SHRIRAM SERENITY

By SHRIRAM PROPERTIES LIMITED

RG-KA-61922 · RERA PRM/KA/RERA/1251/309/PR/170924/007026 · Last updated on RERA Karnataka portal: 12 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • 1 complaint at RERA Karnataka

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
Jul 2029Possession promisedno revision filed
3 of 18Construction stages donefurthest along: Upto Plinth Level, 90%
0 of 270Units unsoldnot recorded sold or booked
1Complaints at RERA Karnatakaon this registration
Jump to the 166 documents Report an error

SHRIRAM SERENITY is a Residential/Group Housing project by SHRIRAM PROPERTIES LIMITED in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/309/PR/170924/007026 on 17 Sep 2024. Possession is promised by 5 Jul 2029. 270 of the 270 units on this registration are recorded sold or booked, and 3 of 18 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameSHRIRAM SERENITY
  • TypeResidential/Group Housing
  • Location
    • Bengaluru North
    • Bengaluru Urban
    • 560064
  • Pincode560064
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/309/PR/170924/007026
  • ReraGenie IDRG-KA-61922

Builder

  • NameSHRIRAM PROPERTIES LIMITED
  • Entity typeCompany
  • CINU72200TN2000PLC044560
  • GSTIN29AAFCS5801D1ZI
  • Authorized SignatoryKRISHNA VEERARAGHAVAN
  • Director & Chief Operating Officer (Bangalore)KRISHNA VEERARAGHAVAN
  • DirectorsKulumani Gopalrathnam Krishnamurthy, M Murali, Thai Salas Vijayan, Srinivasan Natarajan, Vaidyanathan Ramamurthy, Mandot Ritesh Kantilal, Anita Kapoor
  • Project HeadKiran Kumar R
  • Other registrations4 more →
  • Declared earlier projects4 →

Key dates

this monthRegisteredSep 2024PromisedJul 2029

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on17 Sep 2024
  • Promised completion5 Jul 2029
  • Revised completionNone
  • Buildings3 building records
  • Documents filed166 files

Current status

100%270 of 270 units booked
7.5%Of the estimated cost spent so far

Figures as on 12 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---96096
B---78078
C---96096

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 12 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 18 construction stages are filed complete. The stage furthest along is Upto Plinth Level, at 90%.

Building: 29% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level90%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)80%
Retaining wall (All types)100%
RCC or MS Framed structure35%
Masonry Construction9%
Plastering inside , outside & Ceiling0%
Joinery: Doors, Windows, Ventilators etc0%
Basic work of Water supply, Sanitary and Electrification0%
Dadoing, Skirting, Flooring, Tiles work (All types)0%
Railing and Grill fixing0%
Electrification, Water supply and Sanitary Finishing0%
Painting0%
Fire prevention and fire fighting fitting and fixture with network0%
Weather Proof work(tile,concrete)0%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work0%
Internal and External work including landscapes as per sanctioned drawings0%

Progress on shared amenities40

As on 12 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes0%
Sewage and Drainage SystemYes0%
Water conservation/rain water harvesting/recharge of ground waterYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes0%
Solid waste management and disposalYes0%
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsYes0%
Electricity supply transformer and substationYes0%
Storm water drainsYes0%
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes0%
Parks & Tree plantingYes0%
Street LightingYes0%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseYes0%
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolYes0%
GymNoNot applicable
ParksYes0%
Power BackupYes0%
Piped GasNoNot applicable
Water and SanitationNoNot applicable
Air ConditioningNoNot applicable
StaircasesYes0%
LiftsYes0%
Corridor/LobbiesYes0%
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahNoNot applicable
BasementNoNot applicable
TerraceNoNot applicable
Outer WallYes0%
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesYes0%

Land and ownership10

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area15,530 sq m
Named landowners10
LandownerVillageDistrict
Ms Deepa Chikarmane--
Ms Preetha Chandrasekaran--
Ms Deepa Chikarmane--
Ms Preetha Chandrasekaran--
Ms Deepa Chikarmane--
Ms Preetha Chandrasekaran--
Ms Deepa Chikarmane--
Ms Preetha Chandrasekaran--
Ms Deepa Chikarmane--
Ms Preetha Chandrasekaran--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 128.93 cr
Cost incurredRs 9.67 cr
Spent of the estimate7.5%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 91.63 crRs 9.27 cr
Principal sum and interest payable to financial institutions-Non Banking financial institution (NBFC)Rs 20.00 crRs 33.85 lakh
Payment of taxesRs 16.45 crRs 5.66 lakh
Payment of cessRs 85.00 lakh-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectR. Sundaram
EngineerSundaram Rajagopala Iyyar
Chartered AccountantVivek Gupta

Complaints filed with RERA Karnataka1

Case no.ComplainantRespondentFiled
00176/2025-SHRIRAM PROPERTIES LIMITED23/01/2025

Documents filed166

As listed on the registration, under the names the promoter filed them with; the newest 80 of 166 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/309/PR/170924/007026 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form-4 Shriram Serenity Aug 26.pdf12 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: ARCHITECTS CERTIFICATE -SERENITY.PDF12 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form-6 Engineer (QU) Serenity Q2 2026-27.pdf12 Oct 2026
Q2 2026-27 Water supply and sewage board12 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)12 Oct 2026
Q2 2026-27 KSPCB- MOEF (Above 50 Acres)12 Oct 2026
Q2 2026-27 KPTCL- BESCOM12 Oct 2026
Q2 2026-27 Fire and Safety12 Oct 2026
Q2 2026-27 Airport Authority of India12 Oct 2026
Q2 2026-27 BSNL/Telecommunication Department12 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form-4 Shriram Serenity June 26.pdf9 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: ARCHITECTS CERTIFICATE - SHRIRAM SERENITY.pdf9 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form-6 Engineer (QU) Serenity Q1 2026-27.pdf9 Jul 2026
Q1 2026-27 Water supply and sewage board9 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)9 Jul 2026
Q1 2026-27 KSPCB- MOEF (Above 50 Acres)9 Jul 2026
Q1 2026-27 KPTCL- BESCOM9 Jul 2026
Q1 2026-27 Fire and Safety9 Jul 2026
Q1 2026-27 Airport Authority of India9 Jul 2026
Q1 2026-27 BSNL/Telecommunication Department9 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: CA CERTIFICATE.pdf13 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Architect's certificate- Serenity.pdf13 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form-6 Engineer (QU) Serenity Q4 2025-26.pdf13 Apr 2026
Q4 2025-26 Water supply and sewage board13 Apr 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)13 Apr 2026
Q4 2025-26 KSPCB- MOEF (Above 50 Acres)13 Apr 2026
Q4 2025-26 KPTCL- BESCOM13 Apr 2026
Q4 2025-26 Fire and Safety13 Apr 2026
Q4 2025-26 Airport Authority of India13 Apr 2026
Q4 2025-26 BSNL/Telecommunication Department13 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form-4 Shriram Serenity Dec'25.pdf3 Feb 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: ARCHITECTS CERTIFICATE - SERENITY.pdf3 Feb 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form-6 Engineer (QU) Serenity Q3 2024-25.pdf3 Feb 2026
Q3 2025-26 Water supply and sewage board3 Feb 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)3 Feb 2026
Q3 2025-26 KSPCB- MOEF (Above 50 Acres)3 Feb 2026
Q3 2025-26 KPTCL- BESCOM3 Feb 2026
Q3 2025-26 Fire and Safety3 Feb 2026
Q3 2025-26 Airport Authority of India3 Feb 2026
Q3 2025-26 BSNL/Telecommunication Department3 Feb 2026
passbook/ pass sheets of 100%, 70% & 30% account detailsFile: Bank account statement 100% 70% 30% merged.pdf14 Jun 2024
Bank affidavitFile: Bank account affidavit.pdf14 Jun 2024
CA KYC and membership certificate with self attestedFile: Self attested CA membership certificate.pdf14 Jun 2024
Profit loss, Balance sheet and cash flow statement 2020-21File: Shriram Properties Standalone Mar 2021.pdf14 Jun 2024
Profit loss, Balance sheet and cash flow statement 2021-22File: Shriram properties Standalone signed 2022.pdf14 Jun 2024
Profit loss, Balance sheet and cash flow statement 2022-23File: SPL_Standalone Signed FS Mar 2023.pdf14 Jun 2024
Sources of funds to complete the projectFile: letter for Sources of fund to complete the project.pdf14 Jun 2024
Letter for updating of borrowing details in financial statement and CA certificateFile: Letter for updating of borrowing details financial statement and CA cer.pdf14 Jun 2024
Total estimated cost of the project matched with CA certificate and Engineers certificateFile: Form 3 Engineers certificate Total estimated cost brief.pdf14 Jun 2024
quarterly reports and annual audit reports of previous projects.File: Quarterly reports and annual audit reports.pdf14 Jun 2024
EC from 13-12-2023 to till date For all Survey Number of the projectFile: ECC-12062024-1811334.pdf14 Jun 2024
Enclosed cancellation deedFile: Cancellation of Agreement of Sale Deed dated 15-05-2024.pdf14 Jun 2024
correct RTCs of the current yearFile: All merged RTC.pdf14 Jun 2024
development plan order.File: Letter dated 12 Jan 23 Development Plan Sanction Adde Vishwanathpura Project 05 Pages doc114 Jun 2024
certified carpet area calculationFile: RERA - CARPET AREA.PDF14 Jun 2024
CDP map showing the proposed siteFile: VISHWANATHAPURA_CDP PLAN.pdf14 Jun 2024
village map showing the proposed site.File: Village map showing proposed site.pdf14 Jun 2024
Letter for project details in the SEIAA NOC and KSPCB is not matching with the sanction Plan.File: Letter for SEIAA and KSPCB NOC mismatch with sanction plan.pdf14 Jun 2024
Relinquishment deed.File: Relinquishment merged.pdf14 Jun 2024
Requesting letter to Building licenseFile: Letter for building license.pdf14 Jun 2024
Amenities and Common area details calculation sheet certified by the Engineer.File: Amenities and common area calculation sheet.pdf14 Jun 2024
Latest dated self-attested copy of the Engineer license certificateFile: Self Attested Engineer License.pdf14 Jun 2024
Brief estimated cost of construction certified by the registered Civil Engineer.File: Cost of construction Break Up.pdf14 Jun 2024
Updated the annexure-A and upload the proforma of the Allotment letter.File: ALLOTMENT LETTER-12-06-2024.pdf14 Jun 2024
Letter for NOC/permission letter issued by the defence Aerospace station, Yelahanka.File: Letter for NOC issued by the defence aerospace.pdf14 Jun 2024
Updated proforma of Agreement for Sale- highlighted the points which is askedFile: Annexture 86 Agreement for Sale-.pdf14 Jun 2024
STP design drawing certified by the Engineer as per the guidelines of KSPCB NOC.File: STP DRAWING - SHRIRAM.pdf14 Jun 2024
Land cost calculation sheet as per the guidance valueFile: Land cost calculation sheet as per the guidance value.pdf14 Jun 2024
RTC, survey 74/8-
Mutation, survey 74/8-
Encumbrance Certificate, survey 74/8-
Conversion/Alienation Order, survey 74/8-
Sale/Title/Gift Deed, survey 74/8-
JDA, survey 74/8-
Khatha, survey 74/8-
RTC, survey 74/10-
Mutation, survey 74/10-
Encumbrance Certificate, survey 74/10-
Conversion/Alienation Order, survey 74/10-
Sale/Title/Gift Deed, survey 74/10-

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 under way, not due yet
ProjectLocationStatusPromisedDelivered
SHRIRAM SAPPHIRESy.No-72, Bommasandra Village, Attibele-Hobli , Anekal Taluk, Bangalore-Urban , Bommasandra Village , Bengaluru South , Bengaluru Urban, Karnataka - 560099OngoingNov 2028Not due yet

How this compares with Bengaluru Urban

100%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep SHRIRAM SERENITY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmSHRIRAM SERENITYOther 10Dot size: filed unitsN

Filed coordinates, straight-line distance. 10 registered projects within 2 km.

Builder: SHRIRAM PROPERTIES LIMITED

SHRIRAM PROPERTIES LIMITED has 5 registrations on RERA Karnataka, including SHRIRAM SERENITY and SHRIRAM ESQUIRE. Its filings declare 4 earlier projects, none of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if SHRIRAM SERENITY is delayed beyond 5 Jul 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of SHRIRAM SERENITY?

The registered promoter entity is SHRIRAM PROPERTIES LIMITED, a company as per the filing. Its CIN U72200TN2000PLC044560 and GSTIN 29AAFCS5801D1ZI can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in SHRIRAM SERENITY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against SHRIRAM SERENITY?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at SHRIRAM SERENITY?

The professionals named in the filing: Architect: R. Sundaram; Engineer: Sundaram Rajagopala Iyyar; Chartered Accountant: Vivek Gupta. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHRIRAM SERENITY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHRIRAM SERENITY. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHRIRAM SERENITY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.