Home / Browse projects / Nandurbar, Maharashtra / SHREE GANESH CROWN

Registration lapsed No litigation declared Others project

SHREE GANESH CROWN

By PRAKASH RAMAN CHAUDHARI

RG-MH-13466 · RERA P49700025399 · Last updated on MahaRERA portal: 15 Apr 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 16 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nandurbar registration emailed to you, free during the pilot beta.
Jun 2025Possession promised16 months past this date
4 of 11Construction stages donefurthest along: Staircases, 90%
27 of 34Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 71 documents Report an error

SHREE GANESH CROWN is a Others project by PRAKASH RAMAN CHAUDHARI in Nandurbar, Maharashtra, registered with MahaRERA as P49700025399 on 21 May 2020. Possession was promised by 30 Jun 2025 and is now 16 months past that date. 7 of the 34 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete.

At a glance

Project

  • NameSHREE GANESH CROWN
  • TypeOthers
  • Location
    • DONDAICHA KHETIYA DIVERSION ROAD
    • RAMAN NAGAR
    • OPP. BHAU TATYA PETROL PUMP
    • Shahade (r)
    • Shahade
    • Nandurbar
    • 425409
  • Pincode425409
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P49700025399
  • ReraGenie IDRG-MH-13466

Builder

  • NamePRAKASH RAMAN CHAUDHARI
  • Entity typeIndividual
  • Other registrations10 more →
  • Completed7 of 11
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects9 →

Key dates

16 months past promisethis monthRegisteredMay 2020PromisedJun 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on21 May 2020
  • Promised completion30 Jun 2025
  • Revised completionNone
  • Buildings1 building record
  • Documents filed71 files

Current status

21%7 of 34 units booked

Figures as on 15 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SHREE GANESH CROWNNA44241034

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 15 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 90%.

SHREE GANESH CROWN: 72% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises85%
Sanitary Fittings within the flats / premises75%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%

Progress on shared amenities15

As on 15 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes50%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed17

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots17
Open Space17

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,455 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on22 Sep 2025

Approvals and building plan

Sanctioning authoritySub Divisional Officer, Shahada Part
Permissible FSI2036.98
Proposed, not sanctioned1,919 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchFIRST FLOOR, SK OPEN MALL, COLLEGE ROAD, NASHIK 422005

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVINIT PRAKASH CHAUDHARI
EngineerSTRUCON DESIGNERS PVT LTD THROUGH ER RAJENDRA B CHOPDA
EngineerVinit Chaudhari
Chartered AccountantAMOL MISHRA
Chartered AccountantRSPH and Associates
Chartered AccountantP N Sabadra and Associates
PartnerRole in project
PRAKASH RAMAN CHAUDHARI-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 13 May 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 13 May 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 13 May 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 13 May 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed71

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2023-2024)File: 2A SGCrown Mar 24.pdf15 Apr 2026
Form 2A (FY 2024-2025)File: 2A SGCrown Mar 25.pdf15 Apr 2026
Form 5 (FY 2024-2025)File: RERA audit report -Ganesh cresent24-25-Final.pdf25 Dec 2025
Form 5 (FY 2023-2024)File: Shree Ganesh Crown - Audit Report 23-24.pdf4 Oct 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Shree Ganesh Crown - Audit Report 23-24.pdf5 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AR CERT -.pdf26 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Er Certificate - S G Crown - Q1 - Apr 24 to June 24.pdf26 Jul 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory - Shree Ganesh Crown - JUNE 24.pdf26 Jul 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory -.pdf26 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Prakash Crown jun 24_compressed (1).pdf26 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ar Certificate S G Crown - Dec 23-pages-deleted.pdf20 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Mar'24 Crown.pdf20 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate- Mar 24 Crown.pdf20 Apr 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory - Shree Ganesh Crown - DEC 23.pdf20 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate-March 24 Crown.pdf20 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ar Certificate S G Crown - Dec 23.pdf20 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Eng Certificate S G Crown.pdf20 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate S G Crown - Dec 23.pdf20 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Shree Ganesh Crown.pdf22 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate-Sep 23 Crown.pdf25 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Er Certificate S G Crown Sept 23.pdf20 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate - S G Crown - Sept 23.pdf20 Oct 2023
Disclosure of sold/ booked inventoryFile: Disclosure Sold Booked Interntory - S G Crown - June 23.pdf9 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate S G Crown FY 23-24-Q1.pdf23 Sep 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate S G Crown FY 23-24 Q1.pdf23 Sep 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate June'23.pdf23 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ar certificate crown- Mar'23.pdf22 Aug 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Er certificate crown- Mar'23.pdf22 Aug 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate crown Mar'23.pdf22 Aug 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SG Crown June 22 CA Signed Copy.pdf10 Aug 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SG Crown Sept 22 CA Signed Copy.pdf10 Aug 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SG Crown Dec 22 CA Signed Copy.pdf10 Aug 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SG Crown AR Sept 22.pdf7 Jun 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SG Crown AR Dec 22.pdf7 Jun 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SG Crown June 22 CA Signed Copy compressed.pdf7 Jun 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SG Crown Sept 22 CA Signed Copy compressed.pdf7 Jun 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SG Crown Dec 22 CA Signed Copy compressed.pdf7 Jun 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SG Crown AR June 22.pdf6 Jun 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SG Crown ER June 22.pdf6 Jun 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SG Crown ER Sept 22.pdf6 Jun 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SG Crown ER Dec 22.pdf6 Jun 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ar Certificate - S G Crown - 12-21.pdf28 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ar Certificate - S G Crown - 03-22.pdf28 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Er Certificate - S G Crown - 03-21.pdf28 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Er Certificate - S G Crown - 06-21.pdf28 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Er Certificate - S G Crown - 09-21.pdf28 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Er Certificate - S G Crown - 09-21.pdf28 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Er Certificate - S G Crown - 03-22.pdf28 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Shree ganesh crown 3 CA.pdf28 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Shree Ganesh Crown -5 CA.pdf28 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Shree ganesh crown2 CA.pdf28 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Shree Ganesh Crown-4 CA.pdf28 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Shree Ganesh Crown-6 CA.pdf28 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Shree ganesh crown AR.pdf28 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Shree ganesh Crown 1 AR.pdf28 Feb 2023
Layout approvalFile: Layout Order.pdf13 May 2020
Layout approvalFile: Layout Plan.pdf13 May 2020
Building plan approvalFile: Building Permission.pdf13 May 2020
Building plan approvalFile: SG Crown - Optimized.pdf13 May 2020
PAN CardFile: PAN Card - PRC.pdf13 May 2020
Copy of the legal title reportFile: Title Report.pdf13 May 2020
Details of encumbrancesFile: Affidavit.pdf13 May 2020
Copy of Layout Approval (in case of layout)File: Layout Order.pdf13 May 2020
Copy of Layout Approval (in case of layout)File: Layout Plan.pdf13 May 2020
Building Plan Approval / NA Order for plotted developmentFile: Building Permission.pdf13 May 2020
Building Plan Approval / NA Order for plotted developmentFile: SG Crown - Optimized.pdf13 May 2020
Commencement Certificates / NA Order for plotted developmentFile: Building Permission.pdf13 May 2020
Declaration in FORM BFile: Form B.pdf13 May 2020
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate.pdf13 May 2020
Proforma of Allotment letterFile: Agreement.pdf13 May 2020
Proforma of Allotment letterFile: Allotment Letter.pdf13 May 2020

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationRegisteredStatusPromisedDelivered
SHREE GANESH IMPERIALP49700008973Shahade (r), NandurbarAug 2017CompletedJul 2019Nov 2018

Keep SHREE GANESH CROWN on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near RAMAN NAGAR, OPP. BHAU TATYA PETROL PUMP17 in Nandurbar

Builder: PRAKASH RAMAN CHAUDHARI

PRAKASH RAMAN CHAUDHARI has 11 registrations on MahaRERA, including SHREE GANESH IMPERIAL and GENESIS. Its filings disclose 9 earlier MahaRERA projects: declares 8 of 8 past projects completed on time. Read the full track record. See more projects on the Nandurbar district page.

Frequently asked questions

What does it mean that SHREE GANESH CROWN shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if SHREE GANESH CROWN is delayed beyond 30 Jun 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SHREE GANESH CROWN?

The registered promoter entity is PRAKASH RAMAN CHAUDHARI, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SHREE GANESH CROWN?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SHREE GANESH CROWN?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SHREE GANESH CROWN?

The professionals named in the filing: Architect: VINIT PRAKASH CHAUDHARI; Engineer: STRUCON DESIGNERS PVT LTD THROUGH ER RAJENDRA B CHOPDA; Engineer: Vinit Chaudhari; Chartered Accountant: AMOL MISHRA; Chartered Accountant: RSPH and Associates; Chartered Accountant: P N Sabadra and Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHREE GANESH CROWN?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHREE GANESH CROWN. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHREE GANESH CROWN to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.