Home / Browse projects / Bengaluru Urban, Karnataka / SHRIRAM LIBERTY SQUARE
SHRIRAM LIBERTY SQUARE
By Shriprop Developers Private Limited
RG-KA-98671 · RERA PRM/KA/RERA/1251/308/PR/190330/002519
Source: official RERA Karnataka filing
Red flags
- 15 complaints at RERA Karnataka
- Completion date moved by 9 months
- 1 extension taken
Clear
- Separate project account declared
Saved.
SHRIRAM LIBERTY SQUARE is a Residential/Group Housing project by Shriprop Developers Private Limited in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/308/PR/190330/002519 on 30 Mar 2019. Possession is promised by 14 Nov 2024. The completion date has moved by 9 months from the original filing. 15 complaints are on record with the regulator.
At a glance
Project
- NameSHRIRAM LIBERTY SQUARE
- TypeResidential/Group Housing
- Location
- Anekal
- Bengaluru Urban
- PincodeNot stated
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1251/308/PR/190330/002519
- ReraGenie IDRG-KA-98671
Builder
- NameShriprop Developers Private Limited
- Entity typeCompany
- CINU45400KA2016PTC085337
- Authorized SignatoryK.R.RAMESH
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on30 Mar 2019
- Promised completion14 Nov 2024
- Revised completionRevised to 14 Nov 2024 (originally 14 Feb 2024)
- Buildings7 building records
- Documents filed55 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A | - | - | - | 84 | 0 | 84 |
| B | - | - | - | 126 | 0 | 126 |
| C | - | - | - | 77 | 0 | 77 |
| D | - | - | - | 77 | 0 | 77 |
| E | - | - | - | 126 | 0 | 126 |
| F | - | - | - | 77 | 0 | 77 |
| G | - | - | - | 77 | 0 | 77 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building:
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Retaining wall (All types) | - |
| Plinth level Beam | - |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | - |
| RCC or MS Framed structure | - |
| Masonry construction: Bricks, Concrete blocks etc | - |
| Plastering inside , outside & Ceiling | - |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | - |
| Fire prevention and fire fighting fitting and fixture with network | - |
| Weather Proof work(tile,concrete) | - |
| Painting | - |
| Elevation work | - |
| Internal and External work including landscapes as per santioned drawings | - |
Progress on shared amenities41
Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Internal Roads & Footpaths | Yes | - |
| Sewage and Drainage System | Yes | - |
| Parks & Tree planting | Yes | - |
| Street Lighting | Yes | - |
| Provision for community buildings and for treatment and disposal of sewage and sullage water | Yes | - |
| Solid waste management and disposal | Yes | - |
| Water conservation | Yes | - |
| Energy management | Yes | - |
| Fire protection and fire safety requirements | Yes | - |
| Education/Health/Other public amenities | Yes | - |
| Electricity supply transformer and substation | Yes | - |
| Emergency Evacuation services | Yes | - |
| Storm water drains | Yes | - |
| Use of renewable energy | Yes | - |
| Water conservation/rain water harvesting/recharge of ground water | Yes | - |
| Electricity | Yes | - |
| Smart Home Automation | Yes | - |
| CCTV Surveillance | Yes | - |
| Club House | Yes | - |
| Community Hall | Yes | - |
| Outdoor Sports facility | Yes | - |
| Indoor Sports facility | Yes | - |
| Swimming Pool | Yes | - |
| Gym | Yes | - |
| Parks | Yes | - |
| Power Backup | Yes | - |
| Gas | No | Not applicable |
| Water and Sanitation | Yes | - |
| Air Conditioning And incerntion | No | Not applicable |
| Staircases | Yes | - |
| Lifts | Yes | - |
| Staircases and Lift lobbies, corridor,lobbies, corridor | Yes | - |
| Fire escapes | Yes | - |
| Common entrance and exit for the building / common portico/foyer/verandah | Yes | - |
| Basement | Yes | - |
| Terrace | Yes | - |
| Outer Wall | Yes | - |
| Open parking areas and common storage spaces | Yes | - |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | Yes | - |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SUNDARAM ARCHITECTS PVT. LTD. |
| Engineer | R SUNDARAM |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
No reason recorded in the filing
Complaints filed with RERA Karnataka15
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CMP/190809/0003863 | - | Shriprop Developers Private Limited | 09/08/2019 |
| CMP/200207/0005394 | - | Shriprop Developers Private Limited | 07/02/2020 |
| CMP/201109/0006953 | - | Shriprop Developers Private Limited | 09/11/2020 |
| CMP/210104/0007384 | - | Shriprop Developers Private Limited | 04/01/2021 |
| CMP/210303/0007724 | - | Shriprop Developers Private Limited | 03/03/2021 |
| CMP/210520/0007955 | - | Shriprop Developers Private Limited | 20/05/2021 |
| CMP/220201/0008891 | - | Shriprop Developers Private Limited | 01/02/2022 |
| CMP/220507/0009430 | - | Shriprop Developers Private Limited | 07/05/2022 |
| CMP/220510/0009447 | - | Shriprop Developers Private Limited | 10/05/2022 |
| CMP/220520/0009495 | - | Shriprop Developers Private Limited | 20/05/2022 |
| CMP/220625/0009690 | - | Shriprop Developers Private Limited | 25/06/2022 |
| CMP/220719/0009760 | - | Shriprop Developers Private Limited | 19/07/2022 |
| CMP/221107/0010211 | - | Shriprop Developers Private Limited | 07/11/2022 |
| 00271/2023 | - | Shriprop Developers Private Limited | 28/02/2023 |
| 00464/2023 | - | Shriprop Developers Private Limited | 12/04/2023 |
Documents filed55
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/308/PR/190330/002519 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| CertificateFile: 001 COI Shriprop Developers.pdf | - |
| WO and CC combined | - |
| Sanction 10 of 10 - Copy | - |
| Drawing No 10 Site Plan Details Tower A to C Shriram Liberty Square | - |
| sale deed format | - |
| Agreement for Sale | - |
| Sale deed & RTC | - |
| Sanction 10 of 10 - Copy | - |
| Development_plan new compressed | - |
| Allotment Letter | - |
| Brochure without Cta | - |
| 023 Specifications for Liberty Square | - |
| 03 New EC 2019 | - |
| 01 Section 3 AFFIDAVIT Krishna | - |
| KGF Joint affidavit cum declaration | - |
| Khatha all in one | - |
| JDA & GPA combined | - |
| Conversion | - |
| Relinquishment_Deed | - |
| 07 Fire NOC 2019 | - |
| 03 Airports Authority of India 2015 | - |
| 04 KSPCB 2017 | - |
| 02 SEIAA 2017 | - |
| 05 BSNL 2015 | - |
| all in one Plans comp | - |
| Section & Specifications | - |
| Conversion | - |
| Advocate search report | - |
| Balance Sheet 2017 - 2018File: 005 Balance sheet 2018.pdf | - |
| Audited Profit and Loss Statement 2017 - 2018File: 006 P&L 2018.pdf | - |
| Director's Report 2017 - 2018File: 007 Directors Report - Shriprop Developers.pdf | - |
| Cash Flow Statement 2017 - 2018File: 008 Cash Flow 2018.pdf | - |
| Auditor's Report 2017 - 2018File: AUDITORS REPORT 2018.pdf | - |
| Income Tax Return Acknowledgement 2017 - 2018File: ITR 2018.pdf | - |
| Income Tax Return Acknowledgement 2016 - 2017File: ITR 2017.pdf | - |
| Income Tax Return Acknowledgement 2015 - 2016File: ITR 2016.pdf | - |
| form b | - |
| Prospectus/BrochureFile: Brochure without Cta.pdf | - |
| Advertisement Copy 1File: Brochure without Cta.pdf | - |
| Tower Excel SheetFile: Copy of PRM_KA_RERA_1251_308_PR_190330_002519.xlsx | - |
| Loan raised documentFile: loan details.pdf | - |
| Stability CertificateFile: 5 Satbility certificate and completion certificate- Liberty square.PDF | - |
| Road cutting permission letter issued by the planning Authority for laying Water supply line, sanitary line, UFile: Clarrification regarding documents.pdf | - |
| NOC issued by the Fire Force department after completion of workFile: 6 CC Fire Force Dept dated 28 Dec 23 Liberty Square Project Pages 02 OrderCertificate-304. | - |
| Occupancy CertificateFile: 7 Occupancy Certificate dated 06 January 24 Liberty Square Project 06-01-2024 16-11-43.pdf | - |
| Consent for operation issued by KSPCBFile: 9 Shriprop - Liberty Square - KSPCB Acknowledgement.pdf | - |
| Certificate of operation for lifts issued by the Chief of Department of Electrical inspectorate Government of File: SHRIRAM LIBERTY EI000110602662Lift erection.pdf | - |
| Sanctioned Letter issued by concerned ESCOM of Power sanction and details of transformer installed and whetherFile: 10 BESCOM Power sanction Ltr-Liberty square.pdf | - |
| Sanctioned letter issued by concerned water supply and sanitary board for the projectFile: 11 Water supply NOC Grampanchayat dated 13 January 2015.pdf | - |
| Details of external infrastructure work such as drive way, play area, park, STP and water treatment plant, WheFile: Liberty square External infr details.pdf | - |
| Common Area and other amenities facilities are completed or not and details of handling over of the same to asFile: Liberty square Amenity and other common area detail.pdf | - |
| Architect certificate for having completed the work(in format no 5)File: 2 Form5-Architect certificate for project completion liberty square.PDF | - |
| Chartered Accountant certificate for having completed the work(in format no 4)File: 1 Form4 CC-Liberty Square.pdf | - |
| Affidavit cum declaration from promoter for having completed the project as per specification and as per adverFile: 4 Affidavit cum declaration for Completion- Shriram Liberty Square.pdf | - |
| Enclosed clarrification for Road cutting permission, CFO issued by KSPCB and Lift operation certifiFile: Clarrification regarding documents.pdf | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep SHRIRAM LIBERTY SQUARE on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Filed coordinates, straight-line distance. 17 registered projects within 2 km.
Prestige Park Grove
PRESTIGE PROJECTS PRIVATE LIMITED
Prestige Lakeside Habitat
Prestige Habitat Ventures
LivingTree by Kalyani Developers
Kalyani Tech Park Private Limited
PRESTIGE FALCON CITY
PRESTIGE NOTTINGHILL INVESTMENTS
SATTVA CITY
SATTVA CITY PRIVATE LIMITED
GM AMBITIOUS ENCLAVE
M/s. Allam Infinite India Private Limited
See every Bengaluru Urban project, with the district possession charts
Builder: Shriprop Developers Private Limited
Shriprop Developers Private Limited has 1 registration on RERA Karnataka, including SHRIRAM LIBERTY SQUARE. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if SHRIRAM LIBERTY SQUARE is delayed beyond 14 Nov 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of SHRIRAM LIBERTY SQUARE?
The registered promoter entity is Shriprop Developers Private Limited, a company as per the filing. Its CIN U45400KA2016PTC085337 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in SHRIRAM LIBERTY SQUARE?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against SHRIRAM LIBERTY SQUARE?
Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
Who certifies construction progress at SHRIRAM LIBERTY SQUARE?
The professionals named in the filing: Architect: SUNDARAM ARCHITECTS PVT. LTD.; Engineer: R SUNDARAM. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SHRIRAM LIBERTY SQUARE?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback