Home / Browse projects / Sangli, Maharashtra / SHREE SIDDHIVINAYAK HEIGHTS

Completed No litigation declared Commercial project

SHREE SIDDHIVINAYAK HEIGHTS

By SURYAPRATAP PROMOTERS AND BUILDERS

RG-MH-16725 · RERA P53100027420 · Last updated on MahaRERA portal: 20 Jul 2024

Source: official MahaRERA filing

Red flags

  • Completion date moved by 21 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Sangli registration emailed to you, free during the pilot beta.
Mar 2025Possession promisedregistration recorded completed
2 of 11Construction stages donefurthest along: Sanitary Fittings within the flats /..., 70%
0Complaints at MahaRERAon this registration
Jump to the 44 documents Report an error

SHREE SIDDHIVINAYAK HEIGHTS is a Commercial project by SURYAPRATAP PROMOTERS AND BUILDERS in Sangli, Maharashtra, registered with MahaRERA as P53100027420 on 10 Dec 2020. The registration is recorded completed; possession was promised by 26 Mar 2025. The completion date has moved by 21 months from the original filing.

At a glance

Project

  • NameSHREE SIDDHIVINAYAK HEIGHTS
  • TypeCommercial
  • Location
    • MAHVEER NAGAR
    • VITA
    • Khanapur
    • Sangli
    • 415311
  • Pincode415311
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P53100027420
  • ReraGenie IDRG-MH-16725

Builder

  • NameSURYAPRATAP PROMOTERS AND BUILDERS
  • Entity typePartnership
  • PartnersGAURI PRASHANT JADHAV, PRATAP PANDHARINATH PATIL, PRANAV PRATAP PATIL, NAINA PRASANNA PATIL

Key dates

this monthRegisteredDec 2020First promiseJun 2023Revised toMar 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on10 Dec 2020
  • Promised completion26 Mar 2025
  • Revised completionRevised to 26 Mar 2025 (originally 1 Jun 2023)
  • Buildings1 building record
  • Documents filed44 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SHREE SIDDHIVINAYAK HEIGHTSNA70000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 20 Jul 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

2 of 11 construction stages are filed complete. The stage furthest along is Sanitary Fittings within the flats / premises, at 70%.

SHREE SIDDHIVINAYAK HEIGHTS: 44% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)3%
Podiums (if any)0%
Plinth3%
Stilt Floor0%
Slabs of Super Structure5%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises70%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.70%

Progress on shared amenities15

As on 20 Jul 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed2

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots2
Closed/Covered1
Open Space1

Land and ownership6

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,093 sq m
Land owned byThe promoter, with other names on the file
Named landowners6
LandownerVillageDistrict
SURYAPRATAP PROMOTERS AND BUILDERSPune (M Corp.)Pune
PRATAP PANDHARINATH PATILPune (M Corp.)Pune
PRANAV PRATAP PATILPune (M Corp.)Pune
NAINA PRASANNA PATILPune (M Corp.)Pune
PRASHANT PRASURAM JADHAVVita (M Cl)Sangli
GAURI PRASHANT JADHAVVita (M Cl)Sangli

Approvals and building plan

Permissible FSI1973.54
Proposed, not sanctioned1,974 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHIVAJI CHOWK VITA

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMOHAMMED ABU BAKER
EngineerMUKUL PARIKH
Chartered AccountantLAXMAN GAIKWAD
PartnerRole in project
SURYAPRATAP PROMOTERS AND BUILDERS-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT53100024380Jun 2023 → Nov 2024

Reason as filed by the promoterIn accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 83.33% allottees for purpose of extension of RERA registration period of the said project.

EXT53100017050Jun 2023 → May 2024

Reason as filed by the promoterRespected Sir/Madam, I am writing on behalf of Suryapratap Promoters and Developers, the developer responsible for the construction of the "Siddhivinayak Heights" project located at Vita, Sangli. We would like to bring to your attention the reasons for the delay in completing the construction and request an extension of the completion date until 30th May 2024. The delay in the completion of the project can be attributed to two significant factors, which have severely impacted our construction timeline: 1. Non-availability of CEO, Vita Municipal Council for approving sanctioned plan: Due to unf

EXT53100027954Jun 2023 → Mar 2025

Reason as filed by the promoterWe, M/s. Suryapratap Promoters and Builders, hereby declare the following with respect to the project Shree Siddhivinayak Heights bearing registration number. P53100027420 registered under MahaRERA. The delay in the completion of the real estate project has been primarily caused by a delay in OC. The project is 100% completed, we received the Occupation Certificate (OC) on 26th March 2025 and we have initiated the process for the possession as well, hence we won't be required to upload consents. To provide assurance and facilitate a smooth completion process, we are closely monitoring the rema

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 11 Oct 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 21 Oct 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 21 Oct 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 5 Aug 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed44

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - March 2024_compressed.pdf20 Jul 2024
Disclosure of sold/ booked inventoryFile: C - 29.pdf20 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: F3 - M24_compressed.pdf20 Jul 2024
Declaration about Commencement CertificateFile: Format D.pdf6 Jun 2024
Declaration in FORM BFile: Form B.pdf6 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Mar 24.pdf6 Jun 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23).pdf13 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: ACE Scanner_2023_08_19-1.pdf1 Sep 2023
Declaration in FORM BFile: AFFIDAVIT CUM DECLARATION-1.pdf30 Aug 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Surya Pratap rera form 2-1-2.pdf30 Aug 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Surya Pratap rera form 2-3-4.pdf30 Aug 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Surya Pratap rera form 2.pdf30 Aug 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: ACE Scanner_2023_08_19.pdf28 Aug 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: ACE Scanner_2023_08_19(1).pdf28 Aug 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: ACE Scanner_2023_08_19(2).pdf25 Aug 2023
Commencement Certificates / NA Order for plotted developmentFile: CENTRAL REVISED PERMISSION CERT_230805_095613.pdf5 Aug 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A_230805_160928.pdf5 Aug 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: RAW-3.pdf5 Aug 2023
Declaration in FORM BFile: Affidavit cum Declaration.pdf4 Aug 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate.pdf4 Aug 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SCAN_20230704_190024650_230804_134200.pdf4 Aug 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Quality Assurance Certificate.pdf4 Aug 2023
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD.pdf4 Aug 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: shree siddhivinayak heights certificate.pdf4 Aug 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 20-21.pdf4 Aug 2023
Details of encumbrances concerned to FinanceFile: NO ENCUMBRANCE CERTIFICATE.pdf7 Jul 2023
Details of encumbrances concerned to LegalFile: NO ENCUMBRANCE CERTIFICATE.pdf7 Jul 2023
Declaration about Commencement CertificateFile: DECLARATION_ABOUT_COMMENCEMENT_CERTIFICATE[1].pdf7 Jul 2023
CERSAI detailsFile: No Charge.pdf7 Jul 2023
Proforma of Agreement for saleFile: Agreement to Sale.pdf7 Jul 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration Separate Bank Account.pdf7 Jul 2023
Deviation Report with respect to Allotment letterFile: No Deviation Allotment.pdf7 Jul 2023
Deviation Report with respect to model copy of AgreementFile: No Deviation Agreement.pdf7 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE FOR SURYAPRATAP DEV.pdf27 Nov 2020
Proforma of Allotment letterFile: 2 SURYAPRATAP ALLOTEMENT LETTER.pdf27 Nov 2020
Layout approvalFile: Copy of Layout Approval Suryapratap .pdf21 Oct 2020
Building plan approvalFile: BUILDING PLAN APPROVALSURYAPRATAP.pdf21 Oct 2020
Copy of Layout Approval (in case of layout)File: Copy of Layout Approval Suryapratap .pdf21 Oct 2020
Building Plan Approval / NA Order for plotted developmentFile: BUILDING PLAN APPROVALSURYAPRATAP.pdf21 Oct 2020
Commencement Certificates / NA Order for plotted developmentFile: commencement certificate Suryapratap.pdf21 Oct 2020
PAN CardFile: Suryapratap PAN.pdf14 Oct 2020
Copy of the legal title reportFile: Suryapratap Search Report-compressed.pdf11 Oct 2020
Details of encumbrancesFile: Suryapratap Encumbrance .pdf11 Oct 2020
Declaration in FORM BFile: Declaration Form B Suryaoratap-compressed.pdf11 Oct 2020

How this compares with Sangli

11%of Sangli projects moved their completion datethis one moved by 21 months
29%of Sangli registrations have lapsed or been cancelledthis one is completed

Computed across the 790+ Sangli projects on ReraGenie, from their own filings.

Keep SHREE SIDDHIVINAYAK HEIGHTS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near VITA790+ in Sangli

2 kmSHREE SIDDHIVINAYAK HEIGCompleted 15Lapsed / revoked 12Dot size: filed unitsN

Filed coordinates, straight-line distance. 27 registered projects within 2 km.

Builder: SURYAPRATAP PROMOTERS AND BUILDERS

SURYAPRATAP PROMOTERS AND BUILDERS has 1 registration on MahaRERA, including SHREE SIDDHIVINAYAK HEIGHTS. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Sangli district page.

Frequently asked questions

What are my rights if SHREE SIDDHIVINAYAK HEIGHTS is delayed beyond 26 Mar 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SHREE SIDDHIVINAYAK HEIGHTS?

The registered promoter entity is SURYAPRATAP PROMOTERS AND BUILDERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SHREE SIDDHIVINAYAK HEIGHTS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SHREE SIDDHIVINAYAK HEIGHTS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SHREE SIDDHIVINAYAK HEIGHTS?

The professionals named in the filing: Architect: MOHAMMED ABU BAKER; Engineer: MUKUL PARIKH; Chartered Accountant: LAXMAN GAIKWAD. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHREE SIDDHIVINAYAK HEIGHTS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHREE SIDDHIVINAYAK HEIGHTS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHREE SIDDHIVINAYAK HEIGHTS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.