ReraGenieLog inGet a buyer report

Home / Browse projects / Gandhinagar, Gujarat / SHREE NILAY VILLA

Valid until 31 Jul 2027 Residential/Group Housing project

SHREE NILAY VILLA

By SM BUILDCON

RG-GJ-51230 · RERA PR/GJ/GANDHINAGAR/MANSA/Mansa Municipality/RAA15942/011025/310327 · Last updated on GujRERA portal: 22 May 2026

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Jul 2027Possession promisedno revision filed
7 of 9Construction stages donefurthest along: Installation of lifts, 70%
10 of 12Units unsoldnot recorded sold or booked
Jump to the 35 documents Report an error

SHREE NILAY VILLA is a Residential/Group Housing project by SM BUILDCON in Gandhinagar, Gujarat, registered with GujRERA as PR/GJ/GANDHINAGAR/MANSA/Mansa Municipality/RAA15942/011025/310327 on 1 Oct 2025. Possession is promised by 31 Jul 2027. 2 of the 12 units on this registration are recorded sold or booked, and 7 of 9 construction stages are filed complete.

At a glance

Project

  • NameSHREE NILAY VILLA
  • TypeResidential/Group Housing
  • Location
    • C.S.NO. NA1085/2
    • OLD R.S.NO. 1085/2
    • VILLGE:- MANSA
    • TA. MANSA
    • DIST. GANDHINAGAR.
    • MANSA
    • Gandhinagar
    • 382845
  • Pincode382845
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/GANDHINAGAR/MANSA/Mansa Municipality/RAA15942/011025/310327
  • ReraGenie IDRG-GJ-51230

Builder

  • NameSM BUILDCON
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredOct 2025PromisedJul 2027

Key facts

Registration and timeline

  • StatusValid until 31 Jul 2027
  • Registered on1 Oct 2025
  • Promised completion31 Jul 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed35 files

Current status

17%2 of 12 units booked
96.9%Of the estimated cost spent so far

Figures as on 22 May 2026, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUNGLOW (1 TO 12)---12012

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 22 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 9 construction stages are filed complete. The stage furthest along is Installation of lifts, at 70%.

BUNGLOW (1 TO 12): 86% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing70%

Progress on shared amenities19

As on 22 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes50%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes50%
Street lightingYes50%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes100%
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes50%
Fire fightingNoNot applicable
Drinking water facilitiesYes80%
Emergency evacuationNoNot applicable
Use of renewable energyYes30%
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,224 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 1.60 cr
Cost incurredRs 1.55 cr
Spent of the estimate96.88%
BuildingWingEstimatedIncurred
BUNGLOW (1 TO 12)NARs 1.60 crRs 1.55 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDHAVAL NATUBHAI MEWADA
EngineerNITINKUMAR PATEL

Documents filed35

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/GANDHINAGAR/MANSA/Mansa Municipality/RAA15942/011025/310327 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)22 May 2026
Engineer's certificate (Form 2)21 May 2026
Engineer's certificate annexure21 May 2026
Architect's certificate (Form 1)11 May 2026
Site photograph, BUNGLOW (1 TO 12)11 May 2026
Site photograph, BUNGLOW (1 TO 12)11 May 2026
RERA registration certificate1 Oct 2025
Proforma agreement for sale-
Auditor's report (3 of 3)-
Income tax return (3 of 3)-
Project specific document-
Drainage affidavit-
Directors' report (3 of 3)-
Approved sanctioned plan-
Approved layout plan-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Declaration in Form B-
Declaration in Form B1-
Declaration in Form B2-
Approved building or plotting plan-
NOCs from authorities-
Title clearance certificate-
Title report-
Property card-
Statutory document-
Other document-
Project photograph-
Proforma sale deed-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (3 of 3)-

How this compares with Gandhinagar

17%of this project is bookeddistrict median 53%
16%of Gandhinagar projects moved their completion datethis one has not

Computed across the 1,600+ Gandhinagar projects on ReraGenie, from their own filings.

Keep SHREE NILAY VILLA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near MANSA1,600+ in Gandhinagar

2 kmSHREE NILAY VILLAOther 25Dot size: filed unitsN

Filed coordinates, straight-line distance. 25 registered projects within 2 km.

Builder: SM BUILDCON

SM BUILDCON has 1 registration on GujRERA, including SHREE NILAY VILLA. Read the full track record. See more projects on the Gandhinagar district page.

Frequently asked questions

What are my rights if SHREE NILAY VILLA is delayed beyond 31 Jul 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of SHREE NILAY VILLA?

The registered promoter entity is SM BUILDCON, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in SHREE NILAY VILLA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SHREE NILAY VILLA?

The professionals named in the filing: Architect: DHAVAL NATUBHAI MEWADA; Engineer: NITINKUMAR PATEL. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHREE NILAY VILLA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHREE NILAY VILLA. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHREE NILAY VILLA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.