Home / Browse projects / Bengaluru Urban, Karnataka / SHRIRAM 107 SOUTHEAST - PHASE 2

Registration approved No litigation declared Residential/Group Housing project

SHRIRAM 107 SOUTHEAST - PHASE 2

By Shriprop Living Space Private Limited

RG-KA-76169 · RERA PRM/KA/RERA/1251/308/PR/190715/002689 · Last updated on RERA Karnataka portal: 23 Mar 2026

Source: official RERA Karnataka filing

Red flags

  • 8 complaints at RERA Karnataka
  • Completion date moved by 9 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
Mar 2025Possession promisedmoved 9 months from the original
16 of 16Construction stages doneevery applicable stage filed complete
0 of 708Units unsoldnot recorded sold or booked
8Complaints at RERA Karnatakaon this registration
Jump to the 86 documents Report an error

SHRIRAM 107 SOUTHEAST - PHASE 2 is a Residential/Group Housing project by Shriprop Living Space Private Limited in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/308/PR/190715/002689 on 15 Jul 2019. Possession is promised by 14 Mar 2025. The completion date has moved by 9 months from the original filing. 708 of the 708 units on this registration are recorded sold or booked, and 16 of 16 construction stages are filed complete. 8 complaints are on record with the regulator.

At a glance

Project

  • NameSHRIRAM 107 SOUTHEAST - PHASE 2
  • TypeResidential/Group Housing
  • Location
    • Anekal
    • Bengaluru Urban
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/308/PR/190715/002689
  • ReraGenie IDRG-KA-76169

Builder

  • NameShriprop Living Space Private Limited
  • Entity typeCompany
  • CINU70109KA2014PTC076190
  • Authorized SignatoryKrishna veeraraghavan
  • Other registrations2 more →
  • Declared earlier projects2 →

Key dates

this monthRegisteredJul 2019First promiseJun 2024Revised toMar 2025

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on15 Jul 2019
  • Promised completion14 Mar 2025
  • Revised completionRevised to 14 Mar 2025 (originally 14 Jun 2024)
  • Buildings6 building records
  • Documents filed86 files

Current status

100%708 of 708 units booked
0.0%Of the estimated cost spent so far

Figures as on 23 Mar 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
7---1180118
8---1180118
9---1180118
10---1180118
11---1180118
12---1180118

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 23 Mar 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

16 of 16 construction stages are filed complete.

Building: 100% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Retaining wall (All types)100%
Plinth level BeamNot applicable
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
RCC or MS Framed structure100%
Masonry construction: Bricks, Concrete blocks etc100%
Plastering inside , outside & Ceiling100%
Joinery: Doors, Windows, Ventilators etc100%
Basic work of Water supply, Sanitary and Electrification100%
Dadoing, Skirting, Flooring, Tiles work (All types)100%
Railing and Grill fixing100%
Electrification, Water supply and Sanitary Finishing100%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network100%
Weather Proof work(tile,concrete)Not applicable
Painting100%
Elevation work100%
Internal and External work including landscapes as per santioned drawings100%

Progress on shared amenities41

As on 23 Mar 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes100%
Internal Roads & FootpathsYes100%
Sewage and Drainage SystemYes100%
Parks & Tree plantingYes100%
Street LightingYes100%
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes100%
Solid waste management and disposalYes100%
Water conservationNoNot applicable
Energy managementYes100%
Fire protection and fire safety requirementsYes100%
Education/Health/Other public amenitiesYes100%
Electricity supply transformer and substationNoNot applicable
Emergency Evacuation servicesNoNot applicable
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterNoNot applicable
ElectricityYes100%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes100%
Club HouseYes100%
Community HallYes100%
Outdoor Sports facilityYes100%
Indoor Sports facilityYes100%
Swimming PoolYes100%
GymYes100%
ParksYes100%
Power BackupYes100%
GasNoNot applicable
Water and SanitationYes100%
Air Conditioning And incerntionNoNot applicable
StaircasesYes100%
LiftsYes100%
Staircases and Lift lobbies, corridor,lobbies, corridorYes100%
Fire escapesYes100%
Common entrance and exit for the building / common portico/foyer/verandahYes100%
BasementYes100%
TerraceYes100%
Outer WallYes100%
Open parking areas and common storage spacesYes100%
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes100%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area73,349 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 178.29 cr
Spent of the estimate0.0%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 116.71 cr-
Principal sum and interest payable to financial institutions-Non Banking financial institution (NBFC)Rs 32.49 cr-
Payment of taxesRs 21.29 cr-
On-site expenditure-Site OverheadRs 7.80 cr-

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectManiraj D
EngineerArun Nadig

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionJun 2024 → Mar 2025

No reason recorded in the filing

Complaints filed with RERA Karnataka8

Case no.ComplainantRespondentFiled
CMP/220118/0008824-Shriprop Living Space Private Limited18/01/2022
CMP/220206/0008968-Shriprop Living Space Private Limited06/02/2022
00875/2024-Shriprop Living Space Private Limited12/09/2024
01055/2024-Shriprop Living Space Private Limited24/10/2024
01149/2025-Shriprop Living Space Private Limited09/09/2025
00286/2026-Shriprop Living Space Private Limited24/03/2026
00344/2026-Shriprop Living Space Private Limited06/04/2026
00364/2026-Shriprop Living Space Private Limited08/04/2026

Documents filed86

As listed on the registration, under the names the promoter filed them with; the newest 80 of 86 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/308/PR/190715/002689 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form4107 Southeast P2 Dec24 (1).pdf23 Mar 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form5Architect Certificate107Southeast P2Q320 (1).pdf23 Mar 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form6 Engineer QU 107SE P2 Q3 202425 (1).pdf23 Mar 2026
Q4 2025-26 Water supply and sewage board23 Mar 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)23 Mar 2026
Q4 2025-26 KPTCL- BESCOM23 Mar 2026
Q4 2025-26 Fire and Safety23 Mar 2026
Q4 2025-26 Airport Authority of India23 Mar 2026
Q4 2025-26 BSNL/Telecommunication Department23 Mar 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form4107 Southeast P2 Dec24 (1).pdf24 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form5Architect Certificate107Southeast P2Q320 (1).pdf24 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form6 Engineer QU 107SE P2 Q3 202425 (1).pdf24 Jan 2026
Q3 2025-26 Water supply and sewage board24 Jan 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)24 Jan 2026
Q3 2025-26 KPTCL- BESCOM24 Jan 2026
Q3 2025-26 Fire and Safety24 Jan 2026
Q3 2025-26 Airport Authority of India24 Jan 2026
Q3 2025-26 BSNL/Telecommunication Department24 Jan 2026
Enclosed affidavit for the renewed sanction plan and sanction letterFile: Affidavit and sanction plan.pdf27 Jan 2025
Enclosed the CA Certificate for Funds required for Project Completion.File: CA certificate - funds required Southeast 107 Phase 2 -Form Ext 4.pdf27 Jan 2025
Enclosed the CA Certificate for Funds UtilizedFile: CA certificate - fund utilized Southeast 107 P2-Form EXT 3.pdf27 Jan 2025
Enclosed the original copy of the Form Ex5 Engineer certificateFile: Form Ex5-Engg certificate-107SE P2 - work completed.pdf27 Jan 2025
Enclosed the original copy of the Form Ex6 Engineer certificateFile: form Ex6-Engg certificate-107SE P2- work pending.pdf27 Jan 2025
Enclosed the water supply NoCFile: Gramapanchay Water NOC 01082018.pdf27 Jan 2025
CertificateFile: 001 COI Shriprop Living Space.PDF-
Architect Certificate for Work Completion Schedule till DateFile: Arc certificate - work completed R2-compressed.pdf-
Engineer Certificate for Work Completion Schedule till DateFile: Form Ex5-Engg certificate-107SE P2 - work completed.pdf-
CA Certificate for Funds UtilizationFile: CA certificate - fund utilized Southeast 107 P2-Form EXT 3.pdf-
Architect Certificate for Pending Work Completion Schedule.File: Arc certificate - work pending R2-compressed.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: form Ex6-Engg certificate-107SE P2- work pending.pdf-
CA Certificate for Funds required for Project CompletionFile: CA certificate - funds required Southeast 107 Phase 2 -Form Ext 4.pdf-
AffidavitFile: Form Ex7.pdf-
Latest Encumbrance CertificateFile: EC for South East 107 From 09-08-2024 TO 30-11-2024.pdf-
Details Of Sold/ Un-sold UnitsFile: SoldUnsoldDetails as on Nov 2024-107Southeast Phase2.xlsx-
CC-
Drawing No 1 of 9 bldg 1 Site Plan-min-
Sanction plans-
Proforma Sale Deed - Guestline-
Proforma Agreement for Sale ;- Guestline-
017 Saledeed and RTC-
Drawing No 9 of 9 Bldg 1 Elevations and Sections-min-
DP-
Proforma allotment letter-
Project Specifications (107 SE P2)-
EC new 1-
Section 3(1) Affidavit-
107SEp2 Joint Affidavit-
026 Katha Cerificate-
107SE P2 JDA & GPA-
107SE P2 EC compressed-
030 Conversion order or change in land use-
055 RELINQUISHMENT DEED-
Fire-
Airport NOC-
BESCOM-
PCB-
SEIAA-
Sanction plans-
Drawing No 1 of 9 bldg 1 Site Plan-min-
Drawing No 9 of 9 Bldg 1 Elevations and Sections-min-
030 Conversion order or change in land use-
Balance Sheet 2017 - 2018File: 005 2017 Balance sheet.pdf-
Balance Sheet 2016 - 2017File: 005 2016 Balance sheet.pdf-
Balance Sheet 2015 - 2016File: 005 2015 Balance sheet.pdf-
Audited Profit and Loss Statement 2017 - 2018File: 006 2017 P&L.pdf-
Audited Profit and Loss Statement 2016 - 2017File: 006 2016 P&L.pdf-
Audited Profit and Loss Statement 2015 - 2016File: 006 2015 P&L.pdf-
Director's Report 2017 - 2018File: 007 Directors Report - Shriporp Living.pdf-
Director's Report 2016 - 2017File: 007 Directors Report - Shriporp Living.pdf-
Director's Report 2015 - 2016File: 007 Directors Report - Shriporp Living.pdf-
Cash Flow Statement 2017 - 2018File: 008 2017 Cash Flow.pdf-
Cash Flow Statement 2016 - 2017File: 008 2016 Cash Flow.pdf-
Auditor's Report 2017 - 2018File: 009 2017 AR Shriprop Living space.pdf-
Auditor's Report 2016 - 2017File: 009 2016 AR Financials-2016.pdf-
Auditor's Report 2015 - 2016File: 009 2015 AR Financials-2015.pdf-
Income Tax Return Acknowledgement 2017 - 2018File: 2017 ITR.pdf-
Income Tax Return Acknowledgement 2016 - 2017File: 2016 ITR.pdf-
Income Tax Return Acknowledgement 2015 - 2016File: 2015 ITR.pdf-
Form B-
Prospectus/BrochureFile: DCH brochure.pdf-

How this compares with Bengaluru Urban

100%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one moved by 9 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep SHRIRAM 107 SOUTHEAST - PHASE 2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmSHRIRAM 107 SOUTHEAST - Other 14Dot size: filed unitsN

Filed coordinates, straight-line distance. 14 registered projects within 2 km.

Builder: Shriprop Living Space Private Limited

Shriprop Living Space Private Limited has 3 registrations on RERA Karnataka, including SHRIRAM 107SOUTHEAST - PHASE 3 and SHRIRAM 107 SOUTHEAST. Its filings declare 2 earlier projects, none of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if SHRIRAM 107 SOUTHEAST - PHASE 2 is delayed beyond 14 Mar 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of SHRIRAM 107 SOUTHEAST - PHASE 2?

The registered promoter entity is Shriprop Living Space Private Limited, a company as per the filing. Its CIN U70109KA2014PTC076190 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in SHRIRAM 107 SOUTHEAST - PHASE 2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against SHRIRAM 107 SOUTHEAST - PHASE 2?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at SHRIRAM 107 SOUTHEAST - PHASE 2?

The professionals named in the filing: Architect: Maniraj D; Engineer: Arun Nadig. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHRIRAM 107 SOUTHEAST - PHASE 2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHRIRAM 107 SOUTHEAST - PHASE 2. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHRIRAM 107 SOUTHEAST - PHASE 2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.