Home / Browse projects / Thane, Maharashtra / Shiv Shahi Complex Phase II

Registered No litigation declared Residential / Group Housing project

Shiv Shahi Complex Phase II

By Shalini Shivaji Pawar

RG-MH-96133 · RERA P51700017015 · Last updated on MahaRERA portal: 27 Mar 2025

Source: official MahaRERA filing

Red flags

  • Completion date moved by 87 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Mar 2030Possession promisedmoved 87 months from the original
0 of 22Construction stages doneacross 2 buildings; furthest along: Excavation, 50%
0Complaints at MahaRERAon this registration
Jump to the 144 documents Report an error

Shiv Shahi Complex Phase II is a Residential / Group Housing project by Shalini Shivaji Pawar in Thane, Maharashtra, registered with MahaRERA as P51700017015 on 4 Jul 2018. Possession is promised by 31 Mar 2030. The completion date has moved by 87 months from the original filing.

At a glance

Project

  • NameShiv Shahi Complex Phase II
  • TypeResidential / Group Housing
  • Location
    • Narayangaon
    • Murbad
    • Thane
    • 421401
  • Pincode421401
  • RERA no.P51700017015
  • ReraGenie IDRG-MH-96133

Builder

  • NameShalini Shivaji Pawar
  • Entity typeIndividual
  • Other registrations1 more →
  • No longer live1 lapsed, de-registered or revoked

Key dates

this monthRegisteredJul 2018First promiseDec 2022Revised toMar 2030

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on4 Jul 2018
  • Promised completion31 Mar 2030
  • Revised completionRevised to 31 Mar 2030 (originally 30 Dec 2022)
  • Buildings2 building records
  • Documents filed144 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building ANA100000
Building BNA100000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 27 Mar 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Excavation, at 50%.

Building A5%
ActivityProgress
Excavation50%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Building B0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 27 Mar 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed368

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots368
Closed/Covered123
Open Space245
BuildingClosed/CoveredOpen SpaceTotal
Building A61123184
Building B62122184

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,330 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI12423.1
Proposed, not sanctioned12,423 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchOffice No 1, Stellar Tower, Opp K Starmall Sion-Trombay road, Chembur West, Mumbai 400071

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectShailaja Vaidya
PartnerRole in project
Shalini Shivaji Pawar-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700027742Dec 2022 → Mar 2030

Reason as filed by the promoterThe Project was kept on hold due to reason of COVID and other project completion. The Promoter wishes to restart the project and hence extension application is sought before your Lordships.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jun 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 25 Mar 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 18 Mar 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 25 Mar 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Mar 2030

Documents filed144

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 144 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 1 FORM 1 Q3 DEC 2024.pdf27 Mar 2025
Certificates of CA (Form 3)File: 3 Form 3 Dec.pdf27 Mar 2025
Certificates of CA (Form 3)File: 3 Form 3 Dec 2024.pdf27 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 2 Form 2 31-12-2024.pdf27 Mar 2025
Disclosure of sold/ booked inventoryFile: 4 Disc of Sales - B Q3.pdf27 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A.pdf27 Mar 2025
Layout approvalFile: Building Plan B Building_11zon.pdf25 Mar 2025
Layout approvalFile: Building Plan E Building_11zon.pdf25 Mar 2025
Copy of Layout Approval (in case of layout)File: Building Plan E Building_11zon.pdf25 Mar 2025
Copy of Layout Approval (in case of layout)File: Building Plan B Building_11zon.pdf25 Mar 2025
Certificates of CA (Form 3)File: 3 Form 3 June 2024.pdf25 Mar 2025
Certificates of CA (Form 3)File: 3 Form 3 Sep 2024.pdf25 Mar 2025
Certificates of CA (Form 3)File: 3 Form 3 Dec.pdf25 Mar 2025
Certificates of CA (Form 3)File: 3 Form 3 June 2024.pdf25 Mar 2025
Certificates of CA (Form 3)File: 3 Form 3 Sep 2024.pdf25 Mar 2025
Certificates of CA (Form 3)File: 3 Form 3 Dec.pdf25 Mar 2025
Commencement Certificates / NA Order for plotted developmentFile: New CC_11zon.pdf25 Mar 2025
Declaration about Commencement CertificateFile: Declaration of CC.pdf25 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 Certificate - FY 23-24.pdf25 Mar 2025
Certificates of CA (Form 3)File: 3 Form 3 Dec.pdf24 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Form 5 Certificate - FY 18-19.pdf24 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 04-01-2025_11zon (2).pdf24 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 Certificate - FY 18-19.pdf24 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 Certificate - FY 19-20.pdf24 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 Certificate - FY 20-21.pdf24 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 Certificate - FY 22-23.pdf24 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 Certificate - FY 23-24.pdf24 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 04-10-2024_11zon.pdf21 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 2 04-01-2020.pdf21 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 04-07-2024_11zon.pdf21 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 04-01-2025_11zon (2).pdf21 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 2 04-10-2023_11zon.pdf21 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 2 04-07-2023_11zon.pdf21 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 2 04-04-2024_11zon.pdf21 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 2 04-01-2024_11zon.pdf21 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 2 04-10-2022.pdf21 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 2 04-01-2023.pdf21 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 2 04-10-2021.pdf21 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 2 04-04-2022.pdf21 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 2 04-01-2022.pdf21 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 2 04-10-2020.pdf21 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 2 04-07-2020.pdf21 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 2 04-04-2021.pdf21 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 2 04-01-2021.pdf21 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 2 04-10-2019.pdf21 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 2 04-07-2019.pdf21 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 2 04-04-2020.pdf21 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 2 04-04-2019.pdf21 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 2 04-07-2021.pdf21 Mar 2025
Other - TechnicalFile: PERT Building B.pdf21 Mar 2025
Other - TechnicalFile: PERT Building E.pdf21 Mar 2025
Other - TechnicalFile: Reason for Project Completion.pdf21 Mar 2025
Other - TechnicalFile: Reason for Project Completion.pdf21 Mar 2025
Building plan approvalFile: Building Plan B Building_11zon.pdf18 Mar 2025
Building plan approvalFile: Building Plan E Building_11zon.pdf18 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 1 FORM 1 Q1 2019 June.pdf18 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 1 FORM 1 Q4 2018.pdf18 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 1 FORM 1 Q3 DEC 2024.pdf18 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 1 FORM 1 Q2 SEP 2024.pdf18 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 1 FORM 1 Q1 June 2024.pdf18 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 1 Form 1 Q4 2023.pdf18 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 1 FORM 1 Q3 Dec 2023.pdf18 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 1 FORM 1 Q2 Sep 2023.pdf18 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 1 FORM 1 Q1 June 2023.pdf18 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 1 FORM 1 Q4 2022 March.pdf18 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 1 FORM 1 Q3 2022 Dec.pdf18 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 1 FORM 1 Q2 2022 Sep.pdf18 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 1 FORM 1 Q1 2022 June.pdf18 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 1 FORM 1 Q4 2021 March.pdf18 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 1 FORM 1 Q3 2021 Dec.pdf18 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 1 FORM 1 Q2 2021 Sep.pdf18 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 1 FORM 1 Q1 2021 June.pdf18 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 1 FORM 1 Q4 2020 March.pdf18 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 1 FORM 1 Q3 2020 Dec.pdf18 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 1 FORM 1 Q2 2020 Sep.pdf18 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 1 FORM 1 Q1 2020 June.pdf18 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 1 FORM 1 Q4 2019 March.pdf18 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 1 FORM 1 Q3 2019 Dec.pdf18 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 1 FORM 1 Q2 2019 Sep.pdf18 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 1 FORM 1 Q1 2022 June.pdf18 Mar 2025

How this compares with Thane

24%of Thane projects moved their completion datethis one moved by 87 months
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Shiv Shahi Complex Phase II on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Murbad7,600+ in Thane

Builder: Shalini Shivaji Pawar

Shalini Shivaji Pawar has 2 registrations on MahaRERA, including Shiv Shahi Complex and Shiv Shahi Complex Phase II. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if Shiv Shahi Complex Phase II is delayed beyond 31 Mar 2030?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Shiv Shahi Complex Phase II?

The registered promoter entity is Shalini Shivaji Pawar, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Shiv Shahi Complex Phase II?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Shiv Shahi Complex Phase II?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Shiv Shahi Complex Phase II?

The professionals named in the filing: Architect: Shailaja Vaidya. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Shiv Shahi Complex Phase II?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Shiv Shahi Complex Phase II. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Shiv Shahi Complex Phase II to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.