Home / Browse projects / Bengaluru Urban, Karnataka / SHIVAGANGA AR PRAKRUTHI

Registration approved No litigation declared Residential/Group Housing project

SHIVAGANGA AR PRAKRUTHI

By M/s. Prakruthi Properties

RG-KA-66503 · RERA PRM/KA/RERA/1251/310/PR/090523/005917 · Last updated on RERA Karnataka portal: 24 Apr 2023

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Sep 2025Possession promisedno revision filed
0Complaints at RERA Karnatakaon this registration
Jump to the 182 documents Report an error

SHIVAGANGA AR PRAKRUTHI is a Residential/Group Housing project by M/s. Prakruthi Properties in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/090523/005917 on 9 May 2023. Possession is promised by 30 Sep 2025.

At a glance

Project

  • NameSHIVAGANGA AR PRAKRUTHI
  • TypeResidential/Group Housing
  • Location
    • Bengaluru South
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/310/PR/090523/005917
  • ReraGenie IDRG-KA-66503

Builder

  • NameM/s. Prakruthi Properties
  • Entity typePartnership Firm
  • GSTIN29AAQFP6022K1ZQ
  • Authorized SignatoryC S NIRANJAN KUMAR

Key dates

this monthRegisteredMay 2023PromisedSep 2025

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on9 May 2023
  • Promised completion30 Sep 2025
  • Revised completionNone
  • Buildings1 building record
  • Documents filed182 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SHIVAGANGA AR PRAKRUTHI---1200120

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 24 Apr 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Upto Plinth Level-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
Retaining wall (All types)Not applicable
RCC or MS Framed structure-
Masonry Construction-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Painting-
Fire prevention and fire fighting fitting and fixture with network-
Weather Proof work(tile,concrete)-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work-
Internal and External work including landscapes as per sanctioned drawings-

Progress on shared amenities40

As on 24 Apr 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Sewage and Drainage SystemYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
Energy managementYes-
Fire protection and fire safety requirementsYes-
Solid waste management and disposalNoNot applicable
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsYes-
Electricity supply transformer and substationYes-
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes-
Parks & Tree plantingYes-
Street LightingYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseYes-
Community HallYes-
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolYes-
GymYes-
ParksNoNot applicable
Power BackupYes-
Piped GasYes-
Water and SanitationYes-
Air ConditioningNoNot applicable
StaircasesYes-
LiftsYes-
Corridor/LobbiesYes-
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areasYes-
Provision for lodging of management staff and security staffYes-
Water conservation and renewable energyNoNot applicable
Common storage spacesYes-

Land and ownership5

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Named landowners5
LandownerVillageDistrict
Mr. M. Govardhan--
D SUJATHA--
M PRASANNA KUMAR--
V. SOMASHEKAR--
ANJANAPPA V--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 50.76 cr
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 45.93 cr-
Administrative CostRs 4.31 cr-
Architects, Engineer, Consultants Fee etcRs 52.00 lakh-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAMRITA SURESH SHENOI
EngineerCHETHAN A S
Chartered AccountantM SAIGANESH

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed182

As listed on the registration, under the names the promoter filed them with; the newest 80 of 182 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/090523/005917 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Area PlanFile: Plan Copy.pdf24 Apr 2023
Proforma of Agreement for SaleFile: Agreement of Sale Proforma.pdf24 Apr 2023
Jayachandra M R - Net Worth Statement, ITR and Bank StatementFile: Jayachandra M R.pdf24 Apr 2023
Ravishankar L R - Net Worth Statement, ITR and Bank StatementFile: Ravishankar L R.pdf24 Apr 2023
Ramesh C - Net Worth Statement, ITR and Bank StatementFile: Ramesh C.pdf24 Apr 2023
Sharath RK - Net Worth Statement, ITR and Bank StatementFile: Sharath RK.pdf24 Apr 2023
Satish Kumar M - Net Worth Statement, ITR and Bank StatementFile: Satish Kumar M.pdf24 Apr 2023
Somashekar V - Net Worth Statement, ITR and Bank StatementFile: Someshekar V.pdf24 Apr 2023
R Srinivas - Net Worth Statement, ITR and Bank StatementFile: R Srinivasa.pdf24 Apr 2023
Kumar T - Net Worth Statement, ITR and Bank StatementFile: Kumar T.pdf24 Apr 2023
C S Niranjan Kumar - Net Worth Statement, ITR and Bank StatementFile: C S Niranjan Kumar.pdf24 Apr 2023
G Jagadeeswar Naidu - Net Worth Statement, ITR and Bank StatementFile: G Jagadeeswar Naidu.pdf24 Apr 2023
Source of Funds & Partners Networth SummaryFile: Source Summary.pdf24 Apr 2023
FY 2019-20 Balance Sheet, Profit and Loss with ScheduleFile: FY 19-20.pdf28 Mar 2023
FY 2020-21 Balance Sheet, Profit and Loss with ScheduleFile: FY 20-21.pdf28 Mar 2023
FY 2021-22 Balance Sheet, Profit and Loss with ScheduleFile: FY 21-22.pdf28 Mar 2023
Allotmment LetterFile: Model form of Allotment Letter.pdf28 Mar 2023
Agreement of SaleFile: Agreement of Sale Proforma.pdf28 Mar 2023
BBMP Sanction Plan CopyFile: Plan Copy.pdf28 Mar 2023
Area Plan of projectFile: Working Plan.pdf28 Mar 2023
Endorsement given by BBMPFile: dmd_BBMP_EoDB_CH_21711_21-22.pdf28 Mar 2023
ITR Copies FY 2019-20File: ITR FY 19-20.pdf9 Mar 2023
ITR Copies FY 2020-21File: ITR FY 20-21.pdf9 Mar 2023
ITR Copies FY 2021-22File: ITR FY 21-22.pdf9 Mar 2023
Project Area PlanFile: Working Plan.pdf9 Mar 2023
Source of Funds with Net worth Statement of All PartnersFile: Source of Funds with Net Worth.pdf9 Mar 2023
Ground and Typical Floor plans with Signed by DSCFile: Plan Copy.pdf9 Mar 2023
Proforma of Allotment letter in the prescribed formatFile: Model form of allotment letter.pdf9 Mar 2023
Proforma agreement for saleFile: Agreement of Sale Proforma.pdf9 Mar 2023
P & L -2019-20File: P & L 19-20.pdf24 Feb 2023
P & L -2020-21File: P & L 20-21.pdf24 Feb 2023
P & L -2021-22File: P & L 21-22.pdf24 Feb 2023
Balance Sheet - 2019-20File: Balance sheet-19-20.pdf24 Feb 2023
Balance Sheet - 2020-21File: Balance sheet-20-21.pdf24 Feb 2023
Balance Sheet - 2021-22File: Balance sheet-21-22.pdf24 Feb 2023
MR - Sy.No.19-3File: MR Sy No19-3.pdf24 Feb 2023
MR - Sy.No.20-4 & 20-5File: MR - Sy No 20-4 & 20-5.jpg24 Feb 2023
Area PlanFile: Working Plan.pdf24 Feb 2023
Source of FundsFile: Source of Fund.pdf24 Feb 2023
Betterment, Conversion, AmalgamationFile: Betterment, Conversion, Amalgamation.pdf24 Feb 2023
Title deed of Sy.No.20-4 & 20-5File: Title deed of Sy No 20-4 & 20-5-compressed.pdf24 Feb 2023
Encumbrance CertificateFile: EC.pdf24 Feb 2023
CDP - ArehalliFile: CDP - Arehalli.jpg24 Feb 2023
Village MapFile: Village Map.jpg24 Feb 2023
Amalgamation DeedFile: Amalgamation Deed.pdf24 Feb 2023
KSPCB NOCFile: 12 KSPCB NOC.pdf24 Feb 2023
Demarked the Proposed site in the Village MapFile: Village Map.jpg24 Feb 2023
Building LicenseFile: Building License.pdf24 Feb 2023
Section PlanFile: Section Plan.pdf24 Feb 2023
Approved PlanFile: Plan Copy.PDF24 Feb 2023
BWSSB - ReciptFile: 21 Bwssb-Recipt.pdf24 Feb 2023
Engineer CertificateFile: 22 Engineer certificate.pdf24 Feb 2023
Allotment LetterFile: Allotment letter .pdf24 Feb 2023
Proforma of AFSFile: Proforma of AFS.pdf24 Feb 2023
Car parking DetailsFile: Car parking details.PNG24 Feb 2023
Betterment charges paid towards Sy.Nos.20/4 & 20/5File: Betterment charge- Anjanappa.jpeg24 Feb 2023
Estimation CopyFile: 24 Estimate copy.pdf24 Feb 2023
Stability CertificateFile: 23 Stability Certificate.pdf24 Feb 2023
Form Reg 1 CAFile: 20 Form Reg 1 CA.pdf24 Feb 2023
Floor PlanFile: 15 Floor Plan.PDF24 Feb 2023
Reply to queryFile: Reply to query.pdf24 Feb 2023
AffidavitFile: Affidavit.pdf24 Feb 2023
RTC, survey 19/1-
Mutation, survey 19/1-
Encumbrance Certificate, survey 19/1-
Conversion/Alienation Order, survey 19/1-
JDA, survey 19/1-
Khatha, survey 19/1-
RTC, survey 19/2-
Mutation, survey 19/2-
Encumbrance Certificate, survey 19/2-
Conversion/Alienation Order, survey 19/2-
Sale/Title/Gift Deed, survey 19/2-
JDA, survey 19/2-
Khatha, survey 19/2-
RTC, survey 19/3-
Mutation, survey 19/3-
Encumbrance Certificate, survey 19/3-
Conversion/Alienation Order, survey 19/3-
Sale/Title/Gift Deed, survey 19/3-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep SHIVAGANGA AR PRAKRUTHI on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: M/s. Prakruthi Properties

M/s. Prakruthi Properties has 1 registration on RERA Karnataka, including SHIVAGANGA AR PRAKRUTHI. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if SHIVAGANGA AR PRAKRUTHI is delayed beyond 30 Sep 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of SHIVAGANGA AR PRAKRUTHI?

The registered promoter entity is M/s. Prakruthi Properties, a partnership firm as per the filing. Its GSTIN 29AAQFP6022K1ZQ can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in SHIVAGANGA AR PRAKRUTHI?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SHIVAGANGA AR PRAKRUTHI?

The professionals named in the filing: Architect: AMRITA SURESH SHENOI; Engineer: CHETHAN A S; Chartered Accountant: M SAIGANESH. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHIVAGANGA AR PRAKRUTHI?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHIVAGANGA AR PRAKRUTHI. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHIVAGANGA AR PRAKRUTHI to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.