ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / SHREE BALAJI AVENUE

Registered No litigation declared Residential / Group Housing project

SHREE BALAJI AVENUE

By SHREE BALAJI & CO

RG-MH-54896 · RERA P51800047192 · Last updated on MahaRERA portal: 13 Jun 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 18 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 18 months from the original
2 of 11Construction stages donefurthest along: Internal walls, 95%
6 of 11Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 86 documents Report an error

SHREE BALAJI AVENUE is a Residential / Group Housing project by SHREE BALAJI & CO in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800047192 on 11 Oct 2022. Possession is promised by 31 Dec 2026. The completion date has moved by 18 months from the original filing. 5 of the 11 units on this registration are recorded sold or booked, and 2 of 11 construction stages are filed complete.

At a glance

Project

  • NameSHREE BALAJI AVENUE
  • TypeResidential / Group Housing
  • Location
    • CHITTRANJAN NAGAR RAJAWADI
    • GHATKOPAR EAST MUMBAI
    • Kurla
    • Mumbai Suburban
    • 400077
  • Pincode400077
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800047192
  • ReraGenie IDRG-MH-54896

Builder

  • NameSHREE BALAJI & CO
  • Entity typePartnership
  • PartnersKISHOR RATANSI PATEL, RAMESH HANSRAJ PATEL

Key dates

this monthRegisteredOct 2022First promiseJun 2025Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on11 Oct 2022
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 30 Jun 2025)
  • Buildings1 building record
  • Documents filed86 files

Current status

45%5 of 11 units booked
95.1%Work done, per cost certificate

Figures as on 13 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SHREE BALAJI AVENUENA4411011

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 13 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

2 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 95%.

SHREE BALAJI AVENUE: 58% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor90%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises85%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks85%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.85%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 13 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed8

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots8
Closed/Covered4
Open Space4

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area239 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on13 Jun 2026

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI645.3
Proposed, not sanctioned201 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGHATKOPAR EAST MUMBAI 400077
Estimated costRs 3.21 cr
Cost incurredRs 3.05 cr
Work done95.09%
BuildingWingEstimatedIncurred
SHREE BALAJI AVENUENARs 2.92 crRs 2.80 cr
-NARs 29.16 lakhRs 25.00 lakh

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectEastern Architects Mr Jagat P. Vasani
EngineerTrekkbench Structural Engineers & Consultants Mr Bhavesh Patel
Chartered AccountantS K Parasiya & Co Mr Shantilal Parasiya
Chartered AccountantPREMAL & KIRAN
PartnerRole in project
SHREE BALAJI & CO-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA21022619946Jun 2025 → Dec 2026

Reason as filed by the promoterDUE TO SHORTAGE OF FUNDS WORK COULD NOT BE COMPLETED ON TIME BUT NOW WORK IS ABOUT TO GET COMPLETE . SO WE NEED EXTENSION TILL 31.12.2026

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 19 Sep 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 12 Aug 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 22 Aug 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 19 Sep 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed86

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 86 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1__Shree Balaji Avenue_SEP 25.pdf13 Jun 2026
Withdrawal Update Form 1File: Form 1__Shree Balaji Avenue_DEC 25.pdf13 Jun 2026
Withdrawal Update Form 1File: Form 1__Shree Balaji Avenue_MARCH 26.pdf13 Jun 2026
Withdrawal Update Form 1File: Form 1__Shree Balaji Avenue_MARCH 26.pdf13 Jun 2026
Withdrawal Update Form 2File: Form 2__Shree Balaji Avenue_SEP 25.pdf13 Jun 2026
Withdrawal Update Form 2File: Form 2__Shree Balaji Avenue_DEC 25.pdf13 Jun 2026
Withdrawal Update Form 2File: Form 2__Shree Balaji Avenue_MARCH 26.pdf13 Jun 2026
Withdrawal Update Form 2File: Form 2__Shree Balaji Avenue_MARCH 26.pdf13 Jun 2026
Withdrawal Update Form 3File: FORM-3_SEPT 2025.pdf13 Jun 2026
Withdrawal Update Form 3File: FORM-3_DEC 2025.pdf13 Jun 2026
Withdrawal Update Form 3File: Form 3__Shree Balaji Avenue_MARCH 26.pdf13 Jun 2026
Withdrawal Update Form 3File: Form 3__Shree Balaji Avenue_MARCH 26.pdf13 Jun 2026
Withdrawal Update Form 1File: Q1 Jun 2025 Form 1.pdf18 Feb 2026
Withdrawal Update Form 2File: Q1 Jun 2025 Form 2.pdf18 Feb 2026
Withdrawal Update Form 3File: Q1 Jun 2025 Form 3.pdf18 Feb 2026
Form 1File: Q3 Dec 2022 Form 1.pdf11 Feb 2026
Form 2File: Q3 Dec 2022 Form 2.pdf11 Feb 2026
Form 3File: Q3 Dec 2022 Form 3.pdf11 Feb 2026
Disclosure of Sold and Booked InventoryFile: Q3 22-23 Inventory Disclosure.pdf11 Feb 2026
Form 1File: Q4 Mar 2023 Form 1.PDF11 Feb 2026
Form 2File: Q4 Mar 2023 Form 2.pdf11 Feb 2026
Form 3File: Q4 Mar 2023 Form 3.pdf11 Feb 2026
Disclosure of Sold and Booked InventoryFile: Q4 22-23 Inventory Disclosure.pdf11 Feb 2026
Form 2A (FY 2022-2023)File: 22-23 Form-2A SBC.pdf11 Feb 2026
Form 2A (FY 2023-2024)File: 23-24 Form-2A SBC.pdf11 Feb 2026
Form 2A (FY 2024-2025)File: 24-25 Form-2A SBC.pdf11 Feb 2026
Form 5 (FY 2024-2025)File: FY 24-25 Form 5.pdf7 Feb 2026
Form 5 (FY 2022-2023)File: FY 22-23 Form 5.pdf6 Feb 2026
Form 5 (FY 2023-2024)File: FY 23-24 Form 5.pdf6 Feb 2026
Form 1File: Q1 Jun 2023 Form 1.pdf26 Jan 2026
Form 2File: Q1 Jun 2023 Form 2.pdf26 Jan 2026
Form 3File: Q1 Jun 2023 Form 3.pdf26 Jan 2026
Disclosure of Sold and Booked InventoryFile: Rera Quaterly Disclosure Of Inventory.pdf26 Jan 2026
Form 1File: Q2 Sep 2023 Form 1.PDF26 Jan 2026
Form 2File: Q2 Sep 2023 Form 2.pdf26 Jan 2026
Form 3File: Q2 Sep 2023 Form 3.pdf26 Jan 2026
Disclosure of Sold and Booked InventoryFile: Rera Quaterly Disclosure Of Inventory.pdf26 Jan 2026
Form 1File: Q3 Dec 2023 Form 1.pdf26 Jan 2026
Form 2File: Q3 Dec 2023 From 2.pdf26 Jan 2026
Form 3File: Q3 Dec 2023 Form 3.pdf26 Jan 2026
Disclosure of Sold and Booked InventoryFile: Rera Quaterly Disclosure Of Inventory.pdf26 Jan 2026
Form 1File: Q4 Mar 2024 Form 1.pdf26 Jan 2026
Form 2File: Q4 Mar 2024 Form 2.pdf26 Jan 2026
Form 3File: Q4 Mar 2024 Form 3.pdf26 Jan 2026
Disclosure of Sold and Booked InventoryFile: Rera Quaterly Disclosure Of Inventory.pdf26 Jan 2026
Form 1File: Q1 Jun 2024 Form 1.pdf26 Jan 2026
Form 2File: Q1 Jun 2024 Form 2.pdf26 Jan 2026
Form 3File: Q1 Jun 2024 Form 3.pdf26 Jan 2026
Disclosure of Sold and Booked InventoryFile: Rera Quaterly Disclosure Of Inventory.pdf26 Jan 2026
Form 1File: Q2 Sep 2024 Form 1.pdf26 Jan 2026
Form 2File: Q2 Sep 2024 Form 2.pdf26 Jan 2026
Form 3File: Q2 Sep 2024 Form 3.pdf26 Jan 2026
Disclosure of Sold and Booked InventoryFile: Rera Quaterly Disclosure Of Inventory.pdf26 Jan 2026
Form 1File: Q3 Dec 2024 Form 1.pdf26 Jan 2026
Form 2File: Q3 Dec 2024 Form 2.pdf26 Jan 2026
Form 3File: Q3 Dec 2024 Form 3.pdf26 Jan 2026
Disclosure of Sold and Booked InventoryFile: Rera Quaterly Disclosure Of Inventory.pdf26 Jan 2026
Form 1File: Q4 Mar 2025 Form 1.pdf26 Jan 2026
Form 2File: Q4 Mar 2025 Form 2.pdf26 Jan 2026
Form 3File: Q4 Mar 2025 Form 3.pdf26 Jan 2026
Disclosure of Sold and Booked InventoryFile: Rera Quaterly Disclosure Of Inventory.pdf26 Jan 2026
Form 1File: Q1 Jun 2025 Form 1.pdf26 Jan 2026
Form 2File: Q1 Jun 2025 Form 2.pdf26 Jan 2026
Form 3File: Q1 Jun 2025 Form 3.pdf26 Jan 2026
Disclosure of Sold and Booked InventoryFile: Rera Quaterly Disclosure Of Inventory.pdf26 Jan 2026
Copy of the legal title reportFile: Legal Title Report.pdf19 Sep 2022
Details of encumbrances concerned to LegalFile: No Encumberance Letter_Legal.pdf19 Sep 2022
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf19 Sep 2022
Proforma of Allotment letterFile: Draft allotment letter.pdf19 Sep 2022
Proforma of Allotment letterFile: Draft Agreement.pdf19 Sep 2022
Deviation Report with respect to Allotment letterFile: Declaration for No Deviation.pdf19 Sep 2022
Deviation Report with respect to model copy of AgreementFile: Declaration for No Deviation.pdf19 Sep 2022
Details of encumbrances concerned to FinanceFile: Self Declaration for Encumbrances.pdf29 Aug 2022
CERSAI detailsFile: CERSAI Search Report.pdf29 Aug 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf29 Aug 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank Declaration Format A.pdf29 Aug 2022
Building plan approvalFile: Plan Copy.pdf22 Aug 2022
Building Plan Approval / NA Order for plotted developmentFile: Plan Copy.pdf22 Aug 2022
Declaration in FORM BFile: Form B.pdf22 Aug 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf20 Aug 2022

How this compares with Mumbai Suburban

45%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 18 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SHREE BALAJI AVENUE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near GHATKOPAR EAST MUMBAI6,700+ in Mumbai Suburban

2 kmSHREE BALAJI AVENUECompleted 136Lapsed / revoked 107Other 153Dot size: filed unitsN

Filed coordinates, straight-line distance. 396 registered projects within 2 km.

Builder: SHREE BALAJI & CO

SHREE BALAJI & CO has 1 registration on MahaRERA, including SHREE BALAJI AVENUE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if SHREE BALAJI AVENUE is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SHREE BALAJI AVENUE?

The registered promoter entity is SHREE BALAJI & CO, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SHREE BALAJI AVENUE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SHREE BALAJI AVENUE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SHREE BALAJI AVENUE?

The professionals named in the filing: Architect: Eastern Architects Mr Jagat P. Vasani; Engineer: Trekkbench Structural Engineers & Consultants Mr Bhavesh Patel; Chartered Accountant: S K Parasiya & Co Mr Shantilal Parasiya; Chartered Accountant: PREMAL & KIRAN. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHREE BALAJI AVENUE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHREE BALAJI AVENUE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHREE BALAJI AVENUE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.