Home / Browse projects / Bengaluru Urban, Karnataka / SHRIRAM HEBBAL 1

Registration approved No litigation declared Commercial project

SHRIRAM HEBBAL 1

By Shriram Upscale Space Private Limited

RG-KA-12678 · RERA PRM/KA/RERA/1251/309/PR/150223/005722 · Last updated on RERA Karnataka portal: 8 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Jan 2027Possession promisedno revision filed
18 of 18Construction stages doneevery applicable stage filed complete
0 of 9Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 135 documents Report an error

SHRIRAM HEBBAL 1 is a Commercial project by Shriram Upscale Space Private Limited in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/309/PR/150223/005722 on 15 Feb 2023. Possession is promised by 19 Jan 2027. 9 of the 9 units on this registration are recorded sold or booked, and 18 of 18 construction stages are filed complete.

At a glance

Project

  • NameSHRIRAM HEBBAL 1
  • TypeCommercial
  • Location
    • Bengaluru North
    • Bengaluru Urban
    • 560024
  • Pincode560024
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/309/PR/150223/005722
  • ReraGenie IDRG-KA-12678

Builder

  • NameShriram Upscale Space Private Limited
  • Entity typeCompany
  • CINU45500KA2017PTC099721
  • GSTIN29AAYCS0686H1ZV
  • Authorized SignatoryKrishna veeraraghavan
  • Director & Chief Operating OfficerKrishna veeraraghavan
  • DirectorRavindrakumar Pandey
  • Project HeadKiran Kumar R

Key dates

this monthRegisteredFeb 2023PromisedJan 2027

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on15 Feb 2023
  • Promised completion19 Jan 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed135 files

Current status

100%9 of 9 units booked
0.0%Of the estimated cost spent so far

Figures as on 8 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Commercial Building---099

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 8 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

18 of 18 construction stages are filed complete.

Building: 100% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)100%
RCC or MS Framed structure100%
Masonry Construction100%
Plastering inside , outside & Ceiling100%
Joinery: Doors, Windows, Ventilators etc100%
Basic work of Water supply, Sanitary and Electrification100%
Dadoing, Skirting, Flooring, Tiles work (All types)100%
Railing and Grill fixing100%
Electrification, Water supply and Sanitary Finishing100%
Painting100%
Fire prevention and fire fighting fitting and fixture with network100%
Weather Proof work(tile,concrete)100%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work100%
Internal and External work including landscapes as per sanctioned drawings100%

Progress on shared amenities40

As on 8 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes100%
Sewage and Drainage SystemYes100%
Water conservation/rain water harvesting/recharge of ground waterYes100%
Energy managementYes100%
Fire protection and fire safety requirementsYes100%
Solid waste management and disposalYes100%
Emergency Evacuation servicesYes100%
Internal Roads & FootpathsYes100%
Electricity supply transformer and substationYes100%
Storm water drainsYes100%
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes100%
Parks & Tree plantingYes100%
Street LightingYes100%
ElectricityYes100%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes100%
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupYes100%
Piped GasNoNot applicable
Water and SanitationYes100%
Air ConditioningYes100%
StaircasesYes100%
LiftsYes100%
Corridor/LobbiesYes100%
Fire escapesYes100%
Common entrance and exit for the building/common portico/foyer/verandahYes100%
BasementYes100%
TerraceYes100%
Outer WallYes100%
Open parking areasYes100%
Provision for lodging of management staff and security staffYes100%
Water conservation and renewable energyNoNot applicable
Common storage spacesYes100%

Land and ownership2

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area7,284 sq m
Named landowners2
LandownerVillageDistrict
S Narayana Raju--
S Narayana Raju--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 118.46 cr
Spent of the estimate0.0%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 118.46 cr-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectThe Factory Architects
EngineerInnotech Consultants Pvt ltd
Chartered AccountantVGCA and Associates

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed135

As listed on the registration, under the names the promoter filed them with; the newest 80 of 135 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/309/PR/150223/005722 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form-4-Hebbal-1-June'26K.pdf8 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form-5 Architect (QU) HEBBAL 1 Q1 2026-27.pdf8 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form-6 Engineer (QU) HB1 Q1 2026-27.pdf8 Oct 2026
Q2 2026-27 Water supply and sewage board8 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)8 Oct 2026
Q2 2026-27 KSPCB- MOEF (Above 50 Acres)8 Oct 2026
Q2 2026-27 KPTCL- BESCOM8 Oct 2026
Q2 2026-27 Fire and Safety8 Oct 2026
Q2 2026-27 Airport Authority of India8 Oct 2026
Q2 2026-27 BSNL/Telecommunication Department8 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form-4-Hebbal-1-June'26K.pdf8 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form5 Architect QU HEBBAL 1 Q4 202526.pdf8 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form-6 Engineer (QU) HB1 Q1 2026-27.pdf8 Jul 2026
Q1 2026-27 Water supply and sewage board8 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)8 Jul 2026
Q1 2026-27 KSPCB- MOEF (Above 50 Acres)8 Jul 2026
Q1 2026-27 KPTCL- BESCOM8 Jul 2026
Q1 2026-27 Fire and Safety8 Jul 2026
Q1 2026-27 Airport Authority of India8 Jul 2026
Q1 2026-27 BSNL/Telecommunication Department8 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Hebbal-1.pdf10 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form-5 Architect (QU) HEBBAL 1 Q4 2025-26.pdf10 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form-6 Engineer (QU) HB1 Q4 2025-26.pdf10 Apr 2026
Q4 2025-26 Water supply and sewage board10 Apr 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)10 Apr 2026
Q4 2025-26 KSPCB- MOEF (Above 50 Acres)10 Apr 2026
Q4 2025-26 KPTCL- BESCOM10 Apr 2026
Q4 2025-26 Fire and Safety10 Apr 2026
Q4 2025-26 Airport Authority of India10 Apr 2026
Q4 2025-26 BSNL/Telecommunication Department10 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form-4-Hebbal-1-Dec'25.pdf3 Feb 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form-5 Architect (QU) HEBBAL 1 Q3 2025-26.pdf3 Feb 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form-6 Engineer (QU) HB1 Q3 2024-25.pdf3 Feb 2026
Q3 2025-26 Water supply and sewage board3 Feb 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)3 Feb 2026
Q3 2025-26 KSPCB- MOEF (Above 50 Acres)3 Feb 2026
Q3 2025-26 KPTCL- BESCOM3 Feb 2026
Q3 2025-26 Fire and Safety3 Feb 2026
Q3 2025-26 Airport Authority of India3 Feb 2026
Q3 2025-26 BSNL/Telecommunication Department3 Feb 2026
Auditors Report 2019-20 -2020-21 - 2021-22 with CA UDINFile: Shriram upscale AR FY 2019-2020-2021.pdf10 Feb 2023
Balance sheet 2019-20 -2020-21 - 2021-22File: Shriram upscale BS FY 2019-2020-2021.pdf10 Feb 2023
Profit Loss statements 2019-20 -2020-21 - 2021-22File: Shriram upscale PL FY 2019-2020-2021.pdf10 Feb 2023
Cash flow statement 2019-20 -2020-21 - 2021-22File: Shriram upscale CFS FY 2019-2020-2021.pdf10 Feb 2023
CA certificate Form-01File: 2 Form-01 CA certificate.pdf10 Feb 2023
MR for both sy noFile: 3 MR Hebbal 1.pdf10 Feb 2023
Advocate search reportFile: 4 Advocate search report HEBBAL ONE.pdf10 Feb 2023
Notarized joint affidavit with Land Owner signatureFile: 5 Joint affidavit cum declaration.pdf10 Feb 2023
FAR as per sanction is 3 06File: 7 Sanction Plans.pdf10 Feb 2023
Clarification for Carpet AreaFile: 1 FAR AND CARPET AREA CLARIFICATION.pdf10 Feb 2023
CDP mapFile: 2 CDP Map Showing- Hebbal 1 Project.PNG10 Feb 2023
Village Map showing site locationFile: 3 Village Map Hebbal 1 Project.pdf10 Feb 2023
Clarification for Relinquishment deed for road wideningFile: 4 Letter for Relinquishment of Road.pdf10 Feb 2023
Clarification for commencement certificateFile: 5 Letter and clarification for RERA- For commencement certificate.pdf10 Feb 2023
kSPCB CFE NOCFile: 6 KSPCB NOC.pdf10 Feb 2023
All sanction sectional plansFile: 7 Sanction Plans.pdf10 Feb 2023
SEIAA NOCFile: 8 SEIAA NOC.pdf10 Feb 2023
Site location Longitude- 13 0440459 and Latitude 77 5977952File: Hebbal 1-Site location Map.pdf10 Feb 2023
Engineer Certificate Form-3File: Form - 3, Engineer Certificate.pdf10 Feb 2023
Signed Project SpecificationsFile: Signed Project Specifications.pdf10 Feb 2023
Section 3-1 notarized affidavitFile: Annexure 91-Notarized Affidavit for 3-1 Voliation.pdf10 Feb 2023
Letter and affidavits for BESCOM and BWSSB NOCFile: Letter and affidavit for BWSSB and BESCOM NOC with fee receipt.pdf10 Feb 2023
Structural Stability Certificate from Registered EngineerFile: Structural stability certificate.pdf10 Feb 2023
Proforma Agreement of SaleFile: Proforma Agreement of sale Hebbal 1.pdf10 Feb 2023
Proforma Allotment LetterFile: Proforma allotment Letter-Hebbal 1.pdf10 Feb 2023
STP design drawing with STP demarcation planFile: STP demarcation plan with design drawings.pdf10 Feb 2023
Letter and affidavits for renewed NOCs submissionFile: Letter and Affidavits for renewed NOCs submission.pdf10 Feb 2023
UDS are is updated in the inventory details pageFile: Clarification for UDS area.pdf10 Feb 2023
RTC, survey 14-1-
Mutation, survey 14-1-
Encumbrance Certificate, survey 14-1-
Conversion/Alienation Order, survey 14-1-
Sale/Title/Gift Deed, survey 14-1-
JDA, survey 14-1-
Khatha, survey 14-1-
RTC, survey 15-6-
Mutation, survey 15-6-
Encumbrance Certificate, survey 15-6-
Conversion/Alienation Order, survey 15-6-
Sale/Title/Gift Deed, survey 15-6-

How this compares with Bengaluru Urban

100%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep SHRIRAM HEBBAL 1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmSHRIRAM HEBBAL 1Other 10Dot size: filed unitsN

Filed coordinates, straight-line distance. 10 registered projects within 2 km.

Builder: Shriram Upscale Space Private Limited

Shriram Upscale Space Private Limited has 1 registration on RERA Karnataka, including SHRIRAM HEBBAL 1. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if SHRIRAM HEBBAL 1 is delayed beyond 19 Jan 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of SHRIRAM HEBBAL 1?

The registered promoter entity is Shriram Upscale Space Private Limited, a company as per the filing. Its CIN U45500KA2017PTC099721 and GSTIN 29AAYCS0686H1ZV can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in SHRIRAM HEBBAL 1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SHRIRAM HEBBAL 1?

The professionals named in the filing: Architect: The Factory Architects; Engineer: Innotech Consultants Pvt ltd; Chartered Accountant: VGCA and Associates. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHRIRAM HEBBAL 1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHRIRAM HEBBAL 1. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHRIRAM HEBBAL 1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.