak statement-3 months.pdf | 28 Dec 2020 |
| BANK STATEMENT AS PER BANK ACCOUNT CHANGE REQUESTFile: HDFC Bank statement-3 months.pdf | 28 Dec 2020 |
| CertificateFile: Incorporation Certificate - Suvilas Properties Private Limited.pdf | - |
| Architect Certificate for Work Completion Schedule till DateFile: Form Ex-1.pdf | - |
| Engineer Certificate for Work Completion Schedule till DateFile: Form Ex-5.pdf | - |
| CA Certificate for Funds UtilizationFile: Form Ex-3.pdf | - |
| Architect Certificate for Pending Work Completion Schedule.File: Form Ex-2.pdf | - |
| Engineer Certificate for Pending Work Completion Schedule.File: Form Ex-6.pdf | - |
| CA Certificate for Funds required for Project CompletionFile: Form Ex-4.pdf | - |
| AffidavitFile: Form Ex-7 affidavit.pdf | - |
| Latest Encumbrance CertificateFile: EC latest 2020_compressed pages.pdf | - |
| Details Of Sold/ Un-sold UnitsFile: SoldUnsoldDetails.xlsx | - |
| Document 1File: Form B.pdf | - |
| Commencement Certificate - Suvilas Royal Gardenia,15-2 | - |
| Approved Building | - |
| Approved Layout Plan | - |
| Proforma For Sale Deed | - |
| Proforma for Sale of Agreement | - |
| Land documents & Location | - |
| Approved Section Of Building | - |
| Area Development Plan Of Project Area | - |
| Proforma of Allotment Letter | - |
| SRG E Book | - |
| All NOCs from Authority | - |
| Project Specification | - |
| EC Suvilas Royal Gardenia | - |
| Khata & Khata Extract | - |
| Sale Deed | - |
| SRG - Conversion order | - |
| SRG - Fire Force | - |
| SRG- AAI NOC -NEW | - |
| SRG - BESCOM | - |
| SRG - BWSSB | - |
| SRG - KSPCB | - |
| SRG - SEIAA | - |
| SRG - BSNL | - |
| Balance Sheet 2015 - 2016File: Balancesheet.pdf | - |
| Balance Sheet 2014 - 2015File: Balancesheet.pdf | - |
| Balance Sheet 2013 - 2014File: Balancesheet.pdf | - |
| Audited Profit and Loss Statement 2015 - 2016File: P & L.pdf | - |
| Audited Profit and Loss Statement 2014 - 2015File: P & L.pdf | - |
| Audited Profit and Loss Statement 2013 - 2014File: Profit and Loss Account.pdf | - |
| Director's Report 2015 - 2016File: Director Report .pdf | - |
| Director's Report 2014 - 2015File: Directors report.pdf | - |
| Director's Report 2013 - 2014File: Directors Report.pdf | - |
| Cash Flow Statement 2015 - 2016File: cash flow.pdf | - |
| Cash Flow Statement 2014 - 2015File: Cash flow Statement.pdf | - |
| Auditor's Report 2015 - 2016File: Audit report.pdf | - |
| Auditor's Report 2014 - 2015File: Audit_Report.pdf | - |
| Auditor's Report 2013 - 2014File: Audit Report.pdf | - |
| Income Tax Return Acknowledgement 2015 - 2016File: ITR V.pdf | - |
| Income Tax Return Acknowledgement 2014 - 2015File: ITR V.pdf | - |
| Income Tax Return Acknowledgement 2013 - 2014File: ITR V.pdf | - |
| Form B -RERA | - |
| Prospectus/BrochureFile: SUVILA'S BROCHURE Final.pdf | - |
| Advertisement Copy 1File: SUVILA'S BROCHURE Final.pdf | - |
| Tower Excel SheetFile: PRM_KA_RERA_1251_309_PR180227_001096-2-1-2.xlsx | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep SHRIRAM SUVILAS GARDEN OF JOY on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Prestige Park Grove
PRESTIGE PROJECTS PRIVATE LIMITED
Prestige Lakeside Habitat
Prestige Habitat Ventures
LivingTree by Kalyani Developers
Kalyani Tech Park Private Limited
PRESTIGE FALCON CITY
PRESTIGE NOTTINGHILL INVESTMENTS
SATTVA CITY
SATTVA CITY PRIVATE LIMITED
GM AMBITIOUS ENCLAVE
M/s. Allam Infinite India Private Limited
See every Bengaluru Urban project, with the district possession charts
Builder: SUVILAS PROPERTIES PRIVATE LIMITED
SUVILAS PROPERTIES PRIVATE LIMITED has 1 registration on RERA Karnataka, including SHRIRAM SUVILAS GARDEN OF JOY. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if SHRIRAM SUVILAS GARDEN OF JOY is delayed beyond 1 Jan 2022?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of SHRIRAM SUVILAS GARDEN OF JOY?
The registered promoter entity is SUVILAS PROPERTIES PRIVATE LIMITED, a company as per the filing. Its CIN U70102KA2012PTC062139 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in SHRIRAM SUVILAS GARDEN OF JOY?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against SHRIRAM SUVILAS GARDEN OF JOY?
Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
Who certifies construction progress at SHRIRAM SUVILAS GARDEN OF JOY?
The professionals named in the filing: Architect: DESIGN DESK ( RAVI JOHN); Engineer: MANOHAR CONSULTANTS ( N MANOHAR). Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SHRIRAM SUVILAS GARDEN OF JOY?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback