Red flags

  • 3 complaints at RERA Karnataka
  • Completion date moved by 21 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
Oct 2026Possession promisedmoved 21 months from the original
18 of 18Construction stages doneevery applicable stage filed complete
0 of 75Units unsoldnot recorded sold or booked
3Complaints at RERA Karnatakaon this registration
Jump to the 137 documents Report an error

SHRIRAM SOUTHERN CREST - Phase -2 is a Residential/Group Housing project by SHRIPROP PROJECTS PRIVATE LIMITED in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/200310/003331 on 10 Mar 2020. Possession is promised by 21 Oct 2026. The completion date has moved by 21 months from the original filing. 75 of the 75 units on this registration are recorded sold or booked, and 18 of 18 construction stages are filed complete. 3 complaints are on record with the regulator.

At a glance

Project

  • NameSHRIRAM SOUTHERN CREST - Phase -2
  • TypeResidential/Group Housing
  • Location
    • Bengaluru South
    • Bengaluru Urban
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/310/PR/200310/003331
  • ReraGenie IDRG-KA-78393

Builder

  • NameSHRIPROP PROJECTS PRIVATE LIMITED
  • Entity typeCompany
  • CINU45202KA2008PTC046145
  • Authorized SignatoryK.R.RAMESH
  • OthersGOPINATHAN.M
  • Other registrations1 more →
  • Declared earlier projects2 →

Key dates

this monthRegisteredMar 2020First promiseJan 2025Revised toOct 2026

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on10 Mar 2020
  • Promised completion21 Oct 2026
  • Revised completionRevised to 21 Oct 2026 (originally 21 Jan 2025)
  • Buildings4 building records
  • Documents filed137 files

Current status

100%75 of 75 units booked
0.0%Of the estimated cost spent so far

Figures as on 14 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower A---808
Tower B---808
Tower C---808
Tower D---51051

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 14 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

18 of 18 construction stages are filed complete.

Building: 100% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Retaining wall (All types)100%
Plinth level Beam100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
RCC or MS Framed structure100%
Masonry construction: Bricks, Concrete blocks etc100%
Plastering inside , outside & Ceiling100%
Joinery: Doors, Windows, Ventilators etc100%
Basic work of Water supply, Sanitary and Electrification100%
Dadoing, Skirting, Flooring, Tiles work (All types)100%
Railing and Grill fixing100%
Electrification, Water supply and Sanitary Finishing100%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network100%
Weather Proof work(tile,concrete)100%
Painting100%
Elevation work100%
Internal and External work including landscapes as per santioned drawings100%

Progress on shared amenities41

As on 14 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes100%
Internal Roads & FootpathsYes100%
Sewage and Drainage SystemYes100%
Parks & Tree plantingYes100%
Street LightingYes100%
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes100%
Solid waste management and disposalYes100%
Water conservationYes100%
Energy managementYes100%
Fire protection and fire safety requirementsYes100%
Education/Health/Other public amenitiesYes100%
Electricity supply transformer and substationYes-
Emergency Evacuation servicesNoNot applicable
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterNoNot applicable
ElectricityYes100%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes100%
Club HouseYes100%
Community HallYes100%
Outdoor Sports facilityYes100%
Indoor Sports facilityYes100%
Swimming PoolYes100%
GymYes100%
ParksYes100%
Power BackupYes100%
GasNoNot applicable
Water and SanitationYes100%
Air Conditioning And incerntionNoNot applicable
StaircasesYes100%
LiftsYes100%
Staircases and Lift lobbies, corridor,lobbies, corridorYes100%
Fire escapesYes100%
Common entrance and exit for the building / common portico/foyer/verandahYes100%
BasementYes100%
TerraceYes100%
Outer WallYes100%
Open parking areas and common storage spacesYes100%
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes100%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area15,074 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 37.31 cr
Spent of the estimate0.0%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 26.36 cr-
Principal sum and interest payable to financial institutions-Non Banking financial institution (NBFC)Rs 6.00 cr-
Payment of taxesRs 4.95 cr-

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectCnT ARCHITECTS
EngineerINNOTECH ENGINEERING CONSULT PVT LTD

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionJan 2025 → Oct 2025

No reason recorded in the filing

EX/PRM/KA/RERA/1251/310/PR/260422/003331Oct 2025 → Oct 2026

Reason as filed by the promoterAwaiting OC

Complaints filed with RERA Karnataka3

Case no.ComplainantRespondentFiled
CMP/221112/0010254-SHRIPROP PROJECTS PRIVATE LIMITED12/11/2022
00125/2024-SHRIPROP PROJECTS PRIVATE LIMITED29/01/2024
00578/2025-SHRIPROP PROJECTS PRIVATE LIMITED03/04/2025

Documents filed137

As listed on the registration, under the names the promoter filed them with; the newest 80 of 137 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/200310/003331 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form-4-SC-Tower D-Sep-2026.pdf14 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form5 Architect QU Sourther crest P2 (1).pdf14 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form6 Engineer QU SC P2Q1 202627.pdf14 Oct 2026
Q2 2026-27 Water supply and sewage board14 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)14 Oct 2026
Q2 2026-27 KPTCL- BESCOM14 Oct 2026
Q2 2026-27 Fire and Safety14 Oct 2026
Q2 2026-27 Airport Authority of India14 Oct 2026
Q2 2026-27 BSNL/Telecommunication Department14 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form-4-SC-Tower D-June-2026.pdf9 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form5 Architect QU Sourther crest P2.pdf9 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form-6 Engineer (QU) SC P2-Q1 2026-27.pdf9 Jul 2026
Q1 2026-27 Water supply and sewage board9 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)9 Jul 2026
Q1 2026-27 KPTCL- BESCOM9 Jul 2026
Q1 2026-27 Fire and Safety9 Jul 2026
Q1 2026-27 Airport Authority of India9 Jul 2026
Q1 2026-27 BSNL/Telecommunication Department9 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form-4-SC-Tower D-March-2026K.pdf13 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form5 Architect QU Sourther crest P2.pdf13 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form-6 Engineer (QU) SC P2-Q4 2024-25.pdf13 Apr 2026
Q4 2025-26 Water supply and sewage board13 Apr 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)13 Apr 2026
Q4 2025-26 KPTCL- BESCOM13 Apr 2026
Q4 2025-26 Fire and Safety13 Apr 2026
Q4 2025-26 Airport Authority of India13 Apr 2026
Q4 2025-26 BSNL/Telecommunication Department13 Apr 2026
Engineering licenced certificateFile: Engineer-4-Self attested copy of Engineer License.pdf11 Mar 2026
Form-5 For work pendingFile: Form Ex5-Engg certificate - work Completed-Southern crest phase-2.pdf11 Mar 2026
Form-6 for work completionFile: Form Ex6- Engg certificate - work pending- Southern crest P-2.pdf11 Mar 2026
Latest ECFile: Latest Encumarance Certificate- Southern Crest Project.pdf11 Mar 2026
Reason letterFile: Reason Request Letter.pdf11 Mar 2026
Application for OCFile: OC Representation LETTER.pdf11 Mar 2026
Court orderFile: Certified copy of WP No 3132.pdf11 Mar 2026
List of sold & unsold unitFile: List of sold & unsold unit.pdf11 Mar 2026
List handing over certificateFile: Tower D - P2_Lift_Handing Over Certificate.pdf11 Mar 2026
Fire CCFile: New Fire Force Dept CC dated 19 May 2022 Southern .pdf11 Mar 2026
BESCOM NOCFile: NOC BESCOM dated 28 February 2022 Southern Crest.pdf11 Mar 2026
AAI NOCFile: NOC Airport Authority of India Shriram Southern .pdf11 Mar 2026
BSNL NOCFile: NOC BSNL VSS Property Project Seegehalli K R Puram.pdf11 Mar 2026
BMRCKL NOCFile: NOC For BMRCL.PDF11 Mar 2026
BWSSB NOCFile: NOC BWSSB dated 30 May 2018 WRT Modified Site Pla.pdf11 Mar 2026
CLERAFile: Shriram Southern Crest CLRA30122023.pdf11 Mar 2026
KSBCB NOCFile: NOC KSPCB dated 30 August 2018 CTE WRT to Modifie.pdf11 Mar 2026
Scantion planFile: Shriram Southern crest Sheet 01 Site Plan Modified dt 12 Dec 19 Southern Crest Temp00823.P11 Mar 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form4SCTower DSep2025.pdf19 Feb 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form5 Architect QU Sourther crest P2.pdf19 Feb 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form-6 Engineer (QU) SC P2-Q3 2024-25.pdf19 Feb 2026
Q3 2025-26 Water supply and sewage board19 Feb 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)19 Feb 2026
Q3 2025-26 KPTCL- BESCOM19 Feb 2026
Q3 2025-26 Fire and Safety19 Feb 2026
Q3 2025-26 Airport Authority of India19 Feb 2026
Q3 2025-26 BSNL/Telecommunication Department19 Feb 2026
ReplyFile: sc letter.pdf29 Feb 2020
NOC copiesFile: ENC-C- ALL NOC Southern Crest.pdf29 Feb 2020
Customer AgreementFile: A.00.06.pdf29 Feb 2020
Agreement copyFile: Agreement Copy.pdf12 Feb 2020
Project BriefFile: Project Brief.pdf12 Feb 2020
BMRCL LetterFile: BMRCL.PDF12 Feb 2020
Phase 1&2 PlansFile: SC Phase 1&2 Plan comp.pdf12 Feb 2020
Company registration certificateFile: ENC-1 REGISTRATION CERTIFICATE shriprop projects.pdf4 Feb 2020
Conversion order for Sy.No. 42/3AFile: Conversion Order reply.pdf4 Feb 2020
Form-BFile: Form B.pdf4 Feb 2020
EC till DateFile: EC.pdf4 Feb 2020
Duly debarked Sanctioned floor plan and sectionFile: SCp2 Plan explained.pdf4 Feb 2020
Architect Certificate for Work Completion Schedule till DateFile: Form Ex-1 Architect certificate Work pending-compressed.pdf-
Engineer Certificate for Work Completion Schedule till DateFile: Form Ex5-Engg certificate - work Completed-Southern crest phase-2.pdf-
CA Certificate for Funds UtilizationFile: CA certificate - fund utilized Shriram Southern Crest Phase-2 (Form EXT 3).pdf-
Architect Certificate for Pending Work Completion Schedule.File: Form Ex-2 Architect certificate Work pending-compressed.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: Form Ex6- Engg certificate - work pending- Southern crest P-2.pdf-
CA Certificate for Funds required for Project CompletionFile: CA certificate - funds required Shriram Southern Crest Phase-2 (Form Ext 4).pdf-
AffidavitFile: Form EX-7.pdf-
Latest Encumbrance CertificateFile: Latest EC.pdf-
Details Of Sold/ Un-sold UnitsFile: list.pdf-
ENC-B-2- CC Southern Crest-
ALL IN ONE DWG-
Sheet No 1 Site Plan Temp00823-
ENC-27 PROFORMA FOR SALE DEED Southern Crest RERA-
ENC-16 PROFORMA AGREEMENT FOR SALE-

How this compares with Bengaluru Urban

100%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one moved by 21 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep SHRIRAM SOUTHERN CREST - Phase -2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmSHRIRAM SOUTHERN CREST -Other 19Dot size: filed unitsN

Filed coordinates, straight-line distance. 19 registered projects within 2 km.

Builder: SHRIPROP PROJECTS PRIVATE LIMITED

SHRIPROP PROJECTS PRIVATE LIMITED has 2 registrations on RERA Karnataka, including SHRIRAM SOUTHERN CREST and SHRIRAM SOUTHERN CREST - Phase -2. Its filings declare 2 earlier projects, none of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if SHRIRAM SOUTHERN CREST - Phase -2 is delayed beyond 21 Oct 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of SHRIRAM SOUTHERN CREST - Phase -2?

The registered promoter entity is SHRIPROP PROJECTS PRIVATE LIMITED, a company as per the filing. Its CIN U45202KA2008PTC046145 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in SHRIRAM SOUTHERN CREST - Phase -2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against SHRIRAM SOUTHERN CREST - Phase -2?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at SHRIRAM SOUTHERN CREST - Phase -2?

The professionals named in the filing: Architect: CnT ARCHITECTS; Engineer: INNOTECH ENGINEERING CONSULT PVT LTD. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHRIRAM SOUTHERN CREST - Phase -2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHRIRAM SOUTHERN CREST - Phase -2. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHRIRAM SOUTHERN CREST - Phase -2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.