ReraGenieLog inGet a buyer report

Home / Browse projects / Bengaluru Urban, Karnataka / SHREE NANDANA ELITE

Registration approved No litigation declared Residential/Group Housing project

SHREE NANDANA ELITE

By SHREE NANDANA BUILDERS

RG-KA-19975 · RERA PRM/KA/RERA/1251/308/PR/080922/005225 · Last updated on RERA Karnataka portal: 5 Sep 2022

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Jun 2026Possession promisedno revision filed
0Complaints at RERA Karnatakaon this registration
Jump to the 101 documents Report an error

SHREE NANDANA ELITE is a Residential/Group Housing project by SHREE NANDANA BUILDERS in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/308/PR/080922/005225 on 8 Sep 2022. Possession is promised by 1 Jun 2026.

At a glance

Project

  • NameSHREE NANDANA ELITE
  • TypeResidential/Group Housing
  • Location
    • Anekal
    • Bengaluru Urban
    • 560105
  • Pincode560105
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/308/PR/080922/005225
  • ReraGenie IDRG-KA-19975

Builder

  • NameSHREE NANDANA BUILDERS
  • Entity typePartnership Firm
  • GSTIN29AENFS5656K1Z4
  • Authorized SignatoryM Sudhakar

Key dates

this monthRegisteredSep 2022PromisedJun 2026

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on8 Sep 2022
  • Promised completion1 Jun 2026
  • Revised completionNone
  • Buildings1 building record
  • Documents filed101 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower 1---68068

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 5 Sep 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Upto Plinth Level-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
Retaining wall (All types)-
RCC or MS Framed structure-
Masonry Construction-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Painting-
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)-
Wardrobe, Showcase, Kitchen cabinet, Puja work-
Elevation work-
Internal and External work including landscapes as per sanctioned drawings-

Progress on shared amenities40

As on 5 Sep 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Sewage and Drainage SystemYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalNoNot applicable
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsNoNot applicable
Electricity supply transformer and substationYes-
Storm water drainsYes-
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes-
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupNoNot applicable
Piped GasNoNot applicable
Water and SanitationNoNot applicable
Air ConditioningNoNot applicable
StaircasesYes-
LiftsYes-
Corridor/LobbiesYes-
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahNoNot applicable
BasementNoNot applicable
TerraceYes-
Outer WallYes-
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,395 sq m
Named landowners1
LandownerVillageDistrict
Danunjaya Reddy.P--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 12.21 cr
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 12.21 cr-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSantosh
EngineerSrinivasa Rao Bolimunta
Chartered AccountantA. Subramanyam Reddy

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed101

As listed on the registration, under the names the promoter filed them with; the newest 80 of 101 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/308/PR/080922/005225 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Water supply NocFile: Water supply Noc.pdf5 Sep 2022
Borewell PictureFile: Borewell Picture.jpeg5 Sep 2022
Borewell ReportFile: Borewell Report.jpeg5 Sep 2022
Partnership Deed AmendmentFile: Partnership Deed Amend.pdf5 Sep 2022
Local Authority Permission LetterFile: Local Authority Permission Letter.pdf5 Sep 2022
Local Authority Permission_Fees PaidFile: Local Authority Permission_Fees Paid.pdf5 Sep 2022
hissa phody copyFile: Hissa Phody.pdf20 Aug 2022
proforma of Agreement for saleFile: AOS.pdf20 Aug 2022
architect detailsFile: Architect License.pdf20 Aug 2022
building licenseFile: Building License Declartion.pdf20 Aug 2022
change of landFile: CLU.jpeg20 Aug 2022
Architect CertificateFile: ARCHITECT CERTIFICATE.pdf20 Aug 2022
Addendum Partnership DeedFile: Addendum Partnership Deed.pdf20 Aug 2022
MR for syno82/2File: MRT3.jpeg30 Jul 2022
joint affidavit cum decalartionsFile: JDA Affidavit.pdf30 Jul 2022
title deed to k r sridharFile: Title Deed K Sridhar.pdf30 Jul 2022
partnership deedFile: Partnership Deed.pdf30 Jul 2022
relinquishment deed for PRRFile: Relinqueshment deed Affidavit.pdf30 Jul 2022
building licenseFile: Building License.pdf30 Jul 2022
village map demarcationFile: village map.pdf30 Jul 2022
commencement certificateFile: Commencement certificate.pdf30 Jul 2022
Form 3 Engineer CertificateFile: FORM 3 Enginner.pdf30 Jul 2022
project specification.File: Project Specification.pdf30 Jul 2022
Brochure of Current ProjectFile: Brochure NA.pdf30 Jul 2022
Agreement for saleFile: AOS.pdf30 Jul 2022
RTC, survey 82/2-
Mutation, survey 82/2-
Encumbrance Certificate, survey 82/2-
Conversion/Alienation Order, survey 82/2-
Sale/Title/Gift Deed, survey 82/2-
JDA, survey 82/2-
Khatha, survey 82/2-
Registration CertificateFile: Firm Registration Certificate.pdf-
Partnership DeedFile: Partnership Deed.pdf-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Certificate issued by CA Form 1File: CA CERTIFICATE.pdf-
Certificate issued by Architect Form 2File: ARCHITECT CERTIFICATE.pdf-
Certificate issued by Engineer Form 3File: Engineer Certificate.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: No Litigation.pdf-
Certificate from Chartered AccountFile: CA CERTIFICATE.pdf-
Balance Sheet 2020 - 2021File: BS 2022.pdf-
Audited Profit and Loss Statement 2020 - 2021File: PL 2022.pdf-
Income Tax Return Acknowledgement 2020 - 2021File: ITR 2022_23.pdf-
Commencement Certificate-
BESCOM NOC-
Water supply Noc-
Building Plan-
Building Plan and specification-
Building Plan-
Project Specification-
CDP PLAN-
Stability certificate-
Legal Report-
Agreement to sale-Draft-
Allotment Letter (1)-
FORM-B-
Section 3 Affidavit-
JDA Affidavit-
BESCOM NOC-
Water supply Noc-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep SHREE NANDANA ELITE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmSHREE NANDANA ELITEOther 16Dot size: filed unitsN

Filed coordinates, straight-line distance. 16 registered projects within 2 km.

Builder: SHREE NANDANA BUILDERS

SHREE NANDANA BUILDERS has 1 registration on RERA Karnataka, including SHREE NANDANA ELITE. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if SHREE NANDANA ELITE is delayed beyond 1 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of SHREE NANDANA ELITE?

The registered promoter entity is SHREE NANDANA BUILDERS, a partnership firm as per the filing. Its GSTIN 29AENFS5656K1Z4 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in SHREE NANDANA ELITE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SHREE NANDANA ELITE?

The professionals named in the filing: Architect: Santosh; Engineer: Srinivasa Rao Bolimunta; Chartered Accountant: A. Subramanyam Reddy. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHREE NANDANA ELITE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHREE NANDANA ELITE. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHREE NANDANA ELITE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.